* IN THE HIGH COURT OF DELHI AT NEW DELHI

% Judgment reserved on: 09 March 2022  Judgment pronounced on: 31 March 2022

+ W.P.(C) 8779/2019, CM APPLs. 36308/2019 & 44738/2019 THE INDIAN HOTELS COMPANY LTD. ….. Petitioner

Through: Mr. Abhishek Manu Singhvi, Sr. 

Adv. with Mr. Sanjeev Sandhvani, 

Sr. Adv. with Ms. Gunjan Sinha, 

Adv.

Versus

UNION OF INDIA AND ORS. ….. Respondents

Through: Mr. Vikram Jetly, CGSC for R-1.

Mr. Saurabh Sharma, Adv. for R-2.

Mr. Saket Sikri, Adv. for R-3.

CORAM:

HON’BLE MR. JUSTICE YASHWANT VARMA

J U D G M E N T

1. The writ petitioner has approached this Court aggrieved by the action  of the second respondent in forfeiting the bid security which was submitted  by it in the course of a process for award of contract initiated by that  respondent. The challenge essentially is to the communication of 18 March  2019 & 28 May 2019 pursuant to which the second respondent apprised the  petitioner of its decision to forfeit the bid security which had been submitted.

W.P.(C) 8779/2019 Page 1 of 45

2. The second respondent had invited Requests For Proposal1for  selection of developer cum operators of a proposed five-star hotel at the  International Exhibition Cum Convention Center [IECC] at Pragati Maidan,  New Delhi. The proposals were invited on terms which are set forth in the  RFP which stands placed as Annexure P-6. The RFP was published on 06  December 2018. 

3. A process of pre-bid queries was initiated soon thereafter and on 20  December 2018 while addressing queries raised by a prospective bidder, the  second respondent, while responding to that query, apprised all bidders that  no refund of bid security would be permitted in case the bidder chose to  withdraw from further participation after opening of technical bids. It  becomes relevant to note that in terms of the provisions of the RFP, the bid  security was prescribed to be Rs. 20 Crores. The relevant clause of the RFP  dealing with Bid Security is extracted hereinbelow: –

“3.3 RFP Fee and Bid Security

(a) As a part of the Proposal the interested Bidders will have to 

pay a non-refundable amount of INR 1,00,000 (Rupees one lakh 

only) plus Goods & Services Tax @ 18% (Eighteen Percent) as 

non-refundable processing fee (“RFP Fee“) for the RFP through

e- bidding portal’s electronic payment gateway, details of which 

are provided in Annexure 7.

(b) The Bidder shall be required to submit bid security amounting 

to INR 20,00,00,000 (Rupees twenty crore only) through e

payment via e-bidding portal’s electronic payment gateway (“Bid

1 RFP

W.P.(C) 8779/2019 Page 2 of 45

Security“) at the time of RFP submission. Proposals received

without specified bid security will be summarily rejected.

(c) Leasing authority will not be liable to pay any interest on the 

bid security. Bid security of unsuccessful bidders shall returned, 

without any interest within two months of signing the lease deed 

with the successful bidder or when the selection process cancelled 

by leasing authority. The bid security of the successful bidder will 

be returned after signing of lease deed or special purpose 

company as applicable and after receipt of performance 

guarantee.”

4. The response as tendered by the second respondent with respect to  the aforenoted query is extracted hereinbelow: –

S.No.Clause  Refer in  the RFPAs per RFPQueryReply
12.Section 3,  Clause 3.3 (c)Leasing authority will  not be liable to pay any  interest on the bid  security. Bid security  of unsuccessful bidders  shall be returned,  without any interest  within two months of  signing the lease deed  with the successful  bidder or when the  selection process  cancelled by leasing  authority. The bid  security of the  successful bidder will  be returned after  signing of lease deed ori) The Bid Security  of INR 20 crores  should be refunded  to any unsuccessful  bidder within 7  working days from  the declaration of  the Successful  Bidder. The RFP  may be suitably  amended  incorporating this  change. ii) The RFP should  allow refund of the  said Bid Security ofAgreed- Bid  Security of INR  20 crores shall be  refunded to  unsuccessful  bidders within 7  working days  from the  declaration of the  Successful  Bidder.

W.P.(C) 8779/2019 Page 3 of 45

  special purpose  company as applicable  and after receipt of  performance guarantee.  INR 20 Crores to the  entity submitting the  same in case it  wishes to withdraw  from further  participation, i.e., in  the second stage of  the bidding process.  This refund should  be made within 7  working days of the  entity (bidder)  informing the  authority of its  intention to not  participate further in  the bidding process.  .Not agreed. The  bid security will  be forfeited in case the bidder  withdraws from  further   participation after  opening of  technical bids  during the period  of validity.

5. During that process, the second respondent also clarified that the  bidding process does not envisage a minimum number of bidders. This is  evident from its reply to Query no.27 which is extracted hereinbelow: –

S.No.Clause  Refer in  the RFPAs per RFPQueryReply
27.NA There is no mention of  whether there are any  Minimum number of Bidders  and the process to be  followed if Bids are not  received from such Minimum  number of Bidders. The sameNot agreed. Shall  remain as per  RFP.

W.P.(C) 8779/2019 Page 4 of 45

   may be clarified and  mentioned in the RFP  accordingly. 

6. After completion of the aforesaid process, the second respondent  issued two corrigenda dated 08 January 2019 and 14 January 2019.  However, the responses which are noticed above were not introduced either  by way of an addendum or a clarification in the RFP. The petitioner  proceeded to submit its technical bid in January 2019. It becomes pertinent  to note that as per the terms of the RFP, the e-bidding process was divided  into two stages with the first being the submission of technical bids. The  successful bidder was to be identified in an e-auction which was proposed.  Clause 2.2(g) stipulated that only the technically qualified bidders would be  eligible for participation in the second stage of the bidding process which  contemplated the submission of financial bids. Clause (g) specifically  provided that no physical bids would be permitted to be submitted or  considered and that all financial bids would have to be submitted on the e bidding platform. The RFP further prescribed the Pre-set Reserve Price in  Clause 7.3(b)(ii) to be Rs. 611.30 Crores.

7. After the petitioner was found to be eligible and had passed the stage of examination of technical bids, the second respondent initiated the  process of e-bidding. Initially the e-bidding was fixed for 24 January 2019.  However, since the same was communicated to interested parties vide an  email of 22 January 2019 and the petitioner raised the issue of an extremely

W.P.(C) 8779/2019 Page 5 of 45

short notice having been given, it was postponed and rescheduled for 18  February 2019. By a communication of 11 February 2019, the petitioner  disclosed its relationship with another qualified bidder. The relationship of  the petitioner with the other qualified bidder was set forth in its  communications of 11 February 2019, 15 February 2019 and 18 February  2019. On 21 February 2019, the respondents apprised the petitioner that its  apprehensions were misplaced and that they did not, despite the disclosure  made, consider it to be ineligible or disqualified from participating in the  bidding process. The petitioner, thereafter, raised the same issue yet again  in terms of its communication of 25 February 2019 and further indicated  that it would be participating in the bidding process under coercion and  protest. The second respondent by its letter of 26 February 2019 apprised  the petitioner to withdraw the aforesaid communication. However, the  petitioner did not withdraw the letter and indicated that it would be  participating in the e-auction process. 

8. In the e-auction process which was conducted on 26 February 2019,  a bid was submitted by the other technically qualified bidder equivalent to  the pre-set reserve price. While the petitioner had also logged on to the e auction portal, it did not submit a bid higher than the existing bid amount as  was submitted by the other qualified bidder. The singular bid was not  accepted and the second respondent proceeded to cancel the-auction process itself. The respondent is thereafter stated to have issued a fresh RFP  on 05 March 2019. Since the bidding process in which the petitioner  participated was ultimately shelved, a request was submitted to the second

W.P.(C) 8779/2019 Page 6 of 45

respondent for refund of security. Responding to that request, the second  respondent proceeded to issue the impugned communication of 18 March  2019. The petitioner moved the second respondent seeking recall of its  decision and for refund of the bid security amount. However, this request  too was not acceded to and the petitioner apprised of the same by means of  the communication of 28 May 2019. It is, thereafter, that the present writ  petition came to be preferred before this Court. It may additionally be  noted that the bid security of the other bidder M/s Lulu International  Shopping Mall Pvt. Ltd. was subsequently refunded.

9. In order to appreciate the challenge which is raised, it would be  pertinent to extract the relevant parts of the e-bidding process which were set out in the RFP hereinbelow: –

“ANNEXURE – 7: TECHNICAL DETAILS WITH RESPECT TO ELECTRONIC  BIDDING A DEDICATED E-BIDDING PORTAL HAS BEEN 

CREATED BY

Submission of Bids

6. The first step towards submitting the bid is Accept Terms &Conditions  on the left side. Click on Accept Terms & Conditions and fill the form  given therein. Conditions with agree have to be necessarily agreed, while  in the conditions with empty remarks field bidder can give their  comments.

7. After the Accept Terms & Conditions are saved, click on attach  documents on the top.

8. Once the bidder selects from above, they will be required to upload  documents for the said event, A list of previously uploaded files will be  visible at the bottom of the screen. To revise a document please select the  same from the dropdown and upload the new document. Bidders can

W.P.(C) 8779/2019 Page 7 of 45

upload one document against each selection, document can be of any  size. Only PDF documents can be uploaded.

9. After the documents have been uploaded, the bidder can proceed to  saving the Eligibility Terms & Conditions and Price Offer fields. To fill  Accept Eligibility Terms & Conditions form click on Accept Eligibility  Terms &Conditions against any line item and fill the form therein.

10. Once Eligibility Terms & Conditions terms are saved, proceed with  submitting the Price Offer, here the bidder has to input the Price Offer as  per the RFP terms and conditions.

11. After the documents have been uploaded click on the final submit to  finally submit the bid. In case of any amendments after final submit click  on delete bid button to delete the Eligibility Terms & Conditions and  price bids and resubmit the same. The Bidder should also note that a  Bid will be considered as submitted if and only if the Bidder has  made such submission through the “Final Submission” button. Only  such Bids will be opened which have been finally submitted. It is  further clarified that saving of Technical Bid and the Price Offer  without final submission will be treated as non-submission of bid e Auction.

12. The bidders who qualify for e-auction as per rules stipulated in the RFP  document will be intimated about their qualification for electronic  auction through email. It shall be the sole responsibility of the Bidder to  regularly check its email. The Leasing Authority will not be responsible  for non-receipt of email by the Bidder and its consequences.

13. E-auction is the process of inviting binding Price Offer from qualified  bidders through internet for the purpose of determination of the Preferred  Bidder. During this process, the qualified bidder will be able to submit its  Price Offer as many times it wishes. The qualified bidder will remain

anonymous to other qualified bidders qualified bidders participating in  the electronic auction process as well as to the Leasing Authority. The  qualified bidders will be able to see the prevailing highest Price Offer,  but the name of the highest qualified bidder at any point of time will not

be displayed. The qualified bidder shall have to put its Price Offer above  the displayed highest bid become the highest qualified bidder. The  electronic auction process will have a scheduled start and close time  which will be displayed on screen. A qualified bidder will be able to put  its Price Offer after the start of bid time and till the close time of

W.P.(C) 8779/2019 Page 8 of 45

electronic auction. The current server time (IST) will also be displayed  on the screen. In the event a bid is received during the last 8 (eight)  minutes before the scheduled close time of electronic auction, the close  time of electronic auction will be automatically extended by 8 (eight)  minutes from the last received bid time to give equal opportunity to all  other qualified bidders. This process of auto extension will continue till  there is a period of 8 (eight) minutes during which no Price Offer are  received. 

14. For example, assuming that the initial scheduled close time for a  particular electronic auction is 1.00 pm and a Price Offer is received at  12.55 pm, the scheduled close time shall be revised to 1.03 pm. Again, if  a Price Offer is received at 1.01 pm, the scheduled close time shall be  revised to 1.09 pm and so on. In the event that there is no further Price  Offer received till 1.09 pm, the electronic auction will close at 1.09 pm.  The revised close time will be displayed on screen and the qualified  bidders should keep refreshing its webpage to get the latest information.”

10. Assailing the action of the respondents, Dr. Singhvi, learned Senior Counsel appearing for the petitioner, has addressed the following principal  submissions. It was firstly contended that the RFP as framed and drawn by  the second respondent nowhere contemplated a forfeiture of bid security on  a failure on the part of an interested bidder to submit a financial bid higher  than that which may have been submitted by a competitor. Dr. Singhvi,  would submit that the RFP also did not mandate the submission of a bid  higher than the pre-estimated reserve price which was prescribed. In view  of the above, it was submitted that the forfeiture of the bid security was  clearly de hors the provisions of the RFP and thus clearly illegal and  arbitrary. It was then submitted that the submission of a bid in an auction is  essentially a commercial decision and it would be wholly incorrect for the  respondent to assume that all successful bidders must necessarily submit a  bid higher than that which may have been submitted by another competing

W.P.(C) 8779/2019 Page 9 of 45

bidder. According to Dr. Singhvi, the submission of a financial bid must  necessarily be recognized as being a decision which must be left to the  commercial wisdom of the bidder and no principle in law places a bidder  under a compulsory obligation to advance forward in the bidding process or  to submit a bid higher than that submitted by a competing bidder

notwithstanding its own understanding and assessment of the financial  viability of proceeding further.

11. It was submitted that the clarification which was proffered by the  second respondent during the process of pre-bid queries cannot possibly be  viewed as a term which was binding upon the bidders especially when no  such provision stood incorporated in the RFP itself. It was argued that in the  absence of a specific clause entitling the second respondent to forfeit the  bid security on account of “non-improvement” of a quoted financial bid, the  action of the respondents is clearly rendered arbitrary and ultra vires. In  support of the aforesaid submission, learned Senior Counsel placed reliance  upon the decision of the Supreme Court in Union of India v. Vertex  Broadcasting Co. Private Ltd. & Ors.2and more particularly to the  observations as entered in paragraphs 9 and 10 of the report which read  thus:

“9. We have already taken the view that the Union had departed from the  terms of NIT and had incorporated new/additional terms and conditions  in LOI and the draft licence agreements which were finalised by the  Union after exchange of correspondence with the licensees. The precise  

2 (2015) 16 SCC 198

W.P.(C) 8779/2019 Page 10 of 45

content of the departures made has also been set out above. Inherent in  the said finding would be a further determination of the unjustifiability of  the action of the Union in forfeiting the licence fee. The Union could not  have departed from the terms of NIT unilaterally and on the refusal of the  licensees to accept such modified terms and act in terms of LOIs granted  to them the Union could not have resorted to the forfeiture as made. This  is irrespective of the question of the existence of any enabling provision  in NIT for forfeiture of the licence fee.

10. Coming to the aforesaid question of availability of a power to order  forfeiture, a reading of the relevant clauses i.e. Clauses 8(f), 10(d) and 12  extracted above would go to show that the Union had not  protected/empowered itself to forfeit the licence fee. The forfeiture  contemplated by the aforesaid clauses are altogether in different contexts  and situations. In the absence of any such power, the forfeiture that has  taken place in this case will have to be adjudged as null and void.”

12. Additionally, and to buttress the submissions aforenoted, Dr. Singhvi  further placed reliance upon the following observations as made by the  Supreme Court in Suresh Kumar Wadhwa v. State of M.P. & Ors.3 which are reproduced hereinbelow: –

“33. The learned counsel for the respondent State, however, argued that it  was not necessary for the State to specify the condition relating to  forfeiture and four additional terms/conditions in the public notice  because they were already part of RBC, which is applicable to the nazul  lands in question.

34. We find no merit in this submission for more than one reason. First,  the public notice inviting bids did not even contain a term that all the  provisions of RBC will be applicable to the-auction proceedings and  second, the relevant clauses of RBC which, according to the State, were  to govern the-auction proceedings ought to have been quoted in verbatim  in the public notice itself. It was, however, not done.

3 (2017) 16 SCC 757

W.P.(C) 8779/2019 Page 11 of 45

35. In our considered opinion, the object behind publishing all material  term(s) is/are threefold. First, such term(s) is/are made known to the  contracting parties/bidders; second, parties/bidders become aware of their  rights, obligations, liabilities qua each other and also of the consequences  in the event of their non-compliances; and third, it empowers the State to  enforce any such term against the bidder in the event of any breach  committed by the bidder and lastly, when there are express terms in the  contract/public notice then parties are bound by the terms and their rights  are, accordingly, determined in the light of such terms in accordance with  law.

36. When we read the facts and law laid down by this Court in Maula  Bux v. Union of India [Maula Bux v. Union of India, (1969) 2 SCC 554]  and Shree Hanuman Cotton Mills v. Tata Air Craft Ltd. [Shree Hanuman  Cotton Mills v. Tata Air Craft Ltd., (1969) 3 SCC 522] , we find that  there was a specific clause of forfeiture in the contract in both the cases.  Such clause empowered one party to forfeit the earnest money/security  deposit in the event of non-performance of the terms of the contract. It is  in the light of such facts, their Lordships examined the question of  forfeiture in the context of Section 74 of the Contract Act. Such is not  the case here.

37. Our reasoning is supported by a recent decision of this Court in  Union of India v. Vertex Broadcasting Co. (P) Ltd. [Union of India v.  Vertex Broadcasting Co. (P) Ltd., (2015) 16 SCC 198 : (2016) 3 SCC  (Civ) 657] wherein their Lordships held inter alia that in the absence of  any power in the contract to forfeit the licence money deposited by the  licensee, the action of the Union to forfeit the licence fees is held  illegal. This is what was held: (SCC p. 203, para 10)

“10. Coming to the aforesaid question of availability of a power to order forfeiture, a reading of the relevant clauses i.e. Clauses  8(f), 10(d) and 12 extracted above would go to show that the Union  had not protected/empowered itself to forfeit the licence fee. The  forfeiture contemplated by the aforesaid clauses are altogether in  different contexts and situations. In the absence of any such power,  the forfeiture that has taken place in this case will have to be  adjudged as null and void.”

W.P.(C) 8779/2019 Page 12 of 45

40. In the light of the foregoing discussion, we are of the considered  opinion that the appellant did not commit any breach of the term(s) and  condition(s) of the notice inviting bids and on the other hand, it was the  respondents who committed breaches. In these circumstances, the State  had no right to forfeit the security amount and instead it should have been  returned when demanded by the appellant.”

13. Proceeding further, Dr. Singhvi submitted that the forfeiture of bid  security in the facts of the present case would clearly amount to a penal  action and in fact an attempt by a public body to unjustly enrich itself.  According to Dr. Singhvi, the forfeiture of bid security would have to  necessarily meet the tests of manifest arbitrariness and in case where one  finds that the decision is wholly arbitrary, unjust or unfair, the same would  be liable to be quashed by the Court. In support of the aforesaid submission,  Dr. Singhvi has drawn the attention of the Court to the principles  enunciated by the Division Bench of this Court in Simplex Infrastructures  Limited Vs. National Highways Authority of India and Ors.4 where the  Court proceeded to hold thus: –

“11. What has been stressed upon by the petitioner is that without  affording any opportunity to the petitioner of being heard and without  taking into account the fact that the order of debarment in the first  instance was not known to the petitioner when the technical bid was  submitted and that such order of debarment was under temporary  suspension by the order of High Court of Guwahati, the order of  forfeiture of the bid amount was absolutely unjustified, arbitrary and  unsustainable in the eyes of law. It was also argued that no loss was  suffered by the respondent No. 1 as the bid of the petitioner was rejected  at the threshold and that the petitioner was agreeable for forfeiture of an 

4 MANU/DE/0623/2017

W.P.(C) 8779/2019 Page 13 of 45

amount of Rs. 30,000/- towards tender document fee and Rs. 1295/- towards tender processing fee.

12. Reference was made to Lanco Infratech Ltd. v. National Highways  Authority of India & Anr, MANU/DE/0331/2016 and Ashoka Buildcon  Limited & Anr v. National Highways Authority of India & Ors. [W.P(C)  No. 76/2015 in which judgment was delivered on 06.03.2017].

13. In Lanco Infratech Ltd. (Supra) a Bench of this Court had the  occasion to deal with a similar clause in the RFP regarding forfeiture and  it was held that the power to forfeit the bid was not compulsorily to be  invoked and a reasonable exercise of that power was warranted. In the  aforesaid case, the forfeiture was of 5% of the bid security on the ground  of the bid being non responsive. However, the bid of the petitioner, in  that case, was held to be responsive and forfeiture was found to have  been effected without any quantification of the damage suffered. The  Division Bench but did not have the occasion to examine the  enforceability of the forfeiture clause especially in view of the  provisions of Section 74 of the Indian Contract Act, 1872.”

14. The imperative requirement of a clause for forfeiture being specifically found in the offer document was also highlighted by a learned  Judge of this Court in M.C. Luthra v. Ashok Kumar Khanna,5in the  following terms: –

“6.

xxxx xxxx xxxx

41. Law is, therefore, clear that to justify the forfeiture of advance money  being part of „earnest money‟ the terms of the contract should be clear  and explicit. earnest money is paid or given at the time when the contract  is entered into and, as a pledge for its due performance by the depositor  to be forfeited in case of non-performance, by the depositor. There can be  converse situation also that if the seller fails to perform the contract the  purchaser can also get the double the amount, if it is so stipulated. It is    

5 2018 SCC OnLine Del 7462

W.P.(C) 8779/2019 Page 14 of 45

also the law that part payment of purchase price cannot be forfeited  unless it is a guarantee for the due performance of the contract. In other  words, if the payment is made only towards part payment of  consideration and not intended as earnest money then the forfeiture  clause will not apply.

42. In view of the legal proposition as discussed above, in facts and  circumstances of the case while I have already held that both the parties  cannot be held guilty for non-compliance of terms of agreement,  therefore, defendant to my mind is also not entitled for forfeiture of entire  earnest amount. In peculiar facts and circumstances of the case while I  decide the issue no. 1 that defendant has discharged all his liabilities,  therefore, plaintiff is not entitled for double of the amount as claimed.  Therefore, plaintiff to my mind is entitled for recovery of only Rs. 9 lacs  admittedly paid by him to defendant as earnest money however, plaintiff is entitled for such recovery of amount with interest @12 % from the date  of filing of the suit till realization. Above said issues are being  accordingly decided.” (underlining added)”

15. It was then contended that the forfeiture of bid security can only find  sanction in a situation where it is established that an actual loss had in fact  been suffered. Proceeding along these lines, Dr. Singhvi submitted that  even if actual loss had not been established, it would still be incumbent  upon the respondents to prove that the bid security would represent a  genuine pre-estimate of loss that may have been caused. Reliance in this  respect was laid upon the following passages as appearing in the decision of  the Supreme Court in Kailash Nath Associates v. DDA & Anr.6 which  read thus:

“32. By an amendment made in 1899, the section was amended to read: “74.Compensation for breach of contract where penalty  

stipulated for.— When a contract has been broken, if a sum is named in  the contract as the amount to be paid in case of such breach, or if the  

6 (2015) 4 SCC 136

W.P.(C) 8779/2019 Page 15 of 45

contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or  loss is proved to have been caused thereby, to receive from the party  who has broken the contract reasonable compensation not exceeding the  

amount so named or, as the case may be, the penalty stipulated for. Explanation.—A stipulation for increased interest from the date  of default may be a stipulation by way of penalty.

Exception.—When any person enters into any bail-bond,  recognizance or other instrument of the same nature, or, under the  provisions of any law, or under the orders of the Central Government or  of any State Government, gives any bond for the performance of any  public duty or act in which the public are interested, he shall be liable,  upon breach of any condition of any such instrument, to pay the whole  sum mentioned therein.

Explanation.—A person who enters into a contract with  Government does not necessarily thereby undertake any public duty, or  promise to do an act in which the public are interested.”

33. Section 74 occurs in Chapter 6 of the Contract Act, 1872 which reads  “Of the consequences of breach of contract”. It is in fact sandwiched  between Sections 73 and 75 which deal with compensation for loss or  damage caused by breach of contract and compensation for damage  which a party may sustain through non-fulfilment of a contract after  such party rightfully rescinds such contract. It is important to note that  like Sections 73 and 75, compensation is payable for breach of contract  under Section 74 only where damage or loss is caused by such breach.

34. In Fateh Chand v. Balkishan Dass [Fateh Chand v. Balkishan Dass,  (1964) 1 SCR 515 : AIR 1963 SC 1405] , this Court held: (SCR pp. 526- 27 & 530 : AIR pp. 1410-12, paras 8, 10 and 15)

“The section is clearly an attempt to eliminate the somewhat  elaborate refinements made under the English common law in  distinguishing between stipulations providing for payment of  liquidated damages and stipulations in the nature of penalty.  Under the common law a genuine pre-estimate of damages by  mutual agreement is regarded as a stipulation naming liquidated  damages and binding between the parties: a stipulation in a  contract in terrorem is a penalty and the Court refuses to enforce

W.P.(C) 8779/2019 Page 16 of 45

it, awarding to the aggrieved party only reasonable compensation.  The Indian Legislature has sought to cut across the web of rules  and presumptions under the English common law, by enacting a  uniform principle applicable to all stipulations naming amounts to  be paid in case of breach, and stipulations by way of penalty….

***

Section 74 of the Contract Act deals with the measure of damages  in two classes of cases (i) where the contract names a sum to be paid in  case of breach and (ii) where the contract contains any other stipulation  by way of penalty. We are in the present case not concerned to decide  whether a covenant of forfeiture of deposit for due performance of a  contract falls within the first class. The measure of damages in the case of  breach of a stipulation by way of penalty is by Section 74 reasonable  compensation not exceeding the penalty stipulated for. In assessing  damages the Court has, subject to the limit of the penalty stipulated,  jurisdiction to award such compensation as it deems reasonable having  regard to all the circumstances of the case. Jurisdiction of the Court to  award compensation in case of breach of contract is unqualified except  as to the maximum stipulated; but compensation has to be reasonable,  and that imposes upon the Court duty to award compensation according  to settled principles. The section undoubtedly says that the aggrieved  party is entitled to receive compensation from the party who has  broken the contract, whether or not actual damage or loss is proved to  have been caused by the breach. Thereby it merely dispenses with  proof of „actual loss or damages‟; it does not justify the award of  compensation when in consequence of the breach no legal injury at all  has resulted, because compensation for breach of contract can be  awarded to make good loss or damage which naturally arose in the  usual course of things, or which the parties knew when they made  the contract, to be likely to result from the breach.

***

Section 74 declares the law as to liability upon breach of contract where  compensation is by agreement of the parties pre-determined, or where  there is a stipulation by way of penalty. But the application of the

W.P.(C) 8779/2019 Page 17 of 45

enactment is not restricted to cases where the aggrieved party claims  relief as a plaintiff. The section does not confer a special benefit upon  any party; it merely declares the law that notwithstanding any term in the  contract pre-determining damages or providing for forfeiture of any  property by way of penalty, the court will award to the party aggrieved  only reasonable compensation not exceeding the amount named or  penalty stipulated. The jurisdiction of the court is not determined by the  accidental circumstance of the party in default being a plaintiff or a  defendant in a suit. Use of the expression „to receive from the party who  has broken the contract‟ does not predicate that the jurisdiction of the  court to adjust amounts which have been paid by the party in default  cannot be exercised in dealing with the claim of the party complaining of  breach of contract. The court has to adjudge in every case reasonable  compensation to which the plaintiff is entitled from the defendant on  breach of the contract. Such compensation has to be ascertained having  regard to the conditions existing on the date of the breach.”

35. Similarly, in Maula Bux v. Union of India [Maula Bux v. Union of  India, (1969) 2 SCC 554 : (1970) 1 SCR 928] , it was held: (SCR pp.  933-34 : SCC pp. 559-60, paras 5-7)

“Forfeiture of earnest money under a contract for sale of property  — movable or immovable—if the amount is reasonable, does not  fall within Section 74. That has been decided in several  cases: Chiranjit Singh v. Har Swarup [AIR 1926 PC 1 : (1926) 23  LW 172] , Roshan Lal v. Delhi Cloth and General Mills Co.  Ltd. [ILR (1911) 33 All 166] , Mohd. Habibullah v. Mohd.  Shafi [ILR (1919) 41 All 324] , Bishan Chand v. Radha Kishan  Das [ILR (1897) 19 All 489] . These cases are easily explained,  for forfeiture of a reasonable amount paid as earnest money does  not amount to imposing a penalty. But if forfeiture is of the nature  of penalty, Section 74 applies. Where under the terms of the  contract the party in breach has undertaken to pay a sum of  money or to forfeit a sum of money which he has already paid to  the party complaining of a breach of contract, the undertaking is  of the nature of a penalty.

W.P.(C) 8779/2019 Page 18 of 45

Counsel for the Union, however, urged that in the present case Rs  10,000 in respect of the potato contract and Rs 8500 in respect of the  poultry contract were genuine pre-estimates of damages which the Union  was likely to suffer as a result of breach of contract, and the plaintiff was  not entitled to any relief against forfeiture. Reliance in support of this  contention was placed upon the expression (used in Section 74 of the  contract Act), „the party complaining of the breach is entitled, whether or  not actual damage or loss is proved to have been caused thereby, to  receive from the party who has broken the contract reasonable  compensation‟. It is true that in every case of breach of contract the  person aggrieved by the breach is not required to prove actual loss or  damage suffered by him before he can claim a decree, and the Court is  competent to award reasonable compensation in case of breach even if no  actual damage is proved to have been suffered in consequence of the  breach of contract. But the expression „whether or not actual damage or  loss is proved to have been caused thereby‟ is intended to cover different  classes of contracts which come before the courts. In case of breach of  some contracts it may be impossible for the court to assess compensation  arising from breach, while in other cases compensation can be calculated  in accordance with established rules. Where the court is unable to assess  the compensation, the sum named by the parties if it be regarded as a  genuine pre-estimate may be taken into consideration as the measure of  reasonable compensation, but not if the sum named is in the nature of a  penalty. Where loss in terms of money can be determined, the party  claiming compensation must prove the loss suffered by him.

In the present case, it was possible for the Government of India to lead  evidence to prove the rates at which potatoes, poultry, eggs and fish were  purchased by them when the plaintiff failed to deliver „regularly and  fully‟ the quantities stipulated under the terms of the contracts and after  the contracts were terminated. They could have proved the rates at which  they had to be purchased and also the other incidental charges incurred  by them in procuring the goods contracted for. But no such attempt was  made.”

36. In Shree Hanuman Cotton Mills v. Tata Air Craft Ltd. [Shree  Hanuman Cotton Mills v. Tata Air Craft Ltd., (1969) 3 SCC 522 : (1970)

W.P.(C) 8779/2019 Page 19 of 45

3 SCR 127] , it was held: (SCR pp. 139 and 142 : SCC pp. 531 and 533- 34, paras 21 and 28-29)

“From a review of the decisions cited above, the following  principles emerge regarding „earnest‟:

(1) It must be given at the moment at which the contract is 

concluded.

(2) It represents a guarantee that the contract will be 

fulfilled or, in other words, „earnest‟ is given to bind the 

contract.

(3) It is part of the purchase price when the transaction is 

carried out.

(4) It is forfeited when the transaction falls through by 

reason of the default or failure of the purchaser.

(5) Unless there is anything to the contrary in the terms of 

the contract, on default committed by the buyer, the seller 

is entitled to forfeit the earnest.

***

The learned Attorney General very strongly urged that the pleas  covered by the second contention of the appellant had never been raised  in the pleadings nor in the contentions urged before the High Court. The  question of the quantum of earnest deposit which was forfeited being  unreasonable or the forfeiture being by way of penalty, were never raised  by the appellants. The Attorney General also pointed out that as noted by  the High Court the appellants led no evidence at all and, after abandoning  the various pleas taken in the plaint, the only question pressed before the  High Court was that the deposit was not by way of earnest and hence the  amount could not be forfeited. Unless the appellants had pleaded and  established that there was unreasonableness attached to the amount  required to be deposited under the contract or that the clause regarding  forfeiture amounted to a stipulation by way of a penalty, the respondents  had no opportunity to satisfy the Court that no question of  unreasonableness or the stipulation being by way of penalty arises. He  further urged that the question of unreasonableness or otherwise

W.P.(C) 8779/2019 Page 20 of 45

regarding earnest money does not at all arise when it is forfeited  according to the terms of the contract.

In our opinion the learned Attorney General is well founded in his  contention that the appellants raised no such contentions covered by the  second point, noted above. It is therefore unnecessary for us to go into the  question as to whether the amount deposited by the appellants, in this  case, by way of earnest and forfeited as such, can be considered to be  reasonable or not. We express no opinion on the question as to whether  the element of unreasonableness can ever be considered regarding the  forfeiture of an amount deposited by way of earnest and if so what are the  necessary factors to be taken into account in considering the  reasonableness or otherwise of the amount deposited by way of earnest.  If the appellants were contesting the claim on any such grounds, they  should have laid the foundation for the same by raising appropriate pleas  and also led proper evidence regarding the same, so that the respondents  would have had an opportunity of meeting such a claim.”

37. And finally in ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] , it  was held: (SCC pp. 740-43, paras 64 & 67-68)

64. It is apparent from the aforesaid reasoning recorded by the  Arbitral Tribunal that it failed to consider Sections 73 and 74 of  the Contract Act and the ratio laid down in Fateh Chand  case [Fateh Chand v. Balkishan Dass, (1964) 1 SCR 515 : AIR  1963 SC 1405] , SCR at p. 526 wherein it is specifically held that  jurisdiction of the court to award compensation in case of breach  of contract is unqualified except as to the maximum stipulated;  and compensation has to be reasonable. Under Section 73, when a  contract has been broken, the party who suffers by such breach is  entitled to receive compensation for any loss caused to him which  the parties knew when they made the contract to be likely to result  from the breach of it. This section is to be read with Section 74,  which deals with penalty stipulated in the contract, inter alia  (relevant for the present case) provides that when a contract has  been broken, if a sum is named in the contract as the amount to be  paid in case of such breach, the party complaining of breach is  entitled, whether or not actual loss is proved to have been caused,

W.P.(C) 8779/2019 Page 21 of 45

thereby to receive from the party who has broken the contract  reasonable compensation not exceeding the amount so named.  Section 74 emphasises that in case of breach of contract, the party  complaining of the breach is entitled to receive reasonable  compensation whether or not actual loss is proved to have been  caused by such breach. Therefore, the emphasis is on reasonable  compensation. If the compensation named in the contract is by  way of penalty, consideration would be different and the party is  only entitled to reasonable compensation for the loss suffered. But  if the compensation named in the contract for such breach is  genuine pre-estimate of loss which the parties knew when they  made the contract to be likely to result from the breach of it, there  is no question of proving such loss or such party is not required to  lead evidence to prove actual loss suffered by him.…

***

67. … In our view, in such a contract, it would be difficult to  prove exact loss or damage which the parties suffer because of the  breach thereof. In such a situation, if the parties have pre estimated such loss after clear understanding, it would be totally  unjustified to arrive at the conclusion that the party who has  committed breach of the contract is not liable to pay  compensation. It would be against the specific provisions of  Sections 73 and 74 of the Contract Act. There was nothing on  record that compensation contemplated by the parties was in any  way unreasonable. It has been specifically mentioned that it was  an agreed genuine pre-estimate of damages duly agreed by the  parties. It was also mentioned that the liquidated damages are not  by way of penalty. It was also provided in the contract that such  damages are to be recovered by the purchaser from the bills for  payment of the cost of material submitted by the contractor. No  evidence is led by the claimant to establish that the stipulated  condition was by way of penalty or the compensation  contemplated was, in any way, unreasonable. There was no  reason for the Tribunal not to rely upon the clear and  unambiguous terms of agreement stipulating pre-estimate

W.P.(C) 8779/2019 Page 22 of 45

damages because of delay in supply of goods. Further, while  extending the time for delivery of the goods, the respondent was  informed that it would be required to pay stipulated damages.

68. From the aforesaid discussions, it can be held that:

(1) Terms of the contract are required to be taken into  consideration before arriving at the conclusion whether the party  claiming damages is entitled to the same.

(2) If the terms are clear and unambiguous stipulating the  liquidated damages in case of the breach of the contract unless it  is held that such estimate of damages/compensation is  unreasonable or is by way of penalty, party who has committed  the breach is required to pay such compensation and that is  what is provided in Section 73 of the Contract Act.

(3) Section 74 is to be read along with Section 73 and, therefore,  in every case of breach of contract, the person aggrieved by the  breach is not required to prove actual loss or damage suffered by  him before he can claim a decree. The court is competent to  award reasonable compensation in case of breach even if no  actual damage is proved to have been suffered in consequence of  the breach of a contract.

(4) In some contracts, it would be impossible for the court to  assess the compensation arising from breach and if the  compensation contemplated is not by way of penalty or  unreasonable, the court can award the same if it is genuine pre

estimate by the parties as the measure of reasonable  compensation.”

38. It will be seen that when it comes to forfeiture of earnest  money, in Fateh Chand case [Fateh Chand v. Balkishan Dass,  (1964) 1 SCR 515 : AIR 1963 SC 1405] , the counsel for the  appellant conceded on facts that Rs 1000 deposited as earnest  money could be forfeited. (See SCR at pp. 525 and 531.)

W.P.(C) 8779/2019 Page 23 of 45

39.Shree Hanuman Cotton Mills [Shree Hanuman Cotton  Mills v. Tata Air Craft Ltd., (1969) 3 SCC 522 : (1970) 3 SCR  127] which was so heavily relied on by the Division Bench  again was a case where the appellants conceded that they  committed breach of contract. Further, the respondents also  pleaded that the appellants had to pay them a sum of Rs 42,499  for loss and damage sustained by them. (See SCR at p. 132). This  being the fact situation, only two questions were argued before  the Supreme Court: (1) that the amount paid by the plaintiff is  not earnest money; and (2) that forfeiture of earnest money can be  legal only if the amount is considered reasonable (SCR at p. 133).  Both questions were answered against the appellant. In deciding  Question (2) against the appellant, this Court held: (SCC p. 534,  para 31 : SCR p. 143)

“… But, as we have already mentioned, we do not propose 

to go into those aspects in the case on hand. As mentioned 

earlier, the appellants never raised any contention that 

the forfeiture of the amount amounted to a penalty or that 

the amount forfeited is so large that the forfeiture is bad in 

law. Nor have they raised any contention that the amount 

of deposit is so unreasonable and therefore forfeiture of 

the entire amount is not justified. The decision in Maula 

Bux [Maula Bux v. Union of India, (1969) 2 SCC 554 : 

(1970) 1 SCR 928] had no occasion to consider the 

question of reasonableness or otherwise of the earnest 

deposit being forfeited. Because, from the said judgment it 

is clear that this Court did not agree with the view of the 

High Court that the deposits made, and which were under 

consideration, were paid as earnest money. It is under 

those circumstances that this Court proceeded to 

consider the applicability of Section 74 of the Contract 

Act.”

40. From the above, it is clear that this Court held that Maula Bux  case [Maula Bux v. Union of India, (1969) 2 SCC 554 : (1970) 1 SCR  928] was not, on facts, a case that related to earnest money.

W.P.(C) 8779/2019 Page 24 of 45

Consequently, the observation in Maula Bux [Maula Bux v. Union of  India, (1969) 2 SCC 554 : (1970) 1 SCR 928] that forfeiture of earnest  money under a contract if reasonable does not fall within Section 74, and  would fall within Section 74 only if earnest money is considered a  penalty is not on a matter that directly arose for decision in that case.  The law laid down by a Bench of five Judges in Fateh Chand case [Fateh  Chand v. Balkishan Dass, (1964) 1 SCR 515 : AIR 1963 SC 1405] is  that all stipulations naming amounts to be paid in case of breach would  be covered by Section 74. This is because Section 74 cuts across the rules  of the English common law by enacting a uniform principle that would  apply to all amounts to be paid in case of breach, whether they are in the  nature of penalty or otherwise. It must not be forgotten that as has been  stated above, forfeiture of earnest money on the facts in Fateh Chand case [Fateh Chand v. Balkishan Dass, (1964) 1 SCR 515 : AIR 1963 SC  1405] was conceded. In the circumstances, it would therefore be correct  to say that as earnest money is an amount to be paid in case of breach of  contract and named in the contract as such, it would necessarily be  covered by Section 74.

41. It must, however, be pointed out that in cases where a public auction  is held, forfeiture of earnest money may take place even before an  agreement is reached, as DDA is to accept the bid only after the earnest  money is paid. In the present case, under the terms and conditions of  auction, the highest bid (along with which earnest money has to be  paid) may well have been rejected. In such cases, Section 74 may not be  attracted on its plain language because it applies only “when a contract  has been broken”.

42. In the present case, forfeiture of earnest money took place long after  an agreement had been reached. It is obvious that the amount sought to  be forfeited on the facts of the present case is sought to be forfeited  without any loss being shown. In fact it has been shown that far from  suffering any loss, DDA has received a much higher amount on re

auction of the same plot of land.

43. On a conspectus of the above authorities, the law on compensation  for breach of contract under Section 74 can be stated to be as follows:

W.P.(C) 8779/2019 Page 25 of 45

43.1. Where a sum is named in a contract as a liquidated amount payable  by way of damages, the party complaining of a breach can receive as  reasonable compensation such liquidated amount only if it is a genuine  pre-estimate of damages fixed by both parties and found to be such by the  court. In other cases, where a sum is named in a contract as a liquidated  amount payable by way of damages, only reasonable compensation can  be awarded not exceeding the amount so stated. Similarly, in cases where  the amount fixed is in the nature of penalty, only reasonable  compensation can be awarded not exceeding the penalty so stated. In  both cases, the liquidated amount or penalty is the upper limit beyond  which the court cannot grant reasonable compensation.

43.2. Reasonable compensation will be fixed on well-known principles  that are applicable to the law of contract, which are to be found inter alia  in Section 73 of the Contract Act.

43.3. Since Section 74 awards reasonable compensation for damage or  loss caused by a breach of contract, damage or loss caused is a sine qua  non for the applicability of the section.

43.4. The section applies whether a person is a plaintiff or a defendant in  a suit.

43.5. The sum spoken of may already be paid or be payable in future.

43.6. The expression “whether or not actual damage or loss is proved to  have been caused thereby” means that where it is possible to prove actual  damage or loss, such proof is not dispensed with. It is only in cases where  damage or loss is difficult or impossible to prove that the liquidated  amount named in the contract, if a genuine pre-estimate of damage or  loss, can be awarded.

43.7. Section 74 will apply to cases of forfeiture of earnest money under  a contract. Where, however, forfeiture takes place under the terms and  conditions of a public auction before agreement is reached, Section 74  would have no application.”

16. Dr. Singhvi has further drawn the attention of the Court to a tabulated  statement of expenses incurred by the second respondent and which stands

W.P.(C) 8779/2019 Page 26 of 45

placed as Annexure P-6 to the writ petition. From that tabulated statement  and which in turn was based upon the disclosures obtained by the  petitioners by invoking the Right to Information Act, 2005, Dr. Singhvi  contended that it is manifest that no loss at all was caused to the  respondents.

17. Refuting the aforesaid submissions, Mr. Saurabh Sharma, learned  counsel for the second respondent, addressed the following submissions. It  was firstly contended that the response as proffered by the said respondent  during the pre-bid query process clearly placed all intending bidders on  notice of the pre-bid security being liable to be forfeited in case any one of  them chose to withdraw after qualifying the process of scrutiny of technical  bids. Learned counsel submits that undisputedly and although the petitioner  did log on to the e-bidding portal, it failed to submit a bid higher than that  existing and this act would clearly amount to it withdrawing from the  bidding process. Much emphasis was laid on the stature of the petitioner  being one of the leading hoteliers of the country and its failure to submit a  bid higher than the pre-estimated reserve price.

18. Learned counsel would contend that the petitioner had clearly  expressed its reluctance to proceed in the biding process as would be  evident from its communications addressed to the second respondent  disclosing its relationship with the other successful bidder and that it is this  fact alone which appears to have influenced its decision not to submit a bid. Learned counsel argues that the petioner failed to act upon the explicit

W.P.(C) 8779/2019 Page 27 of 45

assurance offered by the second respondent which had clearly expressed its  decision that it would not stand disqualified or be rendered ineligible  notwithstanding its disclosed relationship with the other successful bidder. According to learned counsel, the facts leading up to the commencement of  the bidding process would clearly establish that the petitioner chose to  withdraw from the bidding process without justifiable cause and was only  seeking an excuse to wriggle out from its obligation to proceed further.  According to learned counsel, the action of the petitioner forced the second  respondent to cancel the entire-auction process and thus clearly justifying  the forfeiture of bid security. 

19. Learned counsel further urged that the forfeiture of bid security  would be in consonance with the well settled principles as propounded by  the Supreme Court in State of Haryana v. Malik Traders7 where upon a  consideration of the provisions made in the Contract Act, it was held as  follows:-

“14. The High Court in that case formulated two questions viz.:

(a) whether the forfeiture of security deposit was without authority of law  and without any binding contract between the parties and also contrary to  Section 5 of the Contract Act; and

(b) whether the writ petition was maintainable in a claim arising out of a  breach of contract. Without considering Question (b), the High Court  allowed the writ petition on the ground that the offer was withdrawn  before it was accepted and thus no completed contract had come into  existence. The High Court observed that in law a party could always  

7 (2011) 13 SCC 200

W.P.(C) 8779/2019 Page 28 of 45

withdraw its offer before acceptance. Therefore, it held that the  invocation and encashment of the bank guarantee was illegal and void  and was liable to be set aside. The appellant then approached the  Supreme Court.

15. Allowing the appeal, this Court held as follows: (National Highways  Authority of India case [(2003) 7 SCC 410] , SCC p. 416, para 9)

9. In our view, the High Court fell in error in so holding. By  invoking the bank guarantee and/or enforcing the bid security,  there is no statutory right, exercise of which was being fettered.  There is no term in the contract which is contrary to the  provisions of the Contract Act, 1872. The Contract Act merely  provides that a person can withdraw his offer before its  acceptance. But withdrawal of an offer, before it is accepted, is a  completely different aspect from forfeiture of earnest/security  money which has been given for a particular purpose. A person  may have a right to withdraw his offer but if he has made his offer  on a condition that some earnest money will be forfeited for not  entering into contract or if some act is not performed, then even  though he may have a right to withdraw his offer, he has no right  to claim that the earnest/security be returned to him. Forfeiture of  such earnest/security, in no way, affects any statutory right under  

the Contract Act. Such earnest/security is given and taken to  ensure that a contract comes into existence. It would be an  anomalous situation that a person who, by his own conduct,  precludes the coming into existence of the contract is then  given advantage or benefit of his own wrong by not allowing  forfeiture. It must be remembered that, particularly in government  contracts, such a term is always included in order to ensure that only a genuine party makes a bid. If such a term was not there  even a person who does not have the capacity or a person who  has no intention of entering into the contract will make a bid. The  whole purpose of such a clause i.e. to see that only genuine bids  are received would be lost if forfeiture was not permitted.”

We respectfully agree with the above view of this Court.”

W.P.(C) 8779/2019 Page 29 of 45

20. It becomes pertinent to note that the decision in Malik Traders itself  proceeds on the basis of the judgment of the Supreme Court in National  Highways Authority of India v. Ganga Enterprises,8 where the following  pertinent observations came to be made: –

“9. In our view, the High Court fell in error in so holding. By invoking  the bank guarantee and/or enforcing the bid security, there is no statutory  right, exercise of which was being fettered. There is no term in the  contract which is contrary to the provisions of the Indian Contract Act.  The Indian Contract Act merely provides that a person can withdraw his  offer before its acceptance. But withdrawal of an offer, before it is  accepted, is a completely different aspect from forfeiture of  earnest/security money which has been given for a particular purpose. A  person may have a right to withdraw his offer but if he has made his offer  on a condition that some earnest money will be forfeited for not entering into contract or if some act is not performed, then even though he may  have a right to withdraw his offer, he has no right to claim that the  earnest/security be returned to him. Forfeiture of such earnest/security, in  no way, affects any statutory right under the Indian Contract Act. Such  earnest/security is given and taken to ensure that a contract comes into  existence. It would be an anomalous situation that a person who, by his  own conduct, precludes the coming into existence of the contract is then  given advantage or benefit of his own wrong by not allowing forfeiture. It  must be remembered that, particularly in government contracts, such a  term is always included in order to ensure that only a genuine party  makes a bid. If such a term was not there even a person who does not  have the capacity or a person who has no intention of entering into the  contract will make a bid. The whole purpose of such a clause i.e. to see  that only genuine bids are received would be lost if forfeiture was not  permitted.

10. There is another reason why the impugned judgment cannot be  sustained. It is settled law that a contract of guarantee is a complete and 

8 (2003) 7 SCC 410

W.P.(C) 8779/2019 Page 30 of 45

separate contract by itself. The law regarding enforcement of an “on demand bank guarantee” is very clear. If the enforcement is in terms of  the guarantee, then courts must not interfere with the enforcement of  bank guarantee. The court can only interfere if the invocation is against  the terms of the guarantee or if there is any fraud. Courts cannot restrain  invocation of an “on-demand guarantee” in accordance with its terms by  looking at terms of the underlying contract. The existence or non existence of an underlying contract becomes irrelevant when the  invocation is in terms of the bank guarantee. The bank guarantee  stipulated that if the bid was withdrawn within 120 days or if the  performance security was not given or if an agreement was not signed,  the guarantee could be enforced. The bank guarantee was enforced  because the bid was withdrawn within 120 days. Therefore, it could not  be said that the invocation of the bank guarantee was against the terms of  the bank guarantee. If it was in terms of the bank guarantee, one fails to  understand as to how the High Court could say that the guarantee could  not have been invoked. If the guarantee was rightly invoked, there was  no question of directing refund as has been done by the High Court.”

21. It is these rival submissions which fall for determination. From the  recordal of submissions addressed on behalf of the respondents, it transpires  that the action of forfeiture is premised on the perception of the second  respondent that a failure on the part of the petitioner to submit a price offer  higher than the prevailing bid amounted to a withdrawal from the-auction process. The power to forfeit the bid security is founded and asserted to  flow from the clarification proffered by the second respondent during the  course of addressing the pre bid queries which were received. 

22. The validity of the impugned action of forfeiture of bid security in  the present petition has two facets- firstly whether the second respondent  had the jurisdiction and authority to forfeit the bid security in terms of the  provisions made in the RFP and the pre bid queries which were addressed

W.P.(C) 8779/2019 Page 31 of 45

and secondly whether the forfeiture was justified in the facts of the present  case. While proceeding to deal with the jurisdictional challenge first, the  Court notes that the RFP made the following provisions for forfeiture of bid  security:-

“5. SECTION 5- PAYMENT TERMS

5.4 In case the Bidder(s) fails to deposit payment as per point 1 within the  timeframe given above, the Bid Security of the Bidder will be forfeited and the  bidder may be debarred upto 5 (five) years from participation in any future  bidding/tendering/RFP process of Leasing Authority and Tendering Authority.

5.5 In case a Bidder(s) deposit the payment as per point 1 above within the  time period given but fails to deposit payment as per point 1 within, the  timeframe given above, the Bid Security and the payment of the Bidder(s) as per  point 1 received earlier will be forfeited and the Bidder may be debarred upto 5  (five) years from participation in any future bidding/tendering/RFP process of  Leasing Authority or Tendering Authority.

5.6 After receipt of 100% payment the Leasing Authority will give  reasonable time to the Successful Bidder(s) for execution of the Lease Deed as  per the terms of this RFP. The Successful Bidder will be required to arrange the  requisite stamp papers (and other documents) and submit the complete  documents to the Leasing Authority at least 1 (one) working day before the  proposed date of execution of Lease Deed. In case the Successful Bidder is  unable or unwilling to provide the requisite documents including Performance  Guarantee or execute the same within the date stipulated by the Leasing  Authority, the RFP process will stand annulled. In such case the Tendering  Authority will forfeit the Bid Security and 25% (twenty five percent) of the total  amount received from the bidder and the bidder may be debarred up to 5 (five)  years from participation in any future bidding/ tendering/ RFP process of  Leasing Authority or Tendering Authority/.

6. SECTION 6- SCOPE OF WORK

6.5 In case of delay more than 6 (six) months in completion of the  parameters set out at serial nos. 1 to 3 above or delay of more than 12 (twelve)  months in completion of the parameter set out at serial no. 4 above, the Leasing  Authority shall be entitled to terminate the Lease Deed and take charge and  possession of the Hotel Premises and the site of the Project on “as is where is

W.P.(C) 8779/2019 Page 32 of 45

basis” and all rights of the Lessee with regard to the Hotel Premises, site,  building, material, equipments etc. will stand cancelled with immediate effect  and possession of the Hotel Premises will revert to the Leasing Authority with all  rights of the Successful Bidder without any further act of the parties. After such  termination, the Successful Bidder shall have no right or interest in respect of the  Hotel Premises on any property thereon or any part thereof and Leasing  Authority may, at its sole discretion re-tender the Hotel Premises or use it as per  their internal policy/decision. In case of such termination, the Leasing Authority  shall be entitled to charge a penalty at the rate of 18% (eighteen percent) per  annum on the total amount paid by the Successful Bidder by the Successful  Bidder subject to a minimum penalty of 50% (fifty per cent.) of the total amount  paid by the Successful Bidder in addition to forfeiture of the Performance  Guarantee and remaining amount paid by the Successful Bidder, after deduction  of the penalty, shall be returned to the Successful Bidder without any interest  thereon. The Leasing Authority may at its sole discretion on its own or through  any agency may dismantle the site at the Hotel Premises and e-auction the  material, equipment, building etc. therein. All proceeds of such sale will also be  in favour of the Leasing Authority, without any rights of the Successful Bidder.

7. SECTION 7- BID PROCESS DETAILS

7.3 Submission of Proposals

(i) Each Bidder who intends to participate in the RFP process will be  required to successfully complete the following on or prior to the last date for  submission of online Bid:

xxx xxx xxx

C. In case the information provided by the Bidders or the documents submitted by them are found to incorrect or false at any state during the bidding  process or subsequently their bid will stand annulled and the entire amount  submitted by them till that point will be forfeited unconditionally.

7.4 Proposal evaluation

xxx xxx xxx

(f) The Bidder(s) and their respective officers, employees, agents and advisers shall observe the highest standard of ethics during the Selection  Process. Notwithstanding anything to the contrary contained in this RFP,  the Tendering Authority will reject a Proposal without being liable in any  manner whatsoever to the Bidder, if it determines that the Bidder has,  directly or indirectly or through an agent, engaged in Corrupt Practice,

W.P.(C) 8779/2019 Page 33 of 45

Fraudulent Practice, Coercive Practice, Undesirable Practice Or  Restrictive Practice (as per the meaning ascribed to the terms in  Annexure 3 – Lease Deed and collectively the “Prohibited Practices”) in  respect of the Bidding Process. In such an event, the Tendering Authority  will, without prejudice to its any other rights or remedies, forfeit and  appropriate the Bid Security, as mutually agreed genuine pre-estimated  compensation and damages payable to the Tendering Authority for, inter  alia, time, cost and effort of the Tendering Authority, in regard to the  RFP, including consideration and evaluation of such Bidder’s Proposal.

23. As is evident from a reading of the aforesaid clauses, none of them  envisaged a forfeiture of security for reasons which form the bedrock of the  impugned action. The clauses extracted above far from justifying a  forfeiture, do not appear to even contemplate that action on grounds which  have weighed with the respondents. A forfeiture of bid security would  undoubtedly have grave civil consequences and therefore must be strictly  construed. In order for that punitive measure to be held to be justified, the  RFP or any other similar offer document inviting bids must clearly and  unambiguously specify the circumstances which would warrant and  sanction forfeiture. This position in law cannot possibly be disputed in light  of the principles enunciated by the Supreme Court in Vertex Broadcasting and reiterated in Suresh Kumar Wadhwa. As this Court reads the RFP  and the relevant clauses extracted above, it is of the firm view that none of  them stood attracted in the facts of the present case. The action of forfeiture  when tested on the anvil of the provisions contained in the RFP would thus  clearly appear to be ultra vires

24. Regard must be had to the fact that the second respondent justifies  the forfeiture not on the strength of any particular clause of the RFP but its

W.P.(C) 8779/2019 Page 34 of 45

response as given in the course of answering pre bid queries which were  raised. The submission of learned counsel in this respect was twofold.  Learned counsel firstly urged that the clarification which was proffered  placed parties on sufficient notice of its understanding of the terms of the  offer and the situations where a forfeiture would be considered valid.  Additionally, reliance was placed upon clauses 1 and 6 of the RFP to  submit that the clarification that was given was sufficient to bind parties.  While dealing with the second limb of the submission that was addressed  on this score, it would be appropriate to advert to those clauses which are  reproduced hereinbelow: –

“1. This request for proposal and any other documents and  information provided subsequently to the Bidders (defined hereinafter),  whether verbally, documentary, or any other form, by or on behalf of  Leasing Authority or Tendering Authority or any of their employees or  consultants or advisers, is provided to Bidders on the terms and  conditions set out in this RFP and such other terms and conditions subject  to which such additional documents and information shall be provided,  from time to time. In no circumstances shall the Tendering Authority or  Leasing Authority, or its employees, officers, directors, advisors,  consultants, contractors and/or agents incur any liability arising out of or  in respect of the issue of this RFP, or the Bidding Process set out herein.

2. This RFP is, or neither an offer nor invitation by Leasing  Authority / Tendering Authority or to the prospective Bidders or any  other person and no agreement or transaction shall be deemed to be  entered into, either oral or in writing, till the Definitive Documents  (defined hereinafter) are executed. The purpose of this RFP is to provide  interested parties with information that may be useful to them in the  formulation of their Bids, to be submitted pursuant to this RFP. This RFP  includes statements, which reflect various assumptions and assessments  arrived at by Leasing Authority or Tendering Authority as the case  maybe in relation to their business model The RFP, assumptions,  assessments, statements contained herein and any clarifications,

W.P.(C) 8779/2019 Page 35 of 45

amendments, additional information or addenda issued pursuant hereto  are only to provide selective summaries of available information and do  not purport to contain all the information that each Bidder may require  for the purposes of making a decision for participation in this Bidding  Process.

3. This RFP may not be appropriate for all persons, and it is not  possible for Leasing Authority / Tendering Authority, their employees or  consultants or advisers to consider the objectives, techno-commercial  expertise and particular needs of each Bidder who reads or uses this RFP.

This RFP is subject to updating, expansion, revision and amendment at  the sole discretion of the Leasing Authority and the Tendering Authority,  without the requirement of prior notices to the Bidders or any other  person. Each Bidder should, conduct its own investigations and analysis  and should check the accuracy, adequacy, correctness, reliability and  completeness of the assumptions, assessments and information contained  in this RFP and obtains independent advice from appropriate sources.

4. The information provided in this RFP to the Bidders is on a wide  range of matters, some of which depends upon interpretation of law. The  information given is not an exhaustive account of statutory requirements  and should not be regarded as a complete or authoritative statement of  law. The Leasing Authority and Tendering Authority accept no  responsibility for the accuracy or otherwise for any interpretation or  opinion on the law expressed herein.

5. Whilst the information in this RFP has been prepared in good  faith, no reliance shall be placed

on any information or statements contained herein, the Leasing Authority  or Tendering Authority, their employees, officers, directors, consultants  advisors, contractors and its agents make no representation or warranty  and shall have no liability to any person including any Bidder under any  law, statute, rules or regulations or tort, principles of restitution or unjust

enrichment or otherwise for any loss, damages, cost or expense which  may arise from or be incurred or suffered on account of anything  contained in this RFP or otherwise, including the accuracy, adequacy,  correctness, reliability or completeness of the RFP and any assessment,

W.P.(C) 8779/2019 Page 36 of 45

assumption, statement or information contained therein or deemed to  form part of this RFP or arising in any way in this selection process and it  shall not be assumed that such information or statements will remain  unchanged. The Leasing Authority and Tendering Authority also accept

no liability of any nature whether resulting from negligence or otherwise  caused or arising out of reliance of any Bidder upon the statements  contained in this RFP.

6. The Leasing Authority or Tendering Authority may in their  absolute discretion, but without being under any obligation to do so,  update, amend or supplement the information, assessment or assumption  contained in this RFP but do not undertake to provide any Bidder with  access to any additional information, or to update the information in this  RFP or to correct any inaccuracies herein.”

25. It would be pertinent to note that clauses 1 to 6 are placed in the  Chapter titled “Disclaimer”. The Court fails to appreciate how clauses  placed in a chapter dealing with a disclaimer could be read as sufficiently  empowering the second respondent to forfeit bid security on the strength of  a clarification which was offered in the course of responding to pre bid  queries. A disclaimer is essentially aimed at ensuring that the author of the  document inviting offers is not held responsible for any assumptions that an  intending bidder may choose to make. It essentially places the intending  bidder on notice of being obliged to exercise due diligence and caution  while forming a decision to participate in the bidding process. A disclaimer  essentially seeks to shield and insulate the entity inviting bids from any  liabilities that may arise or accrue in the course of the bidding process.  Clause 1 falling in this Chapter does just that and nothing more. Clause 2  merely placed the intending bidder on caution by specifically noting that  the RFP only constitutes a summary of the available information on the

W.P.(C) 8779/2019 Page 37 of 45

basis of which the bidder may form a decision to participate in the-auction process. 

26. Clauses 3 and 6 conferred a power of the second respondent to add,  amend or supplement the terms of the RFP at any time and at its sole  discretion. It would be pertinent to recall that while the terms of the RFP  were amended on two separate occasions prior to the commencement of the  actual bidding process, no express stipulation of forfeiture on account of a  purported withdrawal from the bidding process was inserted or introduced.  The second respondent had been duly apprised of a doubt that one of the  intending bidders harboured with respect to the issue of forfeiture and yet it  chose not to either amend or supplement the RFP to provision for a  forfeiture of bid security in case of withdrawal from the bidding process. In  any case, this Court is of the firm opinion that it would be unwise to  recognise a chapter dealing with disclaimers to be recognized as being the  repository of the power to forfeit.

27. The Court is further of the firm opinion that a response furnished to  queries by the second respondent cannot be placed on the same pedestal as  a clause contained in the RFP. This since they would not ipso facto become  part of the principal offer document. The answer to a query raised by an  intending bidder cannot be construed as attaining the mantle of a  substantive provision of the RFP. The queries do not instinctively acquire  binding effect similar to a provision laid down in the original offer  document. If a clause for forfeiture were to sustain, it was imperative for  the second respondent to have duly amended the RFP. A response that may

W.P.(C) 8779/2019 Page 38 of 45

have been proffered while attending to a query raised by an intending  bidder, in any case, was not provisioned to amount to an amendment to the  RFP itself. If the submission of the second respondent were to be accepted,  it would tantamount to the RFP being held to be suitably amended, altered  or supplemented based upon the responses that may be proffered during the  pre-bid process. On a more fundamental plane, the Court notes that even the  provisions contained in the chapter titled “Disclaimer” can neither be  interpreted nor construed as providing for responses submitted to pre bid  queries becoming substantive terms and conditions governing the bidding  process. The provisions which were relied upon cannot possibly be  interpreted as envisaging an answer to a query being deemed to have been  incorporated or integrated into the RFP.

28. The Court thus comes to conclude that no provision of the RFP  sanctioned forfeiture of bid security on a perceived withdrawal from the  bidding process. The RFP in that sense was and remained significantly  silent. For reasons aforenoted the Court also comes to the firm conclusion  that the explanation or clarification which was offered by the second  respondent while responding to queries during the pre-bid process would  also not come to its aid nor would it clothe the respondent with the  jurisdiction to forfeit bid security on that basis.

29. That then takes the Court to deal with the question of whether the  action of the petitioner amounted to a withdrawal from the bidding process.  To answer the issue that arises, it would be apposite to notice the procedure  prescribed for the e-auction. However, before proceeding to do so, it would

W.P.(C) 8779/2019 Page 39 of 45

be appropriate to briefly notice the concept of an e-bidding process. The e auction portal essentially creates a virtual auction room where interested  bidders submit their bids electronically. After registration on the platform,  the interested bidders are required to upload requisite documentation as  may be prescribed and submit their bids once the bidding window is  opened. Each valid bid that is submitted is then evaluated and if found to be  responsive in all other respects, the highest offer submitted comes to be  identified. The virtual platform so created dispenses with the requirement of  parties being physically present and enabling them to submit bids  electronically. The e-auction process was elaborately spelt out in Annexure  7 to the RFP. For our purposes it would be relevant to note the provisions  made in clauses 11 and 13 thereof. 

30. In the present case, the RFP in clause 11 clearly provided that an  interested bidder could submit multiple bids during the period when the e auction window remained open. The portal was to display a scheduled start  and close time during which period bids were to be submitted and  registered. The bid was to be submitted with the interested party pressing the “Final Submission” button and thus registering its offer on the platform.  While the identity of the interested bidders was to remain masked, any  bidder who had logged on to the-auction platform could see the prevailing  highest bid submitted and could submit an offer for an amount higher than  that holding the field at the relevant time. This process of submission of  bids and counter bids was envisaged to continue till the e-auction window  finally came to a close at the designated time and hour. The highest offer

W.P.(C) 8779/2019 Page 40 of 45

registered on the e-auction platform would thus be known at the close of the  aforesaid process. 

31. Significantly, however, the platform did not grant an option to a  bidder to match a prevailing price offer. Once a bidder had entered the  virtual auction room and was able to view the prevailing offer, it had no  option but to register a price offer higher than that recorded and displayed  on the portal. This is manifest from a reading of clause 13 which prescribed  that “The qualified bidder shall have to put its Price Offer above the  displayed highest bid to become the highest qualified bidder.” It is this  stipulation and the structure of the bidding process which constitutes the  genesis of the dispute inter partes. The consequential and ancillary question  which arises is whether a bidder who failed to better the prevailing highest  price offer could be said to have “withdrawn” from the-auction and thus  faced the specter of forfeiture of bid security. 

32. It would be pertinent to note that the submission of a bid in an  auction process is essentially a commercial decision which the party is  entitled to take based on its own assumption and judgment of what would  constitute a fair bargain. A party while participating in a bidding process  cannot be compelled by law to submit a bid which may be understood as  being reasonable and fair. The offer is one which must necessarily be left to  the judgment of the intending bidder. The only interdict which operates  upon the exercise of this discretion is of the bidder not being permitted to  submit an offer below the preset reserve price. The Court cannot discount a  situation where more than one bidder in the-auction process submits an

W.P.(C) 8779/2019 Page 41 of 45

offer which either equals the reserve price, may be marginally more than  that price or even equivalent to that offered by another. However, the mere  submission of an offer which equals the reserve price or a competing bid  cannot be viewed as being contrary to the obligation which otherwise  stands placed on a bidder. As was noticed hereinbefore, clause 13 placed  the intending bidder under a compulsion to submit a bid which was higher  than the one displayed on the portal at the relevant point in time. The bidder  was not conferred an option to equal a price bid which had already been  submitted and registered. If at that stage, a bidder chose not to increase the  bid or better the existing or prevailing offer, that cannot be interpreted as  amounting to a withdrawal from the-auction process. This is further evident  from the response of the second respondent itself which held out that the  bid security would be forfeited if the bidder were to withdraw from the auction process after qualifying the technical evaluation process. It is thus  evident that the second respondent itself understood and interpreted the  forfeiture clause as being applicable only in a situation where an intending  bidder chose not to participate in the financial bid process at all after it had  been found to be technically responsive. It is in that limited sense that the  expression “withdraw” is liable to be understood. 

33. In the facts of the present case, it is admitted that the petitioner  logged on to the portal during the financial bid submission process. The  second respondent interprets its failure to better the existing bid as being an  act of withdrawal. The aforesaid stance as struck is clearly unsustainable for  more than one reason. Firstly, the e-auction process structurally did not

W.P.(C) 8779/2019 Page 42 of 45

permit an intending bidder to submit an equivalent offer. It was essentially  designed for the second bidder to necessarily and compulsorily submit a  higher offer. It was this which constrained the petitioner from failing to  register a bid. However, this act cannot be viewed as amounting to a  withdrawal from the-auction process. Additionally, it may be noted that the  second respondent itself clarified that bid security would stand forfeited  only in case a bidder chose to exit the process after its bid had been found  to be technically responsive. In the facts of the present case, it cannot be  said that the action of the petitioner amounted to a withdrawal from the  bidding process. In any case, the conclusion recorded by the Court on this  score are marginalised in light of the primary finding that the RFP did not  contemplate a forfeiture in an eventuality like the present and did not carry  any express stipulation to the aforesaid effect. In addition, the Court also  reiterates its earlier conclusion that the clarification which was issued by  the second respondent did not become an integral part of the RFP so as to bind parties.

34. That takes the Court to consider the submission of Dr. Singhvi  resting on the principles of manifest arbitrariness. Indubitably, Article 14 of  our Constitution constitutes its heart and soul. It infuses meaning and  guides our understanding of the scope and content of the various provisions  contained in that foundational document. The earliest judgments of the  Supreme Court explaining the ambit of this Article had propounded the  concept of “discrimination” as being the anvil on which State action was to  be judged. This led to the evolution of principles such as “reasonable

W.P.(C) 8779/2019 Page 43 of 45

classification” and “intelligible criteria” to test whether an impugned action  fell foul of the mandate of Article 14. The Supreme Court then proceeded to  note that the aforenoted concepts may have constricted and stifled the  contemplated breadth of this Article as envisioned by our founding fathers.  As time progressed, Supreme Court evolved the principles of the rule of  law and the abhorrence of arbitrary exercise of power. The aforesaid  precepts however remained limited to a “procedural due process” review  with State action being tested on the just and fair doctrine. These principles  ultimately gave way to the Supreme Court adopting and extending the  principles of substantive due process and manifest arbitrariness. All that  may be noted today is that Courts are not confined to merely consider  whether a fair procedure was followed but more fundamentally to adjudge  whether the impugned action would stand the test of reasonableness and  fair action in the substantive sense. Article 14 today has thus crossed the  threshold and the rubicon of hesitance to judge whether the impugned  action would withstand the test of good conscience and sense.

35. Viewed on the aforesaid pedestal the Court finds itself unable to  uphold the action of the second respondent. Not only did it fail to place  parties on notice of what would constitute a breach warranting forfeiture, it  has also and more fundamentally failed to justify its action as being  warranted by the acts of the petitioner. An authority which would constitute  State cannot be permitted to unjustly enrich itself based on a perceived or  assumed power to forfeit even though it be unfair or unjustified. The facts  obtaining here constrain the Court to hold that the action of forfeiture was

W.P.(C) 8779/2019 Page 44 of 45

clearly unjustified. The mere existence of power, even if it were assumed to  inhere, would not justify the impugned action. This more so in light of the  facts that have been presented by the petitioner based on the responses  obtained under RTI. The respondents have abjectly failed to prove  prejudice or loss. Their action cannot be sustained on the provisions  contained in the RFP. The Court thus has no hesitation in recording that the  action was not only clearly ultra vires, it is also manifestly arbitrary and  thus cannot be sustained.

36. Having found in favour of the petitioner on the aforesaid grounds, the  Court deems it unnecessary to rule on the submissions addressed in the light  of Section 74 of the Contract Act. This more so in view of the observations  appearing in paragraphs 41 and 43.7 of Kailash Chand which has  explained that at the pre formation of contract stage, Section 74 of the  Contract Act would not even apply. 

37. Accordingly, and for all the aforesaid reasons, the writ petition is  allowed. The impugned orders of 18 March 2019 & 28 May 2019 are  hereby quashed. The respondents in consequence are hereby directed to  refund the forfeited amount of Rs. 20 crores to the petitioner forthwith.

 YASHWANT VARMA, J.

March 31, 2022/neha

W.P.(C) 8779/2019 Page 45 of 45

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.