Calcutta High Court
Mina Begum vs The Kolkata Port Trust And Another on 7 January, 2021 In The High Court at Calcutta
Constitutional Writ Jurisdiction
Original Side

The Hon’ble Justice Sabyasachi Bhattacharyya

W.P.O. No. 466 of 2019
Mina Begum, Proprietor of M/s M N Sultana Enterprise
Vs.
The Kolkata Port Trust and another

With

W.P.O. No. 559 of 2019
Mina Begum, Proprietor of M/s M N Sultana Enterprise
Vs.
The Kolkata Port Trust and others

For the petitioner : Mr. Debasish Banerjee, Sr. Advocate,
Mr. S. Naskar

For the respondents : Mr. Prabal Kr. Mukherjee, Sr. Advocate
Mr. A.K. Jena

Hearing concluded on : 18.12.2020

Judgment on : 07.01.2021

The Court:

1. The writ petitions, bearing W.P.O. No. 466 of 2019 and W.P.O. No.

559 of 2019, are taken up for hearing together, since the cause of

action for both arise from the same sequence of events.

2. The petitioner is the sole proprietor of the firm M/s M N Sultana

Enterprise, which succeeded in an e-tender floated by the Kolkata Port

Trust (KoPT) on September 18, 2017 and was issued a work order,

bearing No. KOPT/KDS/CIV/T/2170/1877, on December 6, 2017 for

upkeep of certain offices of the KoPT (respondent no.1) and providing
2

semi-skilled/unskilled labourers with necessary tools and tackles for

miscellaneous works at different locations for two years.

3. On March 20, 2019, the Superintending Engineer (Kolkata), Civil

Engineering Department, KoPT (respondent no. 2) issued a letter to

the petitioner’s firm and another concern, intimating that Register for

Payment of Contractor’s Employees was required to be produced at

the time of processing the bill for the work for a certain period and

requesting the two concerns to strictly follow all the contractual

clauses of the subject contract and KoPT General Conditions of

Contract (GCC), including the Payment of Wages Act, 1936, to abide

by the provisions of the Payment of Bonus Act, 1965 in respect of

bonus to their employees and to ensure timely payments to the

labourers/employees involved. The petitioner replied in writing on

March 26, 2019, alleging that departmental officers of the KoPT do not

accept payments of ESI, EPF, etc. made by the petitioner and asking

for a cost analysis or break-up of the rate of such payments against

each worker. However, vide letter dated April 10, 2019, respondent no.

2 reiterated his previous stand.

4. On August 8, 2019, the petitioner wrote another letter to respondent

no. 2, expressing her inability to pay wages to the labourers and

deposit EPF and ESI timely due to the petitioner’s allegedly miserable

financial condition. The petitioner also asked for clearance of the

arrears due to the petitioner from respondent no. 1. The petitioner

repeated a similar request vide her letter dated August 29, 2019.
3

5. Vide notice no. C/2175/382 dated September 2, 2019, respondent no.

2 warned the petitioner of termination of the subject contract if the

petitioner failed to regularise all previous dues within seven working

days, in which case the balance work would be carried out by

engaging another agency at “Risk & Cost” of the subject contract.

6. The petitioner has preferred W.P.O. No. 466 of 2019 against the said

notice dated September 2, 2019. A co-ordinate Bench, vide Order

dated September 24, 2019, directed the petitioner to meet respondent

no. 2 on September 26, 2019 at 11 a.m. in the office of the respondent

no. 2 with all documentary evidence of compliance of the labour laws

along with the bills for the months subsequent to April, 2019.

Respondent no. 2 was to prepare a report, detailing the documents

provided by the petitioner, and would be at liberty to look into the

earlier bills of the petitioner, affording the petitioner an opportunity to

produce any other document that he deemed appropriate.

7. The Chief Engineer, Civil Engineering Department, KoPT issued a

further notice, bearing No. Civ/2175/2243, on October 14, 2019,

giving the petitioner’s proprietorship firm three working days to

comply and complete the firm’s tender obligations including clearing

of all dues, failing which the tender contract would be terminated as

per Clause 8.3 of the GCC. It was alleged that the firm’s dues

remained unpaid and that it was in gross violation of terms of contract

with regard to ESI, EPT, EPS, EDLI etc. The petitioner issued an

advocate’s letter in reply on October 19, 2019, citing the pendency of

W.P.O. No. 466 of 2019, alleging that no report had been filed by the
4

Chief Engineer, Civil Engineering Department of the KoPT and that

due payments of the petitioner of about Rs. 8 lakh for work done

under the work order dated December 6, 2017 were withheld.

8. Vide notice no. C/2175/440 dated October 28, 2019, the Chief

Engineer, KoPT terminated the contract with the petitioner’s firm by

invoking Clause 8.3 of the GCC for non-compliance of its tender

obligations including clearing all dues with regard to ESI, EPF, EPS,

EDLI, etc. within three working days from the notice dated October

14, 2019. It was further mentioned that the subject work would be

done through some other agency at the ‘Risk and Cost’ of the

petitioner’s firm.

9. Challenging both the above notices, dated October 14, 2019 and

October 28, 2019 respectively, the petitioner has preferred W.P.O. No.

559 of 2019.

10. Learned counsel for the petitioner submits that termination of the

contract between the parties could only occur under Clause 8.3 of the

GCC. Since none of the grounds stipulated therein is satisfied in the

present case, the termination of the contract is invalid. That apart, the

three days’ prior notice as envisaged therein was absent, which also

invalidates the termination.

11. By placing reliance on Section 21 of the Contract Labour (Regulation

and Abolition) Act, 1970 (hereinafter referred to as “the 1970 Act”),

Section 8-A of the Employees’ Provident Funds and Miscellaneous

Provisions Act, 1952 (hereinafter referred to as “the 1952 Act”) and

Sections 39, 40 and 41 of the Employees’ State Insurance Act, 1948
5

(hereinafter referred to as “the 1948 Act”), learned counsel for the

petitioner argues that, in case of non-deposit of contributions under

the said Acts by the contractor/immediate employer, the

employer/principal employer (as the case may be) has a remedy in

paying such amounts in the first instance and subsequently

recovering the dues from the contractor/immediate employer. Hence,

the termination of the contract of the KoPT with the petitioner’s firm

on such ground was de hors the law.

12. The petitioner further contends that the petitioner had categorically

raised a dispute, on several occasions, over the actual dues payable

by the petitioner’s firm under the relevant labour laws. The petitioner

has claimed during the relevant juncture that her firm overpaid its

dues and that respondent no. 1 was claiming exorbitant and arbitrary

amounts from the firm, exceeding the amount which the firm could be

legally charged with. Termination of the contract without resolution of

such dispute was illegal. It is contended that the petitioner had

already paid more than its dues and, thus, there was no reason for

termination of the contract.

13. Learned counsel for the petitioner cites Union of India and others v.

Tantia Construction Private Limited, reported at (2011) 5 SCC 697, for

the proposition that, even on the question of maintainability of a writ

petition on account of the arbitration clause included in the

agreement between the parties, it is now well established that an

alternative remedy is not an absolute bar to the invocation of the writ

jurisdiction of the High Court or the Supreme Court and that without
6

exhausting such alternative remedy, a writ petition would not be

maintainable. The constitutional powers vested in the said courts

cannot be fettered by any alternative remedy and injustice, whenever

and wherever it takes place, has to be struck down as an anathema to

the rule of law and the provisions of the Constitution. Although, in the

present case, Clause 10.3 of the GCC provides for arbitration, the

same is not an absolute bar to the writ jurisdiction of this court.

Moreover, it is submitted, Clause 10.3 could only become operative

once the remedy in Clause 10.2 of the GCC was exhausted, which did

not happen in the present case.

14. Learned senior counsel appearing for the respondents, on the other

hand, argues that the present writ petitions arise from a contractual

dispute, a decision on which is beyond the domain of the writ court.

Moreover, in view of Clauses 10.2 and 10.3 of the GCC, the petitioner

had to require the matter to be referred to the Chairman within 15

days after receiving notice of the Engineer. If the petitioner was

aggrieved by the decision given by the Chairman on such reference,

the petitioner’s remedy lay in requiring, within 15 days after receiving

notice of such decision, reference to arbitration by the Chairman

within 60 days from the petitioner’s written notice. Since the

petitioner did not exhaust such remedy, the writ court ought not to

entertain the writ petitions.

15. In this context, counsel relies upon Harbanslal Sahnia and another v.

Indian Oil Corpn. Ltd. and others, reported at (2003) 2 SCC 107,

wherein the Supreme Court laid down contingencies in which the
7

High Court may still exercise its writ jurisdiction despite the

availability of an alternative remedy – where the writ petition seeks

enforcement of any of the fundamental rights, where there is failure of

principles of natural justice or where the orders or proceedings are

wholly without jurisdiction or the vires of an Act is challenged.

16. Learned senior counsel for the respondents next cites State of Kerala

and others v. M.K. Jose [(2015) 9 SCC 433] in support of the

proposition that a writ court should ordinarily not entertain a writ

petition if there is a breach of contract involving disputed questions of

fact.

17. Counsel next relies on M/s E.C. Bose & Co. Pvt. Ltd. V. The Board of

Trustees for the Port of Kolkata & Ors., reported at (2016) 3 CHN 280,

to contend that a Division Bench of this court had, in the said case,

held that a writ complaining of the illegality of termination of a

contract by the KoPT was not a fit case where extraordinary

jurisdiction by issuing prerogative writ could be exercised since such

adjudication had to be done by leading evidence, etc. The court also

took note of the fact that an arbitration reference was also envisaged

as adjudication process as per the terms of the contract in the said

case.

18. Thus, it is argued by the respondents that the writ petitions ought to

be dismissed as not maintainable.

19. Learned senior counsel for the respondents further contends that,

admittedly, the petitioner’s firm had been depositing its dues on the

count of contributions under the 1970 Act, the 1952 Act and the 1948
8

Act all along at the stipulated rates. However, subsequently the firm

stopped depositing such dues and even withheld wages of the

labourers on the pretext of having raised a dispute regarding the rates

of its contributions. In fact, the petitioner admitted the inability of her

firm to make payments/deposits due to alleged financial distress.

Hence, it is submitted, the said dispute is a mere excuse for not

making deposits as contemplated in law and in the contract.

20. Referring to Clause 8.3 (v) of the GCC, learned senior counsel submits

that the firm of the petitioner was squarely covered by the said

provision, since it was not executing the works in accordance with the

contract and persistently and flagrantly neglected to carry out its

obligations under the contract.

21. Clause 4.18 (d) of the GCC includes payment for the statutory benefits

of all labourers and workers by the contractor, while Clause 4.1

mandates that the contract shall be governed by all relevant Indian

Acts, including the 1970 Act. Clauses 35 and 36 of the NIT require the

contractor to comply with labour laws, including the 1970 Act, the

1952 Act and the 1948 Act. These contractual obligations were flouted

by the petitioner’s firm despite several reminders, exposing its

contract to termination under Clause 8.3 (v) of the GCC.

22. Learned senior counsel for the respondents lastly submits that one

Arif Ahmed Shek, who is the vice-president of the trade union which

lodged complaint against the contractor, that is, the petitioner’s firm

(as evident from the workmen’s complaint against the contractor, a

copy of which has been annexed at page 91 of the respondents’
9

affidavit-in-opposition to W.P.O. No. 559 of 2019), also affirmed the

affidavits-in-reply in both the current writ petitions as authorised

representative of the contractor. This, by itself, shows the collusive

conduct of the petitioner, it is submitted, entailing dismissal of the

writ petitions since the writ petitioner has not come with clean hands.

23. Addressing the question of maintainability first, it is nobody’s case

that the availability of alternative remedy is an absolute bar, even in

case of contractual and arbitrable disputes. Tantia Constructions

(supra), cited by the petitioner, lays down that even when an

arbitration clause exists, such alternative remedy is not an absolute

bar to the invocation of the writ jurisdiction. The constitutional

powers vested in the High Court or the Supreme Court, it was

observed in the report, cannot be fettered by any alternative remedy.

Injustice, it was held, whenever and wherever it takes place, has to be

struck down as an anathema to the rule of law and the provisions of

the Constitution.

24. M.K. Jose (supra), relied on by the respondents, observes that a writ

court should not “ordinarily” entertain a writ petition, if there is a

breach of contract “involving disputed questions of fact”.

25. The Supreme Court, in Harbanslal Sahnia (supra), relies on Whirlpool

Corporation [(1998) 8 SCC 1] holds that, in an appropriate case, in

spite of availability of alternative remedy, the High Court may still

exercise its writ jurisdiction in “at least” three contingencies, being

enforcement of a fundamental right, failure of principles of natural

justice and where the orders or proceedings are wholly without
10

jurisdiction or the vires of an Act is challenged. In the said report, it is

observed that the rule of exclusion of writ jurisdiction by availability of

an alternative remedy is a “rule of discretion and not one of

compulsion”.

26. In M/s E.C. Bose & Co. (supra), the Division Bench of this court did

not specifically hold that an arbitration clause debars the writ

jurisdiction. The argument regarding existence of such a clause, made

by a party, was merely recorded. The basis of refusing to entertain the

writ petition was that the adjudication involved would require

evidence to be led and a detailed analysis of the facts and provisions

of the contract. The report, ipso facto, does not lay down an absolute

bar to the writ jurisdiction in either arbitrable or contractual disputes.

27. The writ jurisdiction is wide enough to interdict in case of patent

injustice, more so by the State and its instrumentalities, which are

public functionaries and, thus, are on an elevated level of obligations

to adhere to law and natural justice than a mere individual. Even if

the genesis of the dispute is contract, the nature of the present

contract belongs to the public law domain, since the contractor was

issued a work order to discharge public duties as the agent of the

KoPT (itself a public body).

28. However, the scope of the writ jurisdiction has to be filtered through

the prism of self-imposed restrictions of the High Court. It has to be

examined whether, in particular case, there has been a violation of a

fundamental/statutory right, failure of the principles of natural
11

justice, patent lack of jurisdiction or gross abuse of the process of law,

to justify interference.

29. As such, the writ petitioner cannot be shut out at the outset on the

ground of non-maintainability, without looking into the nature and

gravity of the dispute raised.

30. Clause 10.1 of the GCC contemplates disputes arising out of or

connected with the interpretation of the contract and provides that

abandonment or breach of the contract shall be subject to the

decision of the Engineer. Clause 10.2 contemplates a reference to the

Chairman against the Engineer’s decision, upon such requirement

being made by the aggrieved contractor within 15 days from notice of

the Engineer’s decision. Clause 10.3 stipulates that if the contractor is

still dissatisfied with the Chairman’s decision, he shall, within 15 days

after receiving notice of the decision, require that, within 60 days from

his written notice, the Chairman shall refer the matter to an arbitrator

of the panel of arbitrators to be maintained by the Trustees for the

purpose.

31. In the present case, the petitioner bye-passed the procedure laid down

in Clause 10 and preferred the present writ petitions directly. Such

action could only be justified if there was a patent violation of

fundamental/statutory rights or of principles of natural justice and/or

any mala fide or arbitrary action on the part of the respondents

amounting to gross miscarriage of justice.

32. Termination of a contract, in the present context, comes within the

ambit of Clause 8.3 of the GCC. The said Clause provides that,
12

without being liable for any compensation to the contractor, the

Trustees may, in their absolute discretion, terminate the contract and

enter upon the site and works and expel the contractor therefrom

after giving him a minimum 3 days’ notice in writing, on the

occurrence of any of the situations contemplated in the clause .

33. Sub-clause (v) of Clause 8.3 sets out, as a ground for termination, the

contractor not executing the works in accordance with the contract or

persistently or flagrantly neglecting to carry out his obligations under

the contract. This is the only ground which can argued to be attracted

to the present case. The other grounds, as stipulated in Clause 8.3,

are on a different footing and are irrelevant for the present purpose.

34. To understand the expressions “in accordance with the contract” and

“obligations under the contract”, as appearing in Clause 8.3(v) of the

GCC, the other relevant portions of the GCC and the tender document

are to be examined.

35. Clause 4.18 (d) of the GCC stipulates that the contractor’s quoted

rates shall be deemed to be inclusive of, inter alia, making

arrangement for payment of the wages and statutory benefits of the

labourers and workers.

36. Apart from the general Clauses of the GCC, the NIT ought also to be

looked into, in order to grasp the entire conspectus of the contractor’s

obligations as per the tender. Clause 35 of the concerned NIT dated

September 18, 2017 provides that the contractor shall be required to

comply with the Minimum Wages Act, 1948, Employees’ Liability Act,
13

1938, the Industrial Disputes Act, 1947 and the Contract Labour

(Regulation and Abolition) Act, 1970.

37. Clause 36 of the NIT mandates that the successful contractor will

have to comply with the provisions of the 1952 Act and the 1948 Act.

38. Clause 37 of the NIT provides that the successful bidder shall be

deemed to indemnify and keep indemnified the Trustees from and

against all actions, claims, demands and liabilities under and in

respect of breach of any of the provisions of any Law, Rules or

Regulations having the force of law, including but not limited to the

statutes named thereafter. Such statutes include the 1948 Act, the

1970 Act as well as the 1952 Act.

39. Even Clause 4.1(b) of the GCC provides that the contract shall be

governed by all relevant Indian Acts, including the Acts mentioned

therein, which specifically include the 1970 Act.

40. A composite reading of all the aforesaid clauses indicates clearly that

it was the duty of the contractor to comply with all provisions under

the 1970 Act, 1952 Act and the 1948 Act (apart from other statutes)

and to keep the Trustees indemnified against breach of the provisions

of the said Acts. Thus, the expressions “in accordance with the

contract” and “obligations under the contract” as envisaged in Clause

8.3(v) clearly include the compliance with provisions of the aforesaid

Acts within the scope of contractual obligations.

41. The arguments of the petitioner, based on Section 21 of the 1970 Act,

Section 8-A of the 1952 Act and Sections 39, 40 and 41 of the 1948

Act, as regards the remedy of the employer/principal employer lying
14

merely in recovery, is on unsound footing. Recovery is only one of the

remedies, provided statutorily; however, the existence of such remedy

is in addition to the contractual obligations of the

contractor/immediate employer (in the present case, the petitioner).

Such remedies, operate in different fields and do not mutually exclude

each other. Thus, the respondents did not exceed their jurisdiction in

terminating the contract under Clause 8.3(v) of the GCC.

42. The contractual obligations of the petitioner’s firm, in the context of

the present case, were forged into statutory obligations and it is

impossible to distinguish between the statutory and contractual

ingredients of such obligations. As such, a violation of the respective

statutes would simultaneously constitute a breach of the contractual

obligations of the firm as well.

43. Admittedly, the petitioner has been depositing her dues of

contributions under the 1952 Act, the 1970 Act and the 1948 Act,

without raising any objection thereto.

44. About contemporaneously with the failure of the petitioner to pay

wages and deposit statutory contributions of the labourers, the

petitioner raised certain ‘disputes’ with regard to the rates of the

petitioner’s contribution.

45. Such action, on the face of it, indicates ethical dishonesty on the part

of the petitioner. The petitioner, on the one hand, admitted in multiple

correspondence as to her inability to pay/deposit the wages and

statutory dues in time on the ground of financial hardship and, on the

other, asked for disbursal of her dues. The petitioner further added
15

the ‘windmill’ (courtesy: Orwell in Animal Farm) of bogey disputes, to

shift the focus from her defaults.

46. It must be made clear that, whatever disputes the petitioner might

have regarding overpayment and/or rate of deposits, the petitioner

cannot avoid her statutory liabilities, merged into her contractual

liabilities as it stands, on such pretext. Such disputes, if any, and the

obligations are independent phenomena and cannot be interlinked to

create confusion.

47. In the event the petitioner had any complaint regarding rates of

deposit and overpayments, which broadly pertain to the interpretation

of the contractual clauses, the petitioner ought to have taken up the

issue in consonance with Clause 10.2 and, if necessary Clause 10.3

thereafter, as per contemplation in the GCC. Having failed to do so

within the respective periods stipulated in Clause 10.2 and Clause

10.3, the petitioner cannot seek such monetary relief on the ground of

arrear dues to her in the garb of the writ petition, nor hold out such

dispute/objection as a defence for non-compliance of her statutory

obligations.

48. The disputes regarding alleged overpayment and rates of deposit are

between the firm of the petitioner and the respondents. However, the

default of the petitioner in depositing the statutory dues in compliance

with the labour laws directly affects the labourers and their livelihood.

That apart, the petitioner has been deducting the statutory

contributions from the employees on the one hand and desisting from
16

depositing such amount with the respondents, thereby unduly

enriching herself de hors the law.

49. The petitioner not only withheld statutory contributions in respect of

the employees but also defaulted in payment of wages, both of which

acts were in direct contravention of the contract between the

petitioner’s firm and the respondents, as crystallized by the NIT and

the GCC, as well as the law. Such blatant violation of the statutes and

contract speaks poorly of the conduct and intent of the petitioner. As

such, the petitioner cannot said to have come with clean hands before

this court.

50. It is seen from the records that the order of the co-ordinate Bench

dated September 24, 2019, passed in W.P.O. No.466 of 2019, was

duly complied with by the respondent-authorities and a report was

filed in consonance thereto.

51. Several opportunities over an inordinate period of time were given to

the petitioner to mend her defaults, but the petitioner chose not to do

so on one pretext of the other, sometimes harping on a pseudo-

dispute and at others appealing to the sympathy of the respondents.

In such circumstances, the respondents were absolutely within their

jurisdiction in terminating their contract with the petitioner. Such

termination, as such, was valid both as per the contract and in law.

52. As regards the allegation that Arif Ahmed Shek, the Vice President of

the complainant Trade Union, has himself acted as the authorized

representative of the contractor to affirm the affidavits-in-reply in both

the writ petitions, it is not clear beyond reasonable doubt that the two
17

persons are the same. The letter-head of the concerned Trade Union

displayed the name of Arif Ahmed Shek but does not give out any

further particulars regarding the person, sufficient to tally the identity

of the Vice President with the authorized representative. That apart,

such allegation leads neither here nor there, since the same, if

established, would invalidate not only the affidavits-in-reply of the

petitioner but might also cast doubt on the veracity of the complaint

against the contractor in the first place.

53. In any event, complicity between the leaders of Trade Union and the

immediate employer/principal employer are not unknown to the

Indian polity. However, it would be unnecessary and even improper,

given the paucity of materials, to delve into the question of the

integrity of such Arif Ahmed Shek and the question of complicity, if

any, between the contractor and the labour leaders.

54. Even if there were to be such complicity, a resolution or retribution in

that regard cannot feed the labourers, who are cheated and deprived

due to withholding of the statutory dues by the petitioner. Thus, the

said question is irrelevant for the present context and best left

unanswered in the present writ petitions.

55. Thus, in view of the above discussions, the petitioner has failed to

establish any illegality/irregularity on the part of the respondents in

terminating the contract of the petitioner, after issuing warning to do

so, worth interference by the writ court.

56. Accordingly, W.P.O No.466 of 2019 and W.P.O. No.559 of 2019 are

dismissed on contest.
18

57. The connected pending applications, if any, also stand disposed of

accordingly.

58. There will be no order as to costs.

59. Urgent certified website copies of the order shall be provided to the

parties upon due compliance of all requisite formalities.

( Sabyasachi Bhattacharyya, J. )

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.