IN THE HIGH COURT OF DELHI AT NEW DELHI %

Judgment delivered on: 04.04.2022

+ OMP (ENF.) (COMM.) 258/2018 & EA(OS) Nos. 1026/2019,  188/2020, 16240/2018 & 8918/2019

M/S KARAM CHAND THAPAR & BROS. (COAL  SALES) LTD. ….. Decree Holder

versus

MMTC LTD. ….. Judgment Debtor 

Advocates who appeared in this case:

For the Decree Holder: Mr Rajeev K. Virmani, Senior Advocate with  Mr Rishabh Bhargava and Ms Niharika, 

Advocates.

For the Judgment Debtor: Mr Sanat Kumar, Senior Advocate with Mr  Abhishek Bhardwaj and Mr Manish K. Singh, 

Advocates.

CORAM

HON’BLE MR JUSTICE VIBHU BAKHRU

JUDGMENT

VIBHU BAKHRU, J

1. The petitioner (Decree Holder) has filed the present petition  under Section 36 of the Arbitration and Conciliation Act, 1996  (hereafter ‘the A&C Act’) seeking to enforce an Arbitral Award dated  07.01.2017 (hereafter the ‘Arbitral Award’). The Arbitral Award has  been enforced to a substantial extent.

OMP (ENF.) (COMM.) 258/2018 Page 1 of 18

2. The only contentious issue that remains to be addressed is regarding the rate of conversion of foreign exchange to be applied for determining the amount required to satisfy the Arbitral Award to the  extent of the amount awarded in foreign currency (US Dollars). The  petitioner claims that the rate of conversion is to be determined with  reference to the date on which the respondent’s (Judgment Debtor’s)  Special Leave Petition (SLP) was dismissed by the Supreme Court and  the Arbitral Award became final. The respondent (hereafter ‘MMTC’)  contends that the rate of conversion is to be reckoned in reference to the  date when the demand for the same was made by the petitioner for the  first time (that is, on 15.05.2010). 

3. Briefly stated the relevant facts necessary to address the aforesaid  controversy are as under:

3.1 The petitioner is a company incorporated in India and is engaged  in the business of stevedoring and handling, cleaning and forwarding,  transportation and escorting etc. MMTC is a Public Sector Undertaking. 

3.2 National Thermal Power Corporation Ltd. (hereafter ‘NTPC  Ltd.’), a public sector undertaking, had placed an order with MMTC  for import of coal and supply to its various power stations in the  country. Accordingly, MMTC had entered into an Agreement dated  01.06.2005 with the petitioner, whereby the petitioner was engaged as  a stevedoring and handling contractor for handling imported coal from foreign vessels at the port of discharge (Paradip Port) and, for its

OMP (ENF.) (COMM.) 258/2018 Page 2 of 18

transportation to NTPC Ltd’s Thermal Power Station, Kaniha at  Talcher, for the period June, 2005 to May, 2006. 

3.3 Disputes arose between the parties in connection with the said  contract. The same were referred to arbitration under the aegis of the Indian Council for Arbitration. The Arbitral Tribunal comprised of  three former High Court Judges. The arbitral proceedings culminated in the Arbitral Award dated 07.01.2017, which is sought to be enforced in  this petition. 

3.4 The operative part of the Arbitral Award reads as under:

AWARD

Accordingly, the Arbitral Tribunal proceeds to make 

this award holding the Claimant entitled to recover from the  Respondent the following amounts:

1. Rs.1,27,62,425/- under claim No.1 on account of service  charges;

2. USD 2,42,445.03 under claim No.2 on account of  despatch money;

3. Rs.17,46,576/- with Rs. 2,22,688.44 towards interest  @10% per annum from 02.06.2009 till 09th September,  2010, the date of the filing of the statement of Claim,  total Rs.19,69,264.44, under claim No. 3, on account of  bank guarantee charges.

4. Under claim No.1 for an amount of Rs. 95,30,830.50  towards pendente lite interest from 09th September,  2010, the date of filing of the claim till the date of the  award, at the rate of 12% per annum on Rs.1,27,62,425/-

.

5. Under claim No.2 for an amount of USD 1,81,106.43  towards pendente lite interest from 09th September,

OMP (ENF.) (COMM.) 258/2018 Page 3 of 18

2010, the date of filing of the claim till the date of the  award, at the rate of 12% per annum on USD  2,42,445/43.

6. Under claim No.3 for an amount of Rs. 13.04,692/27  towards pendente lite interest from 09th September,  2010, the date of filing of the claim till the date of the  award, at the rate of 12% per annum on Rs.17,46,576/27.

7. Future interest at the rate of 12% per annum from the  date of the award till the date of payment on the awarded  amount of Rs. 2,53,44,523/77 and USD 4,23,551/46.

8. The Claimant is also held entitled to full costs of the  arbitral proceedings. Award signed, published and  delivered at New Delhin on 7th January, 2017.” 

3.5 MMTC challenged the award under Section 34 of the A&C Act  [OMP(COMM) 193/2017 captioned MMTC Ltd. v. M/s Karam Chand Thapar & Bros. (Coal Sales) Ltd.]. The said petition was  disposed of by this Court by a judgment dated 31.10.2018. The Arbitral  Award was not interfered with except to the extent of cost awarded by  the Arbitral Tribunal. 

3.6 MMTC appealed the judgment dated 31.10.2018 before the  Division Bench of this Court [FAO(OS)(COMM) 2/2019 captioned  MMTC Limited v. M/s Karam Chand Thapar and Bros. (Coal Sales) Ltd.] which was dismissed by an order dated 25.02.2019. 

3.7 MMTC sought to appeal against the said decision before the  Supreme Court and filed a Special Leave Petition [SLP (C) No.  9877/2019], which was dismissed by the Supreme Court by an order  dated 29.04.2019.

OMP (ENF.) (COMM.) 258/2018 Page 4 of 18

3.8 On 07.05.2019, MMTC deposited a sum of ₹6,97,47,541/- with  the Registry of this Court. MMTC states that the aforesaid figure was  computed by converting the amount awarded in US Dollars to Indian  currency at the rate of ₹ 73.996/- which was the prevalent exchange rate  at the material time. 

3.9 Out of the aforesaid sum of ₹6,97,47,541/- a sum of  ₹5,71,04,716/- was released to the petitioner. This comprised of the  amount awarded in Indian currency along with interest till 07.05.2019  (that is, the date of deposit). And, the amount in INR equivalent to the

amount awarded foreign currency (US$) converted at an exchange rate  of ₹45.10 per USD – the exchange rate as applicable on 15.05.2010 – along with interest. This amount was admittedly payable to the  petitioner. According to MMTC, the component of the Arbitral Award  in foreign currency (US Dollars) was to be discharged in Indian  currency computed at a conversion rate as applicable on 15.05.2010 –

being the date on which the petitioner had demanded the amount for the  first time. 

4. In view of the above, the only contentious issue that requires to  be addressed at this stage is regarding the conversion rate to be applied  for discharge of the amount awarded in foreign currency in terms of the  Arbitral Award. 

5. According to MMTC, the foreign currency conversion rate as  applicable on 15.05.2010 is required to be used for computing the  Indian currency equivalent to the amount awarded in US Dollars.

OMP (ENF.) (COMM.) 258/2018 Page 5 of 18

MMTC claims that since the petitioner had articulated its demand for  the first time on 15.05.2010, the said date is relevant for computation of  the conversion rate. The petitioner, on the other hand, claims that the  conversion rate as applicable on 29.04.2019 – the date on which  MMTC’s Special Leave Petition was dismissed by the Supreme Court

of India – is relevant, as the Arbitral Award became final and  enforceable on that date. 

Submissions

6. Mr Virmani, learned senior counsel for the petitioner, had  referred to the decisions of the Supreme Court in Forasol v. Oil and  Natural Gas Commission: (1984) Supp SCC 263 and the decision of  this Court in Trammo AG v. MMTC Limited: 2019 SCC OnLine Del  7337 in support of his contention. 

7. Mr Sanat Kumar, learned senior counsel for MMTC, submitted  that the decision in the case of Forasol v. Oil and Natural Gas  Commission (supra) and Trammo AG v. MMTC Limited (supra) are  inapplicable to the facts of the present case. He submitted that the said  decisions were rendered where one of the parties to the dispute was a  foreign entity. He submitted that the said decisions would have no  bearing to disputes where both parties are Indian Nationals/Indian  entities. He submitted that in such cases, there is no dispute that the  arbitral award is required to be discharged in Indian currency, and  therefore, the conversion rate as applicable on date of the first demand, would be the relevant date.

OMP (ENF.) (COMM.) 258/2018 Page 6 of 18

8. He submitted that a fortiori in the present case, the contract in  question was to be performed in India and all payments were required  to be discharged in Indian currency. He submitted that the first  Statement of Claims filed by the petitioner had also quantified the

claimed amounts in Indian currency. However, subsequently, the  petitioner had filed a second Statement of Claims claiming certain  amounts in US Dollars. He submitted that the Arbitral Tribunal had also  awarded interest in foreign currency at the same rate as applicable to  the amounts awarded in Indian currency (at the rate of 12% per annum).  According to him, this would not be sustainable if the conversion rate  is accepted to be the rate on which the Arbitral Award became final. He  referred to the decision in the case of Vedanta Ltd. v. Shenzen  Shandong Nuclear Power Construction Co. Ltd.: (2019) 11 SCC 465 in support of his contention.

9. He also referred to the decision of the Supreme Court in Triveni  Kodkany and Ors. v. Air India Ltd. and Ors.: 2020 SCC OnLine SC  876 and on the strength of the said decision contended that since both  parties were Indian, the decisions in the case of Forasol v. Oil and  Natural Gas Commission (supra) and Trammo AG v. MMTC Limited (supra), are inapplicable. 

Reasons and Conclusion 

10. It is trite law that in execution proceedings, the Court is not  required to go behind the decree. The decree must be accepted on its

OMP (ENF.) (COMM.) 258/2018 Page 7 of 18

own terms and shall be enforced. There is no room to revisit contentious  issues, which have attained finality, at this stage. 

11. In the present case, the petitioner had filed a Statement of Claim  claiming certain amounts in foreign currency. The Arbitral Award was  dispositive of the disputes between the parties and it is clear from the  face of the Arbitral Award that an amount of USD 242,445.03 has been  awarded against Claim No.2 along with pre-reference and pendente lite interest at the rate of 12% per annum quantified at USD 181,106.43

12. Admittedly, the Agreement between the parties does not contain  any provision regarding conversion of the foreign currency component  in Indian rupees. Thus, the Arbitral Award must be enforced on its own  terms. However, the Arbitral Award does not indicate the conversion  rate for computing the Indian currency equivalent to the amounts  awarded in US Dollars. 

13. Given the aforesaid circumstances, the question as to the  exchange rate to be applied for computing in Indian currency equivalent  of the amount awarded in foreign currency is no longer res integra. In  Forasol v. Oil and Natural Gas Commission (supra), the Supreme  Court had considered the aforesaid question and had held that the date  on which the decree had become final would be the relevant date for  determining the applicable exchange rate. The relevant extract of the  decision is set out below:

“23. The question which now remains to be considered in  Forasol’s appeal is the date to be selected by the Court for

OMP (ENF.) (COMM.) 258/2018 Page 8 of 18

converting into Indian rupees the French franc part of the  said award in respect of which no rate of exchange has been  fixed either by the said contract or the said award.

24. In an action to recover an amount payable in a foreign  currency, five dates compete for selection by the Court as  the proper date for fixing the rate of exchange at which the  foreign currency amount has to be converted into the  currency of the country in which the action has been  commenced and decided. These dates are:

(1) the date when the amount became due and payable; (2) the date of the commencement of the action; (3) the date of the decree;

(4) the date when the Court orders execution to issue;  and

(5) the date when the decretal amount is paid or realised.

25. In a case where a decree has been passed by the Court  in terms of an award made in a foreign currency a sixth date  also enters, the competition, namely, the date of the award.  The case before us is one in which a decree in terms of such  an award has been passed by the Court.

xxxx xxxx xxxx

41. The first of the five dates listed earlier by us, namely,  the date when the amount became due and payable, does not  have the effect of putting the plaintiff in the same position  in which he would have been had the defendant discharged  his obligation when he should have done because between  that date and the date when the suit is decreed the rate of  exchange may have fluctuated to the plaintiff’s prejudice,  resulting in the amount decreed in rupees representing only  a fraction of what he was entitled to receive. Equally, the  possibility of the plaintiff getting more than what he had  bargained for in case the rate of exchange had fluctuated in  his favour cannot be ruled out. To select, as the English  courts had done earlier, the date when the amount became  due or the “breach date”, as the English courts have termed

OMP (ENF.) (COMM.) 258/2018 Page 9 of 18

it, is thus to expose the parties to the unforeseeable changes  in the international monetary market. The selection of the  “breach date” cannot, therefore, be said to be just, fair or  equitable because in a case where the rate of exchange has  gone against the plaintiff, the defendant escapes by paying  a lesser sum than what he was bound to and thus is the  gainer by his default while in the converse case where the  rate of exchange has gone against the defendant, the  defendant would be subjected to a much greater burden than  what he should be.

xxxx xxxx xxxx

43. We will now consider the feasibility of selecting the  third date, namely, the date of the decree. A decree  crystallizes the amount payable by the defendant to the  plaintiff and it is the decree which entitles the judgment

creditor to recover the judgment debt through the processes  of law. An objection which can, however, be taken to  selecting this date is that the decree of the trial court is not  the final decree for there may be appeals or other  proceedings against it in superior courts and by the time the  matter is finally determined, the rate of exchange prevailing  on that date may be nowhere near that which prevailed at  the date of the decree of the trial court. To select the date of  the decree of the trial court as the conversion date would,  therefore, be to adopt as unrealistic a standard as the “breach  date”. This difficulty is, however, easily overcome by  selecting the date when the action is finally disposed of, in  the sense that the decree becomes final and binding between  the parties after all remedies against it are exhausted. This  can be achieved by the court which hears the appeal  providing that the date of its decree or other proceedings in  which the decree is challenged would be the date for  conversion of the foreign currency sum into Indian rupees  in cases where the decree has not been executed in the mean  time. The real objection to selecting this date, however, is  that a money decree and the payment by the judgment  debtor of the judgment debt under it are two vastly different  matters widely separated by successive execution

OMP (ENF.) (COMM.) 258/2018 Page 10 of 18

applications and objections thereto unless the judgment debtor chooses to pay up the judgment debt of his own  accord which is generally not the case. In the vast majority  of cases a money decree is required to be enforced by  execution.

xxxx xxxx xxxx

46. The above difficulties would rule out the taking of the  date when the court grants an application for execution as  the date of conversion and would make inapplicable to our  courts the Rule laid down in the Miliangos case [1976 AC  443 : (1975) 3 All ER 801 : (1975) 3 WLR 758 (HL)] .

xxxx xxxx xxxx

52. For the above reason, it is not possible for us to accept  the date of payment or realization of the decretal debt as the  proper date for the rate of conversion.

53. This then leaves us with only three dates from which to  make our selection, namely, the date when the amount  became payable, the date of the filing of the suit and the date  of the judgment, that is, the date of passing the decree. It  would be fairer to both the parties for the Court to take the  latest of these dates, namely, the date of passing the decree,  that is, the date of the judgment.”

14. The aforesaid decision has been followed by the Supreme Court  in Renusagar Power Co. Ltd. v. General Electric Co.: 1994 Supp (1)  SCC 644; Standard Chartered Bank Ltd. v. B.N. Raman (Dr.): (2006)  5 SCC 727; and Meenakshi Saxena v. ECGC Ltd.: (2018) 7 SCC 479.

15. It is important to note that during the course of the proceedings  under Section 34 of the A&C Act filed by MMTC to impugn the  Arbitral Award [OMP(COMM) 193/2017], the aspect of the applicable  foreign exchange was raised during oral submissions. Mr Kumar,

OMP (ENF.) (COMM.) 258/2018 Page 11 of 18

learned senior counsel for MMTC, had earnestly contended that this Court had held that the question relating to the applicable exchange rate  was left open for the Executing Court to decide. He also referred to the  following passage from the said decision [OMP(COMM) 193/2017 captioned : MMTC Ltd. v. M/s Karam Chand Thapar & Bros (Coal  Sales) Ltd.’]:

“33.2 While on the issue at hand, I may also advert to one  other aspect (which was, once again, put forth across the  bar by Mr. Sanat Kumar) as to the applicable exchange  rate. In my view, this is an aspect which the Executing  Court will examine, if it reaches that stage having regard  to the applicable law on the issue. As correctly contended  by Mr. Virmani, the judgment debtor, if it happens to be  the petitioner, could offer to pay the amount in Indian  rupees and the conversion rate, which would apply would  be the rate, which is prevalent on the date of the decree.”

16. This Court is of the view that the aforesaid observations do not  support the contention advanced by Mr Kumar. On the contrary, it  appears that the Court was of the view that the conversion rate on the  date of the decree, would be applicable. The contention of Mr Virmani,  learned senior counsel who appears for the petitioner (respondent in that  proceedings) was accepted by the Court. The question regarding the  applicable conversion rate was left open for the Executing Court to  decide as at that stage, the Arbitral Award had not attained finality.  Therefore, the Court had observed that if the petitioner happens to be  the Judgment Debtor, it would pay the applicable rate prevalent on the  date of the decree.

OMP (ENF.) (COMM.) 258/2018 Page 12 of 18

17. MMTC also understood the observations made by the Court as  above and thus, specifically raised the same as a ground of appeal before  the Division Bench of this Court. The relevant ground urged by MMTC  before the Division Bench of this Court was articulated as under:

“P. It is submitted that the Ld. Single Judge after having  held that the executing Court would determine the  exchange rate applicable in the present matter, further  observed that the Appellant if it wanted to pay the  claim No.2 in INR it could do so at the exchange rate  as applicable on the date of the decree. These two  findings are completely contrary to each other. Once  the Ld. Single judge has found that the executing court  shall have the power to decide as to what rate the USD  is to be converted into INR, the Ld. Single Judge  should not have gone further and observed on the said  issue.”

18. As noted above, the Division Bench of this Court dismissed the  appeal [FAO(OS)(COMM) 2/2019] preferred by MMTC. MMTC  carried the matter before the Supreme Court [SLP (C) No. 9877/2019].  Before the Supreme Court, MMTC sought to challenge the decision of  the Co-ordinate Bench of this Court as well as the Division Bench of  this court by urging that the Court had wrongly applied the judgment in  the case Centravis Production Ukraine v. Gallium Industries Limited: (2014) SCC OnLine Del 6787 as the said case was pertaining to a

foreign award. It contended that the principles as applicable in the said  judgment and Forasol v. Oil and Natural Gas Commission (supra)  would not be applicable in the facts of the present case. The relevant  ground urged before the Supreme Court are set out below:

OMP (ENF.) (COMM.) 258/2018 Page 13 of 18

“S. Because in the present matter the date on which the said  amount would have to be converted into INR would be  the first date on which the said amount was demanded  by the Respondent which would be the date of the legal  notice dated 15.05.2010 issued by the Respondent  through its counsel demanding the said amount. The  Ld. Single Judge has wrongly applied the principles  which are given in the judgment of Centravis  Production Ukraine v. Gallium Industries Limited  2014 SCC Del 6787. It is submitted that the judgment  of Centravis Production Ukraine v. Gallium Industries  Limited (supra) is in the context of a foreign award  where a party can subject to the contract demand its  claims to be awarded in a foreign currency. However,  in the present case as mentioned above, the payment  can never be made in USD. In domestic award the  payment must necessarily be made in INR and that being the case the principles which are applicable in  the cases such as Centravis Production Ukraine v.  Gallium Industries Limited supra and Forasol v. Oil  and Natural Gas Commission 2015 (1) ArbR 113  (Delhi) etc would not be applicable to the facts of the present case.

xxxx xxxx xxxx

W. Because the Division Bench of the Hon’ble High Court  failed to appreciate that the finding of the Ld. Single  Judge that the claim No. 2 was rightly awarded in terms  of USD, is completely contrary to the contract. Under  the contract any payments which were to be made to  the Respondent by the Petitioner were to be made in  INR. Both the Petitioner and the Respondent are Indian  companies and therefore there is no question of them  entering into a contract where the payments are to be  made in USD. In fact such a contract would not be  legally permissible.

OMP (ENF.) (COMM.) 258/2018 Page 14 of 18

X. Because the Division Bench of the Hon’ble High Court  failed to appreciate that the finding of the Ld. Single  Judge that the Claim No. 2 could be awarded in USD  because the calculations of demurrage/ despatch was in  USD is erroneous. It is submitted that merely because  the rate of demurrage/ despatch was in USD does not  mean that the quantified demurrage/ despatch amount  is also required to be paid in USD. The rate of  demurrage/ despatch being given in USD does not  entitle the Respondent to claim the said amount in USD  instead of INR, especially in a domestic arbitration  where both the parties are Indian.

xxxx xxxx xxxx

BB Because the Division Bench of the Hon’ble High Court  failed to appreciate that the Ld. Single Judge after  having held that the executing Court would determine  the exchange rate applicable in the present matter,  further observed that the Petitioner if it wanted to pay  the claim No.2 in INR it could do so at the exchange  rate as applicable on the date of the decree. These two  findings are completely contrary to each other. Once  the Ld. Single judge has found that the executing court  shall have the power to decide as to what rate the USD  is to be converted into INR, the Ld. Single Judge  should not have gone further and observed on the said  issue.”

19. It is clear from the above, that MMTC had contested the  observations of the Co-ordinate Bench of this Court to the effect that if  MMTC was a Judgment Debtor then the rate of exchange to be applied  would be as applicable on the date of the decree. 

20. Having unsuccessfully raised this question at earlier stages,  MMTC’s attempt to re-agitate this question is not justified.

OMP (ENF.) (COMM.) 258/2018 Page 15 of 18

21. The decision in the case of Triveni Kodkany and Ors. v. Air  India Ltd. (supra) is not applicable to the facts of this case. In that case,  the NCDRC (National Consumer Disputes Redressal Commission) awarded compensation in Indian currency, albeit on the basis of  applying the conversion rate as prevailing on the date of the complaint.  NCDRC had computed the compensation payable at AED 58,81,135/-

which was converted to Indian currency on the basis of the conversion  rate as applicable on the date of the complaint. This was not a case  where any amount was awarded in foreign currency. 

22. It is also relevant to note that the complainants before the  NCDRC were legal heirs of a person who had died in an air crash. They  had claimed compensation in Indian currency for future income that  would have accrued to the deceased and medical aid on account of  negligence on the part of Air India. NCDRC had computed the

compensation at AED 58,81,135/- which was equivalent to  ₹7,35,14,187/-. A sum of ₹4 crores had already been received by the  complainants and a sum of ₹40,00,000/- had been disbursed to the  parents of the deceased. The remaining balance sum quantified at  ₹2,95,14,187/- was awarded to the complainants along with interest at  the rate of 9% per annum. 

23. The appellants before the Supreme Court had challenged the  amount decreed, and one of the questions, which fell for consideration  before the Court, was whether the rate of conversion adopted by the  Trial Court (NCDRC) was justified. It is in the aforesaid context, the  Court had distinguished the applicability of the decisions in the case of

OMP (ENF.) (COMM.) 258/2018 Page 16 of 18

Renusagar Power Co. Ltd. v. General Electric Co (supra) and Forasol  v. Oil and Natural Gas Commission (supra). The question now raised  by MMTC is regarding the applicable exchange rate where the decree  is in foreign currency. 

24. The contention that the decision in Forasol v. Oil and Natural  Gas Commission (supra) is required to be distinguished on the basis  that in that case one of the parties was a foreign entity, is not persuasive.  This Court finds it difficult to accept that an Executing Court would  determine the exchange rate to be used for enforcing decrees based on  whether both the parties are Indian entities or not. It is not necessary  that the commercial transactions between Indian parties be confined to  Indian territories alone. There may be transactions which may entail  exposure in foreign currency. For the purposes of enforcement, no  distinction can be made between decree/awards where amounts are  decreed/awarded in foreign currencies on the basis of the nationality of  the disputing parties.

25. In view of the above, the exchange rate to be applied for  computing the amount due and payable under the awarded amount is  the exchange rate as prevailing on 29.04.2019, being the date on which  MMTC’s SLP was dismissed by the Supreme Court and the Arbitral  Award attained finality. 

26. It is not disputed that the exchange rate on that date for one USD  was ₹70.1445 which was less than the exchange rate as on 07.05.2019  (the date on which MMTC had made the deposit). The petitioner would

OMP (ENF.) (COMM.) 258/2018 Page 17 of 18

be entitled to the remaining amount – amount awarded in US$  computed at ₹ 35.045 (₹70.1445 less ₹45.10). The remaining amount is  required to be refunded to MMTC.

27. The petition be listed before the Joint Registrar on 13.04.2022 for  the remaining amount to be disbursed to the parties on the aforesaid  basis. 

28. The petition is disposed of in the aforesaid terms. 

VIBHU BAKHRU, J

APRIL 4, 2022

RK

OMP (ENF.) (COMM.) 258/2018 Page 18 of 18

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.