IN THE HIGH COURT OF DELHI AT NEW DELHI %

Judgment delivered on: 25.03.2022

+ O.M.P. (COMM) 273/2021 and IA Nos. 11808/2021 &  11810/2021

IRCON INTERNATIONAL LIMITED ….. Petitioner versus

GPT-RAHEE JV ….. Respondent Advocates who appeared in this case:

For the Petitioner : Mr Suman K. Doval, Advocate For the Respondent : Mr Gourab Banerji, Senior Advocate with Mr Anshuman Pande, Ms Gaurika Mohan and 

Ms Vishalakshi Singh, Advocates

CORAM

HON’BLE MR JUSTICE VIBHU BAKHRU

JUDGMENT

VIBHU BAKHRU, J

1. The petitioner (hereafter “Ircon”) has filed the present petition  impugning the Arbitral Award dated 19.12.2020 (hereafter the  “impugned award”) passed by the Arbitral Tribunal comprising of a  Sole Arbitrator (hereafter the “Arbitral Tribunal”). 

Factual Background 

2. On 10.02.2009, the East Central Railways under the Ministry of  Railways through its Tender No. 22 of 2008-2009 awarded Ircon the

O.M.P. (COMM) 273/2021 Page 1 of 19

project of “Construction of Steel Superstructure and Other Ancillary  Works of Rail-cum-road Bridge Across River Ganga at Patna” (hereafter the “Project”).

3. Ircon, in turn, issued a Notice Inviting Tender (NIT) on  27.06.2008, in respect of works pertaining to “Fabrication of 17 x 123  m + 2 x 64m triangulated steel bridge girders for new rail-cum-road  bridge over river Ganges (Ganga) at Patna by setting up of field  workshop on the Dighaghat end (South End) of river Ganges including  leading of structural steel from Fatuha Stockyard, shop painting and  trail assemble of one span of each type in the shop as a complete job”, arising out of the aforesaid Project.

4. The respondent was declared as the lowest bidder and  accordingly, Ircon issued a Letter of Award (LoA) dated 22.08.2008 in  favour of the respondent for execution of the aforesaid works, for a total  contract value of ₹135.39 crores. 

5. Subsequently, on 22.01.2009, the parties entered into a Contract  bearing number IRCON/2044/Ganga Bridge/05 for “Fabrication of 17  x 123 m + 2 x 64m span triangulated steel bridge girders for new rail cum-road bridge over river Ganges (Ganga) at Patna” (hereafter the  “Fabrication Contract”). 

6. Thereafter, on 27.03.2009, the parties also entered into a Contract  bearing number IRCON/2044/Ganga Bridge/07 for “Assemble,  Erection/Launching of 18 x 123 m + 1 x 64m span triangulated steel  girders for new Rail-Cum-Road bridge across river Ganga at Patna

O.M.P. (COMM) 273/2021 Page 2 of 19

from Digha Ghat end (South End) including transportation of  fabricated components of (17 X 123 m + 1 X 64m)” (hereafter the  “Erection Contract”) for a total contract value of ₹107.08 crores. 

7. The Fabrication Contract and the Erection Contract are hereafter  collectively referred to as the “Contracts”

8. In terms of the Fabrication Contract, the works were to  commence on 22.08.2008 and were to be completed within a period of  forty-two months, that is, on or before 21.02.2012. Admittedly, the  respondent completed the said works on 30.09.2015.

9. In respect of the Erection Contract, the works were to commence  on 18.02.2009 and were to be completed within a period of forty-five  months, that is, on or before 17.11.2012. However, works in respect of  the Erection Contract were completed by the respondent after a period  of eighty-six months from the date of commencement of the said  Contract, that is, on 30.04.2016.

10. The respondent claimed that there was a delay in completion of  the works under the Contracts for reasons attributable to Ircon as a result of which, it had suffered financial hardships and incurred heavy losses.  Ircon, on the other hand, claimed that the respondent was responsible  for the delay in performance of the Contracts. 

11. In view of the disputes between the parties, a meeting was held  on 10.09.2015 and certain issues were settled as recorded in the Minutes  of the Meeting dated 10.09.2015.

O.M.P. (COMM) 273/2021 Page 3 of 19

12. On 13.12.2016, the respondent executed a No Claim Certificate  (hereafter “NCC”). Ircon states that in lieu of the NCC, all claims of  the respondent were settled and thus, the respondent was precluded  from raising any further claims. 

13. However, the respondent by its letter dated 25.01.2018 raised  additional claims for losses suffered by it due to Ircon’s failure of  performing its obligations in a timely manner under the Contracts. The  respondent received no response to the aforesaid letter by Ircon.  Thereafter, by a letter dated 27.03.2018, the respondent invoked the  Arbitration Agreement and sought reference of the disputes to  arbitration. The respondent claimed an amount of ₹50,95,18,949/- in  respect of the Fabrication Contract and an amount of ₹35,26,10,345/- under the Erection Contract.

14. By the impugned award, the Arbitral Tribunal partly allowed the  claims of the respondent. A tabular statement of the claims allowed by  the Arbitral Tribunal under the Fabrication Contract and Erection  Contract is set out below:

Fabrication Contract
Claim No. 7 – Claim for idling costs  incurred and extra works done by the  claimant till the revised zero date i.e.  01.02.2010₹1,78,00,000/-

O.M.P. (COMM) 273/2021 Page 4 of 19

Claim No. 8 – Claim for additional  overheads due to prolongation₹22,89,000/- [Modified to ₹2,41,37,864/- by the Arbitral Tribunal  under Section 33 of the  A&C Act]
Claim No. 10 – Claim for excessive  interest recovered on mobilization  advance₹2,36,27,000/-
Claim No. 11 – Claim for costs of  extension of bank guarantees₹39,02,000/-
Erection Contract
Claim No. 2 – Claim for unjustified  recovery made on rectification of  riveting work₹18,50,000/- along with  interest at the rate of 6% per  annum from the date of the  Final Bill.
Claim No. 7 – Claim for additional  overheads due to prolongation₹2,11,37,000/-
Claim No. 9 – Claim for refund of  excess interest recovered on  mobilization advance₹1,49,35,750/-

O.M.P. (COMM) 273/2021 Page 5 of 19

Claim No. 10 – Claim for excess cost  incurred by the Claimant in extension  of bank guaranteesNil [Modified to ₹35,59,764/- by the Arbitral Tribunal  under Section 33 of the  A&C Act]

Submissions

15. Mr. Doval, learned counsel appearing for Ircon has confined the  challenge to the impugned award on three grounds. First, he submitted that the Arbitral Tribunal’s decision to accept the NCC submitted by the  respondent as conditional and not binding, is patently illegal. He  submitted that the Arbitral Tribunal had grossly erred in not  appreciating that the NCC was issued at a time when bulk of the  payments had already been made. He submitted that almost 99.65% of  the amounts payable under the Fabrication Contract were paid until

13.12.2016. Similarly, approximately 99.47% of the payments in  respect of the Erection Contract were made by 13.12.2016. Thus, less  than 1% of the total amount remained outstanding on the date on which  the respondent had furnished the NCC. He contended that this clearly  indicated that no economic pressure was exerted on the respondent by  withholding the admitted amounts. 

16. He further contended that even though the Arbitral Tribunal had  concluded that the respondent was in need of funds, Ircon was not  responsible for the respondent’s financial condition. Therefore, the

O.M.P. (COMM) 273/2021 Page 6 of 19

Arbitral Tribunal’s conclusion that the respondent was not precluded  from agitating its claims notwithstanding the execution of the NCC, is  manifestly erroneous. 

17. Second, he submitted that the Arbitral Tribunal had grossly erred  in awarding the claims regarding prolongation of work merely on the  basis of a Certificate issued by a Chartered Accountant. The Certificate  of the Chartered Accountant [Annexure C(F)-A-35] was denied by  Ircon and therefore, it was necessary for the respondent to prove its  contents. Additionally, the author of the said Certificate (Chartered  Accountant) was not examined and therefore, the quantification of the  claims awarded to the respondent on the basis of the said Certificate is without evidence. He submitted that the Arbitral Tribunal had also erred  in not observing that Ircon had challenged the said Certificate. He stated  that on the contrary, Ircon had not only denied the Certificate of the  Chartered Accountant but denied the contents of the said Certificate as  well. 

18. Third, he submitted that the Arbitral Tribunal had grossly erred  in awarding claims, which were premised on the basis of delay in  completion of the works as the Arbitral Tribunal had concluded that  both parties were responsible for the delay. He submitted that having  found that the respondent was also responsible for delay in completion  of the works, there is no question of awarding the respondent any  compensation on account of such delay.

O.M.P. (COMM) 273/2021 Page 7 of 19

19. Mr. Gaurab Banerji, learned senior counsel appearing for the  respondent countered the aforesaid submissions. He submitted that the  covering letter under which the NCC was furnished to Ircon, clearly  indicated that the respondent had executed the NCC involuntarily and,

the same was not unconditional. 

20. Next, he submitted that the Certificate of the Chartered  Accountant was supported with voluminous documents including bills  and vouchers establishing quantification of the amounts as reflected in  the Certificate of the Chartered Accountant. He submitted that the said  documents have not been filed by Ircon before this court but were part  of the said Certificate [Annexure C(F)-A-35]. 

21. Lastly, he submitted that the Arbitral Tribunal had examined the  question of compensation payable for delay in execution of the  Contracts and had used the principle of apportionment. He stated that  the same is permissible in law and therefore, the impugned award  cannot be assailed on this ground. 

Reasons and Conclusion

22. At the outset, it is relevant to note that although it is averred in  the petition that the impugned award is contrary to the provisions of the  Contracts; Mr. Doval did not advance any submissions in this regard.  He confined the challenge to the impugned award to the three grounds  as stated above.

O.M.P. (COMM) 273/2021 Page 8 of 19

23. Clause 49.5 of the GCC provides that in the event of any delay  on the part of Ircon or the Engineer, the time for completing the  Contracts would be reasonably extended but no damages would be  payable to the respondent. Before the Arbitral Tribunal, it was  contended on behalf of Ircon that no compensation on account of delay  is payable to the respondent in view of the said Clause.

24. The interpretation of the said clause was debated before the  Arbitral Tribunal. The respondent had relied on the decision of the  Supreme Court in Asian Techs Ltd. v. Union of India & Ors.: (2009)  10 SCC 354 in support of the contention that the exclusionary clause  was required to be read in a restrictive manner and would not be  applicable in case of a loss resulting due to an unreasonable delay. The  respondent had also relied on the decision of the Supreme Court in  Board of Trustees for the Port of Calcutta v. Engineers-De-Space Age: (1996) 1 SCC 516 and contended that such exclusionary clause  would only bind the department and not the Arbitrator. Ircon had also  relied upon certain decisions including the decision of the Supreme  Court in Syed Israr Masood, Forest Contractor, Ret Ghat, Bhopal v.  State of Madhya Pradesh: (1981) 4 SCC 289 and Associated  Engineering Co. v. Govt. of Andhra Pradesh & Anr.: (1991) 4 SCC  93

25. The Arbitral Tribunal had considered the aforesaid decisions and  in addition also referred to other decisions including a decision of this  Court in Simplex Concrete Piles (India) Ltd. v. Union of India: 2010  (115) DRJ 616 wherein this Court had examined the validity of such

O.M.P. (COMM) 273/2021 Page 9 of 19

clauses in the context of Section 23 of the Indian Contract Act, 1872. After considering the controversy, the Arbitral Tribunal had concluded  that Clause 49.5 of the GCC did not prohibit the Arbitrator from  entertaining a claim in regard to compensation. The Arbitral Tribunal  held that Clause 49.5 of the GCC would be applicable only in cases of  reasonable delay. The Arbitral Tribunal held that the said clause would  not be applicable where the delay is unreasonable and of a long  duration. The Arbitral Tribunal held that in the present case, the delay  was abnormal and therefore, the exclusionary clause (Clause 49.5 of the  GCC) would not preclude the respondent from raising a claim for  compensation. The Arbitral Tribunal was of the view that a ‘Business  Efficacy Test’ was required to be applied while considering the  exclusionary clause. In this regard, the Arbitral Tribunal drew strength  from the decision of the Supreme Court in Nabha Power Ltd. v. Punjab  State Power Corporation Limited & Anr.: (2018) 11 SCC 508. 

26. It is well settled that the question as to interpretation of a clause of a contract falls within the jurisdiction of an arbitral tribunal. The  decision of the arbitral tribunal cannot be interfered with unless the  same is found to be patently illegal or in conflict with the Public Policy  of India. 

27. In the instance case, the view expressed by the Arbitral Tribunal  is a plausible one. It was accepted on behalf of Ircon that Courts have taken divergent views in respect of applicability and interpretation of  exclusionary clauses. Clearly, the decision of the Arbitral Tribunal,  accepting one view, cannot be construed as implausible or one that no

O.M.P. (COMM) 273/2021 Page 10 of 19

reasonable person can by any stretch of imagination consider to be  implausible or one that no reasonable person would hold. Mr Doval has  thus fairly not assailed the impugned award as contrary to the terms of  the Contracts. 

28. The contention that the impugned award is vitiated by patent  illegality as the Arbitral Tribunal had accepted Ircon’s contention that  the Contracts were discharged by accord and satisfaction is unmerited.  It was the respondent’s case that the NCC was issued by it under  economic duress and not voluntarily. Thus, one of the principal  questions that fell for consideration before the Arbitral Tribunal was  whether the respondent had furnished the NCC under duress or  voluntarily. 

29. Ircon had filed an application under Section 16 of the A&C Act  on the ground that the Contracts were discharged by accord and satisfaction. The respondent had contested the same on the ground that  it had furnished the NCC under duress. The covering letter under which  the NCC was furnished also clearly indicated that the respondent did  not intend to give up its claims. In view of the rival contentions, the  Arbitral Tribunal had by an order dated 06.02.2019 rejected the  application under Section 16 of the A&C Act. However, the Arbitral  Tribunal had also observed that the question whether the respondent had  furnished the NCC under duress or voluntarily, would be determined at  the final stage.

O.M.P. (COMM) 273/2021 Page 11 of 19

30. A reading of the impugned award indicates that the Arbitral  Tribunal had discussed the law on the subject and also examined the  facts of the case. The Arbitral Tribunal noted that the respondent’s  claim was largely due to (a) prolongation of the Contracts; (b) claims  arising in respect of measurement of certain items; and (c) claims on  account of extra works. The respondent had communicated its  grievance and had highlighted the issues on several occasions during  the course of execution of the works. The parties had also attempted to  discuss and settle the issues amicably. The Arbitral Tribunal noted that a meeting was held between the parties on 10.09.2015 to settle the  issues. The Arbitral Tribunal was of the view that the decisions taken  at the said meeting were voluntary and without any coercion. Thus, the  issues that were settled at the said meeting could not be reopened.  However, insofar as the issues that were not settled, it was difficult to  accept that the respondent had voluntarily waived its outstanding claims  which it was diligently pursuing with Ircon. Some of the claims that  remained pending were specifically mentioned by the respondent in the  letters dated 09.12.2016 (that is, barely four days prior to furnishing the  NCC). The Arbitral Tribunal noted that even at that stage, the  respondent had stated that it may have other claims which were under  preparation. The Arbitral Tribunal also noted the following assertion  made by the respondent in its letters dated 09.12.2016:

“…..In this connection, we have now been advised 

to sign a “No Claim” Certificate in favour of 

IRCON as per the attached proforma. We are 

further given to understand that the due payments

O.M.P. (COMM) 273/2021 Page 12 of 19

will be released only after submission of the 

certificate.” 

31. In view of the above, the Arbitral Tribunal concluded that it was  discernable from the letters that certain claims were under preparation  and the respondent had clearly indicated that it would be preferring  those claims. The Arbitral Tribunal was of the view that the NCC was required to be examined along with the covering letter under which it  was sent. Apart from the above, the Arbitral Tribunal was also of the  view that the respondent was in need of money and was facing financial  stress and Ircon had withheld certain payments due to the respondent, in addition to levying liquidated damages. The findings of the Arbitral  Tribunal in this regard are relevant and are reproduced below:

“10.56 I am also of the view that the Claimant was 

in need of money and was facing financial 

stress. The amount payable to the Claimant 

at that time cannot be considered vis-à-vis 

the total amount of the contract and the 

amount which had already been paid, which 

was the contention of the learned Counsel 

for the Respondent. Ground realities as on 

the date of signing the NCC have to be 

looked into. The contract had been stretched 

for more than three years which is quite 

considerable having regard to the original 

time for completion of the project stated in 

the contract. Because of this prolongation, 

the Claimant felt that it was entitled to 

escalation amount in terms of Clause 59.3 of 

the contract. This prolongation had also 

contributed towards increase in overhead 

costs.

O.M.P. (COMM) 273/2021 Page 13 of 19

10.57 The Respondent had withheld certain  payments and had also recovered amount on  account of Liquidated Damages which the  Respondent was ready to refund back only  on signing of NCC. Threat of invocation of  Bank Guarantees also loomed large. Under  these circumstances, when the Claimant  signed the NCC, in order to receive the  payments of the amount which the  Respondent had agreed to, it cannot be said  that NCC was given voluntarily. Be as it  may, as already mentioned above, covering  letter dated 09.12.2016 itself states that the  Claimant was signing as it was given to  understand that payment would be released  only after submission of the Certificate. The  Claimant was, therefore, faced with  Honson’s choice – either to receive whatever  is offered by signing NCC or to refuse to sign  NCC and raise the claims. Latter alternative  would have resulted in withholding the  payment, non-refund of Liquidated  Damages and even invocation of Bank  Guarantees. All these could be part of the  claims to be raised by the Claimant in that  even along with other claims which the  Claimant has raised now, making the  Claimant to await the passing of the award  by the Arbitral Tribunal. If the Claimant  chose the first alternative by signing the  NCC, but at the same time made it clear in  the covering letter that it would be preferring  some other claims, I am of the view that the  singing of the NCCs cannot preclude  Claimant from making further claims.”

O.M.P. (COMM) 273/2021 Page 14 of 19

32. The contention that the Arbitral Tribunal has failed to appreciate  that only a small fraction of the total admitted amount was payable by  Ircon at the material time, is unpersuasive. 

33. It is clear that Arbitral Tribunal had examined various facets of  the disputes and has taken an informed decision. The scope of  interference on the ground of patent illegality under Section 34(2A) of  the A&C Act does not extend to re-appreciating the material before the  Arbitral Tribunal and re-adjudicating the disputes. 

34. The contention that the impugned award is vitiated by patent  illegality as it is based on no evidence is also unmerited. It is necessary  to bear in mind that the Indian Evidence Act, 1872 and the strict rules  of evidence are inapplicable to arbitral proceedings. The Arbitral  Tribunal is required to render a decision after evaluating the material  placed before it. 

35. In the present case, the respondent had supported its claim by  furnishing a Certificate of an independent Chartered Accountant [Annexure C(F)-A-35]. A plain reading of the said Certificate indicates  that it was accompanied by Statement of Administrative and other  Overhead Expenses. Further, the concerned Chartered Accountant had  also certified that he had examined the same from various books and  accounts maintained by the respondent including vouchers, bank  statements, bills, invoices, as well as other relevant supporting records  and documents maintained by the respondent. The Arbitral Tribunal had  accepted the said Certificate. Although, the author of the said Certificate

O.M.P. (COMM) 273/2021 Page 15 of 19

was not examined, the concerned officer of the respondent had  produced the said Certificate and duly affirmed the quantification. As  noted above, strict rules of evidence do not apply to arbitral proceedings  and there is considerable discretion available with the Arbitral Tribunal  to take a view on the quality and the sufficiency of evidence. The  contention that the impugned award is required to be set aside on the  ground that quantification of certain claims awarded in favour of the  respondent is without any material, is unmerited. 

36. Mr. Doval had earnestly contended that Ircon had denied the  aforesaid Certificate as well as its contents. However, Ircon had not  disputed the said Certificate apart from making a bald denial in the  Statement of Admission and Denial. The petitioner also did not raise

any specific objection regarding the reasonableness of the expenditure  as mentioned in the Certificate of the independent Chartered  Accountant including the Statement of Expenses forming part of the  said Certificate.

37. As noticed above, the respondent’s claim was premised mainly  on account of prolongation of works. Admittedly, the respondent was  present at site and had executed the works. It is obvious that the respondent had incurred expenses on account of administrative charges  and overhead expenses during the period of prolongation of the works.  If Ircon would have found any of the expenditure to be exorbitant or  unreasonable, it was certainly open for Ircon to have raised that  objection. The observation made by the Arbitral Tribunal to the effect  that Ircon had not raised any specific challenge must be read in that

O.M.P. (COMM) 273/2021 Page 16 of 19

context. The said observation cannot be read to mean that Ircon had  admitted the expenditure as claimed. It merely means that Ircon had not  “specifically laid any challenge to the details so provided” by the  respondent.

38. Lastly, the contention that the impugned award is vitiated by  patent illegality as the Arbitral Tribunal has awarded claims on account  of delay in completion of the works despite holding that the respondent  was partly responsible for the same, is unmerited. The Arbitral Tribunal  found that there were delays on the part of Ircon in handing over the  site. The site was required to be levelled and the work of earth filling  continued till March, 2009. The site for the first workshop after  levelling was handed over in January, 2009 and the site for the second  workshop was handed over by April, 2009. However, in terms of Clause  13 of the Additional Special Conditions of Contract (ASCC) read with  its corrigendum, the site was required to be handed over within a period  of 15 days from 06.09.2008. In view of the above, the Arbitral Tribunal  concluded that there was delay in handing over of the site. The Arbitral  Tribunal also found that there was inordinate delay in handing over of  the GFC drawings. This was a fundamental obligation on the part of  Ircon and the same was breached. The Arbitral Tribunal also held that  the respondent could not continue certain preparatory work in the  absence of the requisite drawings. 

39. The Arbitral Tribunal accepted that there was certain delay on the  part of the respondent as well. However, the Arbitral Tribunal  concluded that the delays on the part of Ircon were in respect of “critical

O.M.P. (COMM) 273/2021 Page 17 of 19

aspects” and the said delays were dominant in prolongation of the  works. The conclusion of the Arbitral Tribunal in this regard is set out  below: 

“10.160. The Respondent has committed 

fundamental breaches in not providing site for 

construction of workshop etc. in time. Further 

there has been abnormal delay I providing good 

GFC for construction drawings. Delay was also 

caused because of change in drawings from time to 

time. Like-wise, absence of incorporation of 

strengthening provisions in the drawings too 

caused the delay. The timeless, as specified in the 

contract, were not adhered to. There were some 

other delays caused by the Respondent. It is also 

recorded that there were initial delays on the part 

of the Claimant as well as insofar as preparatory 

work is concerned as the signing of the contract 

itself was delayed due to non-submission of 

Performance Security, Bank Guarantee for 

mobilization advance, etc. An overall picture 

which emerges is that for significant part of the 

contract, there is contributory / concurrent delay on 

the part of Claimant as well which happened 

parallel during the project. However, certain 

delays occurred solely because of the non

fulfillment of obligations by the Respondent.” 

40. The Arbitral Tribunal is of the view that given that the parties had  contributed to certain delays, it was essential to apply the principle of  apportionment. After evaluating the reasons for the delay, the Arbitral  Tribunal concluded that half of the delay could be apportioned to both  Ircon and the respondent. However, for the remaining half, Ircon was  solely responsible for the same. Therefore, only half of the claim made

O.M.P. (COMM) 273/2021 Page 18 of 19

by the respondent on account of idling costs was allowed by the Arbitral  Tribunal. The relevant paragraph of the impugned award embodying  the said conclusion is set out below:

“10.171 Keeping in view all the aforesaid 

considerations, I am of the view that the Claimant 

would be entitled to the losses suffered by it because 

of certain fundamental delays on the part of the 

Respondent, but at the same time, the claim 

preferred by the Claimant to be reduced by applying 

the principle of apportionment because of the reason 

that to some extent, delays are caused due to the 

factors attributable to the Claimant itself. After 

considering the overall circumstances, the period of 

delay solely attributable to the Respondent is 

reduced to half, as for the other period, the Claimant 

is also liable and therefore, cannot take advantage. 

The Claims for compensation on the ground of delay 

are adjudicated on this yardstick.” 

41. This Court finds no infirmity in the approach of the Arbitral  Tribunal. The contention that the same is contrary to law is unmerited.  This Court is unable to accept that the impugned award requires any  interference in this proceeding. 

42. The petition is accordingly dismissed. The pending applications  are also disposed of. 

VIBHU BAKHRU, J

MARCH 25, 2022

‘gsr’

O.M.P. (COMM) 273/2021 Page 19 of 19

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.