Calcutta High Court
Mina Begum vs The Kolkata Port Trust And Another on 7 January, 2021 In The High Court at Calcutta
Constitutional Writ Jurisdiction
Original Side
The Hon’ble Justice Sabyasachi Bhattacharyya
W.P.O. No. 466 of 2019
Mina Begum, Proprietor of M/s M N Sultana Enterprise
Vs.
The Kolkata Port Trust and another
With
W.P.O. No. 559 of 2019
Mina Begum, Proprietor of M/s M N Sultana Enterprise
Vs.
The Kolkata Port Trust and others
For the petitioner : Mr. Debasish Banerjee, Sr. Advocate,
Mr. S. Naskar
For the respondents : Mr. Prabal Kr. Mukherjee, Sr. Advocate
Mr. A.K. Jena
Hearing concluded on : 18.12.2020
Judgment on : 07.01.2021
The Court:
1. The writ petitions, bearing W.P.O. No. 466 of 2019 and W.P.O. No.
559 of 2019, are taken up for hearing together, since the cause of
action for both arise from the same sequence of events.
2. The petitioner is the sole proprietor of the firm M/s M N Sultana
Enterprise, which succeeded in an e-tender floated by the Kolkata Port
Trust (KoPT) on September 18, 2017 and was issued a work order,
bearing No. KOPT/KDS/CIV/T/2170/1877, on December 6, 2017 for
upkeep of certain offices of the KoPT (respondent no.1) and providing
2
semi-skilled/unskilled labourers with necessary tools and tackles for
miscellaneous works at different locations for two years.
3. On March 20, 2019, the Superintending Engineer (Kolkata), Civil
Engineering Department, KoPT (respondent no. 2) issued a letter to
the petitioner’s firm and another concern, intimating that Register for
Payment of Contractor’s Employees was required to be produced at
the time of processing the bill for the work for a certain period and
requesting the two concerns to strictly follow all the contractual
clauses of the subject contract and KoPT General Conditions of
Contract (GCC), including the Payment of Wages Act, 1936, to abide
by the provisions of the Payment of Bonus Act, 1965 in respect of
bonus to their employees and to ensure timely payments to the
labourers/employees involved. The petitioner replied in writing on
March 26, 2019, alleging that departmental officers of the KoPT do not
accept payments of ESI, EPF, etc. made by the petitioner and asking
for a cost analysis or break-up of the rate of such payments against
each worker. However, vide letter dated April 10, 2019, respondent no.
2 reiterated his previous stand.
4. On August 8, 2019, the petitioner wrote another letter to respondent
no. 2, expressing her inability to pay wages to the labourers and
deposit EPF and ESI timely due to the petitioner’s allegedly miserable
financial condition. The petitioner also asked for clearance of the
arrears due to the petitioner from respondent no. 1. The petitioner
repeated a similar request vide her letter dated August 29, 2019.
3
5. Vide notice no. C/2175/382 dated September 2, 2019, respondent no.
2 warned the petitioner of termination of the subject contract if the
petitioner failed to regularise all previous dues within seven working
days, in which case the balance work would be carried out by
engaging another agency at “Risk & Cost” of the subject contract.
6. The petitioner has preferred W.P.O. No. 466 of 2019 against the said
notice dated September 2, 2019. A co-ordinate Bench, vide Order
dated September 24, 2019, directed the petitioner to meet respondent
no. 2 on September 26, 2019 at 11 a.m. in the office of the respondent
no. 2 with all documentary evidence of compliance of the labour laws
along with the bills for the months subsequent to April, 2019.
Respondent no. 2 was to prepare a report, detailing the documents
provided by the petitioner, and would be at liberty to look into the
earlier bills of the petitioner, affording the petitioner an opportunity to
produce any other document that he deemed appropriate.
7. The Chief Engineer, Civil Engineering Department, KoPT issued a
further notice, bearing No. Civ/2175/2243, on October 14, 2019,
giving the petitioner’s proprietorship firm three working days to
comply and complete the firm’s tender obligations including clearing
of all dues, failing which the tender contract would be terminated as
per Clause 8.3 of the GCC. It was alleged that the firm’s dues
remained unpaid and that it was in gross violation of terms of contract
with regard to ESI, EPT, EPS, EDLI etc. The petitioner issued an
advocate’s letter in reply on October 19, 2019, citing the pendency of
W.P.O. No. 466 of 2019, alleging that no report had been filed by the
4
Chief Engineer, Civil Engineering Department of the KoPT and that
due payments of the petitioner of about Rs. 8 lakh for work done
under the work order dated December 6, 2017 were withheld.
8. Vide notice no. C/2175/440 dated October 28, 2019, the Chief
Engineer, KoPT terminated the contract with the petitioner’s firm by
invoking Clause 8.3 of the GCC for non-compliance of its tender
obligations including clearing all dues with regard to ESI, EPF, EPS,
EDLI, etc. within three working days from the notice dated October
14, 2019. It was further mentioned that the subject work would be
done through some other agency at the ‘Risk and Cost’ of the
petitioner’s firm.
9. Challenging both the above notices, dated October 14, 2019 and
October 28, 2019 respectively, the petitioner has preferred W.P.O. No.
559 of 2019.
10. Learned counsel for the petitioner submits that termination of the
contract between the parties could only occur under Clause 8.3 of the
GCC. Since none of the grounds stipulated therein is satisfied in the
present case, the termination of the contract is invalid. That apart, the
three days’ prior notice as envisaged therein was absent, which also
invalidates the termination.
11. By placing reliance on Section 21 of the Contract Labour (Regulation
and Abolition) Act, 1970 (hereinafter referred to as “the 1970 Act”),
Section 8-A of the Employees’ Provident Funds and Miscellaneous
Provisions Act, 1952 (hereinafter referred to as “the 1952 Act”) and
Sections 39, 40 and 41 of the Employees’ State Insurance Act, 1948
5
(hereinafter referred to as “the 1948 Act”), learned counsel for the
petitioner argues that, in case of non-deposit of contributions under
the said Acts by the contractor/immediate employer, the
employer/principal employer (as the case may be) has a remedy in
paying such amounts in the first instance and subsequently
recovering the dues from the contractor/immediate employer. Hence,
the termination of the contract of the KoPT with the petitioner’s firm
on such ground was de hors the law.
12. The petitioner further contends that the petitioner had categorically
raised a dispute, on several occasions, over the actual dues payable
by the petitioner’s firm under the relevant labour laws. The petitioner
has claimed during the relevant juncture that her firm overpaid its
dues and that respondent no. 1 was claiming exorbitant and arbitrary
amounts from the firm, exceeding the amount which the firm could be
legally charged with. Termination of the contract without resolution of
such dispute was illegal. It is contended that the petitioner had
already paid more than its dues and, thus, there was no reason for
termination of the contract.
13. Learned counsel for the petitioner cites Union of India and others v.
Tantia Construction Private Limited, reported at (2011) 5 SCC 697, for
the proposition that, even on the question of maintainability of a writ
petition on account of the arbitration clause included in the
agreement between the parties, it is now well established that an
alternative remedy is not an absolute bar to the invocation of the writ
jurisdiction of the High Court or the Supreme Court and that without
6
exhausting such alternative remedy, a writ petition would not be
maintainable. The constitutional powers vested in the said courts
cannot be fettered by any alternative remedy and injustice, whenever
and wherever it takes place, has to be struck down as an anathema to
the rule of law and the provisions of the Constitution. Although, in the
present case, Clause 10.3 of the GCC provides for arbitration, the
same is not an absolute bar to the writ jurisdiction of this court.
Moreover, it is submitted, Clause 10.3 could only become operative
once the remedy in Clause 10.2 of the GCC was exhausted, which did
not happen in the present case.
14. Learned senior counsel appearing for the respondents, on the other
hand, argues that the present writ petitions arise from a contractual
dispute, a decision on which is beyond the domain of the writ court.
Moreover, in view of Clauses 10.2 and 10.3 of the GCC, the petitioner
had to require the matter to be referred to the Chairman within 15
days after receiving notice of the Engineer. If the petitioner was
aggrieved by the decision given by the Chairman on such reference,
the petitioner’s remedy lay in requiring, within 15 days after receiving
notice of such decision, reference to arbitration by the Chairman
within 60 days from the petitioner’s written notice. Since the
petitioner did not exhaust such remedy, the writ court ought not to
entertain the writ petitions.
15. In this context, counsel relies upon Harbanslal Sahnia and another v.
Indian Oil Corpn. Ltd. and others, reported at (2003) 2 SCC 107,
wherein the Supreme Court laid down contingencies in which the
7
High Court may still exercise its writ jurisdiction despite the
availability of an alternative remedy – where the writ petition seeks
enforcement of any of the fundamental rights, where there is failure of
principles of natural justice or where the orders or proceedings are
wholly without jurisdiction or the vires of an Act is challenged.
16. Learned senior counsel for the respondents next cites State of Kerala
and others v. M.K. Jose [(2015) 9 SCC 433] in support of the
proposition that a writ court should ordinarily not entertain a writ
petition if there is a breach of contract involving disputed questions of
fact.
17. Counsel next relies on M/s E.C. Bose & Co. Pvt. Ltd. V. The Board of
Trustees for the Port of Kolkata & Ors., reported at (2016) 3 CHN 280,
to contend that a Division Bench of this court had, in the said case,
held that a writ complaining of the illegality of termination of a
contract by the KoPT was not a fit case where extraordinary
jurisdiction by issuing prerogative writ could be exercised since such
adjudication had to be done by leading evidence, etc. The court also
took note of the fact that an arbitration reference was also envisaged
as adjudication process as per the terms of the contract in the said
case.
18. Thus, it is argued by the respondents that the writ petitions ought to
be dismissed as not maintainable.
19. Learned senior counsel for the respondents further contends that,
admittedly, the petitioner’s firm had been depositing its dues on the
count of contributions under the 1970 Act, the 1952 Act and the 1948
8
Act all along at the stipulated rates. However, subsequently the firm
stopped depositing such dues and even withheld wages of the
labourers on the pretext of having raised a dispute regarding the rates
of its contributions. In fact, the petitioner admitted the inability of her
firm to make payments/deposits due to alleged financial distress.
Hence, it is submitted, the said dispute is a mere excuse for not
making deposits as contemplated in law and in the contract.
20. Referring to Clause 8.3 (v) of the GCC, learned senior counsel submits
that the firm of the petitioner was squarely covered by the said
provision, since it was not executing the works in accordance with the
contract and persistently and flagrantly neglected to carry out its
obligations under the contract.
21. Clause 4.18 (d) of the GCC includes payment for the statutory benefits
of all labourers and workers by the contractor, while Clause 4.1
mandates that the contract shall be governed by all relevant Indian
Acts, including the 1970 Act. Clauses 35 and 36 of the NIT require the
contractor to comply with labour laws, including the 1970 Act, the
1952 Act and the 1948 Act. These contractual obligations were flouted
by the petitioner’s firm despite several reminders, exposing its
contract to termination under Clause 8.3 (v) of the GCC.
22. Learned senior counsel for the respondents lastly submits that one
Arif Ahmed Shek, who is the vice-president of the trade union which
lodged complaint against the contractor, that is, the petitioner’s firm
(as evident from the workmen’s complaint against the contractor, a
copy of which has been annexed at page 91 of the respondents’
9
affidavit-in-opposition to W.P.O. No. 559 of 2019), also affirmed the
affidavits-in-reply in both the current writ petitions as authorised
representative of the contractor. This, by itself, shows the collusive
conduct of the petitioner, it is submitted, entailing dismissal of the
writ petitions since the writ petitioner has not come with clean hands.
23. Addressing the question of maintainability first, it is nobody’s case
that the availability of alternative remedy is an absolute bar, even in
case of contractual and arbitrable disputes. Tantia Constructions
(supra), cited by the petitioner, lays down that even when an
arbitration clause exists, such alternative remedy is not an absolute
bar to the invocation of the writ jurisdiction. The constitutional
powers vested in the High Court or the Supreme Court, it was
observed in the report, cannot be fettered by any alternative remedy.
Injustice, it was held, whenever and wherever it takes place, has to be
struck down as an anathema to the rule of law and the provisions of
the Constitution.
24. M.K. Jose (supra), relied on by the respondents, observes that a writ
court should not “ordinarily” entertain a writ petition, if there is a
breach of contract “involving disputed questions of fact”.
25. The Supreme Court, in Harbanslal Sahnia (supra), relies on Whirlpool
Corporation [(1998) 8 SCC 1] holds that, in an appropriate case, in
spite of availability of alternative remedy, the High Court may still
exercise its writ jurisdiction in “at least” three contingencies, being
enforcement of a fundamental right, failure of principles of natural
justice and where the orders or proceedings are wholly without
10
jurisdiction or the vires of an Act is challenged. In the said report, it is
observed that the rule of exclusion of writ jurisdiction by availability of
an alternative remedy is a “rule of discretion and not one of
compulsion”.
26. In M/s E.C. Bose & Co. (supra), the Division Bench of this court did
not specifically hold that an arbitration clause debars the writ
jurisdiction. The argument regarding existence of such a clause, made
by a party, was merely recorded. The basis of refusing to entertain the
writ petition was that the adjudication involved would require
evidence to be led and a detailed analysis of the facts and provisions
of the contract. The report, ipso facto, does not lay down an absolute
bar to the writ jurisdiction in either arbitrable or contractual disputes.
27. The writ jurisdiction is wide enough to interdict in case of patent
injustice, more so by the State and its instrumentalities, which are
public functionaries and, thus, are on an elevated level of obligations
to adhere to law and natural justice than a mere individual. Even if
the genesis of the dispute is contract, the nature of the present
contract belongs to the public law domain, since the contractor was
issued a work order to discharge public duties as the agent of the
KoPT (itself a public body).
28. However, the scope of the writ jurisdiction has to be filtered through
the prism of self-imposed restrictions of the High Court. It has to be
examined whether, in particular case, there has been a violation of a
fundamental/statutory right, failure of the principles of natural
11
justice, patent lack of jurisdiction or gross abuse of the process of law,
to justify interference.
29. As such, the writ petitioner cannot be shut out at the outset on the
ground of non-maintainability, without looking into the nature and
gravity of the dispute raised.
30. Clause 10.1 of the GCC contemplates disputes arising out of or
connected with the interpretation of the contract and provides that
abandonment or breach of the contract shall be subject to the
decision of the Engineer. Clause 10.2 contemplates a reference to the
Chairman against the Engineer’s decision, upon such requirement
being made by the aggrieved contractor within 15 days from notice of
the Engineer’s decision. Clause 10.3 stipulates that if the contractor is
still dissatisfied with the Chairman’s decision, he shall, within 15 days
after receiving notice of the decision, require that, within 60 days from
his written notice, the Chairman shall refer the matter to an arbitrator
of the panel of arbitrators to be maintained by the Trustees for the
purpose.
31. In the present case, the petitioner bye-passed the procedure laid down
in Clause 10 and preferred the present writ petitions directly. Such
action could only be justified if there was a patent violation of
fundamental/statutory rights or of principles of natural justice and/or
any mala fide or arbitrary action on the part of the respondents
amounting to gross miscarriage of justice.
32. Termination of a contract, in the present context, comes within the
ambit of Clause 8.3 of the GCC. The said Clause provides that,
12
without being liable for any compensation to the contractor, the
Trustees may, in their absolute discretion, terminate the contract and
enter upon the site and works and expel the contractor therefrom
after giving him a minimum 3 days’ notice in writing, on the
occurrence of any of the situations contemplated in the clause .
33. Sub-clause (v) of Clause 8.3 sets out, as a ground for termination, the
contractor not executing the works in accordance with the contract or
persistently or flagrantly neglecting to carry out his obligations under
the contract. This is the only ground which can argued to be attracted
to the present case. The other grounds, as stipulated in Clause 8.3,
are on a different footing and are irrelevant for the present purpose.
34. To understand the expressions “in accordance with the contract” and
“obligations under the contract”, as appearing in Clause 8.3(v) of the
GCC, the other relevant portions of the GCC and the tender document
are to be examined.
35. Clause 4.18 (d) of the GCC stipulates that the contractor’s quoted
rates shall be deemed to be inclusive of, inter alia, making
arrangement for payment of the wages and statutory benefits of the
labourers and workers.
36. Apart from the general Clauses of the GCC, the NIT ought also to be
looked into, in order to grasp the entire conspectus of the contractor’s
obligations as per the tender. Clause 35 of the concerned NIT dated
September 18, 2017 provides that the contractor shall be required to
comply with the Minimum Wages Act, 1948, Employees’ Liability Act,
13
1938, the Industrial Disputes Act, 1947 and the Contract Labour
(Regulation and Abolition) Act, 1970.
37. Clause 36 of the NIT mandates that the successful contractor will
have to comply with the provisions of the 1952 Act and the 1948 Act.
38. Clause 37 of the NIT provides that the successful bidder shall be
deemed to indemnify and keep indemnified the Trustees from and
against all actions, claims, demands and liabilities under and in
respect of breach of any of the provisions of any Law, Rules or
Regulations having the force of law, including but not limited to the
statutes named thereafter. Such statutes include the 1948 Act, the
1970 Act as well as the 1952 Act.
39. Even Clause 4.1(b) of the GCC provides that the contract shall be
governed by all relevant Indian Acts, including the Acts mentioned
therein, which specifically include the 1970 Act.
40. A composite reading of all the aforesaid clauses indicates clearly that
it was the duty of the contractor to comply with all provisions under
the 1970 Act, 1952 Act and the 1948 Act (apart from other statutes)
and to keep the Trustees indemnified against breach of the provisions
of the said Acts. Thus, the expressions “in accordance with the
contract” and “obligations under the contract” as envisaged in Clause
8.3(v) clearly include the compliance with provisions of the aforesaid
Acts within the scope of contractual obligations.
41. The arguments of the petitioner, based on Section 21 of the 1970 Act,
Section 8-A of the 1952 Act and Sections 39, 40 and 41 of the 1948
Act, as regards the remedy of the employer/principal employer lying
14
merely in recovery, is on unsound footing. Recovery is only one of the
remedies, provided statutorily; however, the existence of such remedy
is in addition to the contractual obligations of the
contractor/immediate employer (in the present case, the petitioner).
Such remedies, operate in different fields and do not mutually exclude
each other. Thus, the respondents did not exceed their jurisdiction in
terminating the contract under Clause 8.3(v) of the GCC.
42. The contractual obligations of the petitioner’s firm, in the context of
the present case, were forged into statutory obligations and it is
impossible to distinguish between the statutory and contractual
ingredients of such obligations. As such, a violation of the respective
statutes would simultaneously constitute a breach of the contractual
obligations of the firm as well.
43. Admittedly, the petitioner has been depositing her dues of
contributions under the 1952 Act, the 1970 Act and the 1948 Act,
without raising any objection thereto.
44. About contemporaneously with the failure of the petitioner to pay
wages and deposit statutory contributions of the labourers, the
petitioner raised certain ‘disputes’ with regard to the rates of the
petitioner’s contribution.
45. Such action, on the face of it, indicates ethical dishonesty on the part
of the petitioner. The petitioner, on the one hand, admitted in multiple
correspondence as to her inability to pay/deposit the wages and
statutory dues in time on the ground of financial hardship and, on the
other, asked for disbursal of her dues. The petitioner further added
15
the ‘windmill’ (courtesy: Orwell in Animal Farm) of bogey disputes, to
shift the focus from her defaults.
46. It must be made clear that, whatever disputes the petitioner might
have regarding overpayment and/or rate of deposits, the petitioner
cannot avoid her statutory liabilities, merged into her contractual
liabilities as it stands, on such pretext. Such disputes, if any, and the
obligations are independent phenomena and cannot be interlinked to
create confusion.
47. In the event the petitioner had any complaint regarding rates of
deposit and overpayments, which broadly pertain to the interpretation
of the contractual clauses, the petitioner ought to have taken up the
issue in consonance with Clause 10.2 and, if necessary Clause 10.3
thereafter, as per contemplation in the GCC. Having failed to do so
within the respective periods stipulated in Clause 10.2 and Clause
10.3, the petitioner cannot seek such monetary relief on the ground of
arrear dues to her in the garb of the writ petition, nor hold out such
dispute/objection as a defence for non-compliance of her statutory
obligations.
48. The disputes regarding alleged overpayment and rates of deposit are
between the firm of the petitioner and the respondents. However, the
default of the petitioner in depositing the statutory dues in compliance
with the labour laws directly affects the labourers and their livelihood.
That apart, the petitioner has been deducting the statutory
contributions from the employees on the one hand and desisting from
16
depositing such amount with the respondents, thereby unduly
enriching herself de hors the law.
49. The petitioner not only withheld statutory contributions in respect of
the employees but also defaulted in payment of wages, both of which
acts were in direct contravention of the contract between the
petitioner’s firm and the respondents, as crystallized by the NIT and
the GCC, as well as the law. Such blatant violation of the statutes and
contract speaks poorly of the conduct and intent of the petitioner. As
such, the petitioner cannot said to have come with clean hands before
this court.
50. It is seen from the records that the order of the co-ordinate Bench
dated September 24, 2019, passed in W.P.O. No.466 of 2019, was
duly complied with by the respondent-authorities and a report was
filed in consonance thereto.
51. Several opportunities over an inordinate period of time were given to
the petitioner to mend her defaults, but the petitioner chose not to do
so on one pretext of the other, sometimes harping on a pseudo-
dispute and at others appealing to the sympathy of the respondents.
In such circumstances, the respondents were absolutely within their
jurisdiction in terminating their contract with the petitioner. Such
termination, as such, was valid both as per the contract and in law.
52. As regards the allegation that Arif Ahmed Shek, the Vice President of
the complainant Trade Union, has himself acted as the authorized
representative of the contractor to affirm the affidavits-in-reply in both
the writ petitions, it is not clear beyond reasonable doubt that the two
17
persons are the same. The letter-head of the concerned Trade Union
displayed the name of Arif Ahmed Shek but does not give out any
further particulars regarding the person, sufficient to tally the identity
of the Vice President with the authorized representative. That apart,
such allegation leads neither here nor there, since the same, if
established, would invalidate not only the affidavits-in-reply of the
petitioner but might also cast doubt on the veracity of the complaint
against the contractor in the first place.
53. In any event, complicity between the leaders of Trade Union and the
immediate employer/principal employer are not unknown to the
Indian polity. However, it would be unnecessary and even improper,
given the paucity of materials, to delve into the question of the
integrity of such Arif Ahmed Shek and the question of complicity, if
any, between the contractor and the labour leaders.
54. Even if there were to be such complicity, a resolution or retribution in
that regard cannot feed the labourers, who are cheated and deprived
due to withholding of the statutory dues by the petitioner. Thus, the
said question is irrelevant for the present context and best left
unanswered in the present writ petitions.
55. Thus, in view of the above discussions, the petitioner has failed to
establish any illegality/irregularity on the part of the respondents in
terminating the contract of the petitioner, after issuing warning to do
so, worth interference by the writ court.
56. Accordingly, W.P.O No.466 of 2019 and W.P.O. No.559 of 2019 are
dismissed on contest.
18
57. The connected pending applications, if any, also stand disposed of
accordingly.
58. There will be no order as to costs.
59. Urgent certified website copies of the order shall be provided to the
parties upon due compliance of all requisite formalities.
( Sabyasachi Bhattacharyya, J. )
Comments