Page No.# 1/9 

GAHC010008272019 

 THE GAUHATI HIGH COURT 

(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)  

Case No. : Arb.A./5/2019  

UNION OF INDIA  REPRESENTED BY THE CHIEF ENGINEER PROJECT VARTAK, BORDER  ROAD ORGANISATION, C/O 99 APO  DIST SONITPUR, ASSAM 784001 VERSUS  M/S TENZING CONSTRUCTION  MAIN MARKET, DIRANG, WEST KAMENG, ARUNACHAL PRADESH 790101

Advocate for the Petitioner : MR. S C KEYAL  

Advocate for the Respondent : MR. D WANGDI  

BEFORE 

HONOURABLE MR. JUSTICE PARTHIVJYOTI SAIKIA 

JUDGMENT 

Date : 18-01-2022 

Heard Mr. H. Gupta, learned counsel appearing for the appellant as well as Mr. U. K. Nair, learned senior counsel representing the respondent.  

2. This is an appeal under Section 37 of the Arbitration and Conciliation Act, 1996  (Amendment) Act, 2015. 

Page No.# 2/9 

3. The arbitral award was passed on 02.05.2018. The statutory time limit for filing  appeal against the award had expired and the appeal was filed on 01.09.2018. The  learned trial court held that the appellant could not show proper and cogent reasons for not preferring the appeal within time stipulated by law. Therefore, the court below held that the prayer of the appellant under Section 34 (3) Arbitration and Conciliation Act, 1996 (Amendment) Act, 2015 to entertain the appeal under Section 34 of the  said Act is not maintainable. The Court below dismissed the appeal on that ground.  

4. Mr. Gupta has submitted the chronology of events whereby the delay  occurred. The list submitted by Mr. Gupta reads as under: 

Appx. “A” 

CRITICAL DATES IN R/O CA NO. 27 & 28 OF 2009-10 

Date Activity/Incident took place Remarks
02.May 2018 Hon’ble Sole Arbitrator Shri Raaj  Wardhan Agarwal, published award  signed on 02 May, 2018. An amount of Rs. 2,10,86,850/- (Rupees Two Crores,  Ten Lacs Eight Six Thousands, Eight  Hundred and Fifty only) awarded in  favour of the Contractor (petitioner)  the impugned Award was received  by this HQ on 11 May, 2018.
11 May, 2018 Award was received by this HQ on 11  May, 2018.
16 May, 2018 This HQ instructed HQ 42 BRTF vide  letter No. 80941/Arb/Web/E8 dated 16 May 2018 for submission of following  documents :- (a) Parawise  comments on Award. (b) Detailed SoC  supported with annexure for 
Contesting the Award. (c) Liaison with RLC (E)  for obtaining legal opinion On  Award. (d) Recommendation  of Commander TF.
15 June. 2018 The SOC, Parawise comments on  impugnedAward Recommendation of Commander were received By this HQ on 15 June, 2018.
25 June 2018 This HQ vide letter No.  80941/Arb/88/E8 dated 25 June  approached HQ ADGBR(E) for  seeking Legal Opinion of ASGI.
29 June, 2018 Legal Opinion of ASGI Shri Subhash  Chandra Kayal, Advocate, received  by this HQ on 29 June 2018.
30 June 2018 Notice served by the Contractor for  filing Money Execution Case.
02 July, 2018 Case forwarded to HQs ADGBR(East)  for challenging the impugned Award and requested for  further advice on all the records  submitted before him.
16 July, 2018 In the mean time HQ 42 BRTF vide their letter No.8001/725/Arb/106/E8 dated  12 July, 2018 forwarded the case for  contesting the Award, which was  received by this HQ on 16 July, 2018.
20 July, 2018 Case forwarded to HQ ADGBR (East)  vide this HQ letter 

Page No.# 3/9 

No.80941/Arb/101/E8 dated 20 July,  2018 for legal opinion of LA (Def),  which is required for contesting or  implementing the Award.
24 July, 2018 This HQ approached Advo9cate Shri  Surendar Mishra, Govt. Pleader to  defend Money Execution Case in  Hon’ble District Court Sonitpur at  Tezpur.
30 July, 2018 Case forwarded to HQ DGBR by HQ  ADGBR (East).
31 July, 2018 Money Execution Case 03/2018 filed  by the Contractor in Hon’ble District  Court Sonitpur at Tezpur.
16 Aug. 2018 HQ ADGBR (East) suggested to file  case to safe guard Govt. Dues vide  their letter No.  80002/ADG(E)/—/ARB/28/E8.
23 Aug, 2018 This HQ approached Advocate Shri  Surendar Mishra, Govt. Pleader to File  the Petition to set aside Award for  safe Guard of Govt. Dues.
04 Sept, 2018 Petition No. 05/2018 filed by the  department to set aside Arbitration  Award.

Page No.# 4/9 

5. The submission of Mr. Gupta is primarily based on the fact that the appellant is a 

Page No.# 5/9 

part of the Union of India having its headquarters outside the State of Assam and  Arunachal Pradesh. Mr. Gupta has submitted that because of official  communication the delay took place.  

6. In order to buttress his argument, Mr. Gupta has relied upon the decision of the  Supreme court in G. Ramegowda v. Spl. Land Acquisition Officer, (1988) 2 SCC 142. In this case, the Supreme Court has held as under: 

15. In litigations to which Government is a party there is yet another aspect  which, perhaps, cannot be ignored. If appeals brought by Government are lost for such defaults, no person is individually affected; but what, in the ultimate  analysis, suffers is public interest. The decisions of Government are collective  and institutional decisions and do not share the characteristics of decisions of  private individuals. 

16. The law of limitation is, no doubt, the same for a private citizen as for  governmental authorities. Government, like any other litigant must take  responsibility for the acts or omissions of its officers. But a somewhat different  complexion is imparted to the matter where Government makes out a case  where public interest was shown to have suffered owing to acts of fraud or bad faith on the part of its officers or agents and where the officers were clearly at  cross-purposes with it. 

17. Therefore, in assessing what, in a particular case, constitutes “sufficient  cause” for purposes of Section 5, it might, perhaps, be somewhat unrealistic to  exclude from the considerations that go into the judicial verdict, these factors  which are peculiar to and characteristic of the functioning of the government.  Governmental decisions are proverbially slow encumbered, as they are, by a  considerable degree of procedural red tape in the process of their making. A  certain amount of latitude is, therefore, not impermissible. It is rightly said that  those who bear responsibility of Government must have “a little play at the  joints”. Due recognition of these limitations on governmental functioning — of  course, within reasonable limits — is necessary if the judicial approach is not to  be rendered unrealistic. It would, perhaps, be unfair and unrealistic to put  government and private parties on the same footing in all respects in such  matters. Implicit in the very nature of governmental functioning is procedural  delay incidental to the decision-making process. In the opinion of the High  Court, the conduct of the law officers of the Government placed the  Government in a predicament and that it was one of those cases where the  mala fides of the officers should not be imputed to Government. It relied upon  and trusted its law officers. Lindley, M.R., in the In re National Bank of Wales  Ltd. [LR (1899) 2 Ch 629, 673] observed, though in a different context: 

“Business cannot be carried on upon principles of distrust. Men in responsible  positions must be trusted by those above them, as well as by those below them, until there is reason to distrust them.” 

Page No.# 6/9 

In the opinion of the High Court, it took quite some time for the government to  realise that the law officers failed that trust. 

18. While a private person can take instant decision a “bureaucratic or  democratic organ” it is said by a learned Judge “hesitates and debates,  consults and considers, speaks through paper, moves horizontally and vertically till at last it gravitates towards a conclusion, — unmindful of time and  impersonally”. Now at the end, should we interfere with the discretion exercised by the High Court? Shri Datar criticised that the delay on the part of  Government even after January 20, 1971 for over a year cannot be said to be  either bona fide or compelled by reasons beyond its control. This criticism is not  without substance. Government could and ought to have moved with greater  diligence and dispatch consistent with the urgency of the situation. The  conduct of Government was perilously close to such inaction as might,  perhaps, have justified rejection of its prayer for condonation. But as is implicit  in the reasoning of the High Court, the unarticulated thought, perhaps was that in the interest of keeping the stream of justice pure and clean the awards  under appeal should not be permitted to assume finality without an  examination of their merits. The High Court noticed that the Government  Pleader who was in office till December 15, 1970 had applied for certified  copies on July 20, 1970, but the application was allowed to be dismissed for  default. In one case, however, he appears to have taken away the certified  copy even after he ceased to be a Government Pleader. In a similar context  where delay had been condoned by the High Court, this Court declined to  interfere and observed [Spl. Land Acquisition Officer v. B.M. Krishna Murthy,  (1985) 1 SCC 469] : (SCC p. 472, para 5).” 

7. Mr. Gupta has further relied upon another decision of the Supreme Court in  State of Haryana v. Chandra Mani, (1996) 3 SCC 132. Here, the Supreme Court has  held as under: 

“11. It is notorious and common knowledge that delay in more than 60 per cent of the cases filed in this Court — be it by private party or the State — are barred by limitation and this Court generally adopts liberal approach in condonation  of delay finding somewhat sufficient cause to decide the appeal on merits. It is  equally common knowledge that litigants including the State are accorded  the same treatment and the law is administered in an even-handed manner.  When the State is an applicant, praying for condonation of delay, it is common knowledge that on account of impersonal machinery and the inherited  bureaucratic methodology imbued with the note-making, file-pushing, and  passing-on-the-buck ethos, delay on the part of the State is less difficult to  understand though more difficult to approve, but the State represents  collective cause of the community. It is axiomatic that decisions are taken by  officers/agencies proverbially at slow pace and encumbered process of  pushing the files from table to table and keeping it on table for considerable  time causing delay — intentional or otherwise — is a routine. Considerable  delay of procedural red-tape in the process of their making decision is a  common feature. Therefore, certain amount of latitude is not impermissible. If  

Page No.# 7/9 

the appeals brought by the State are lost for such default no person is  individually affected but what in the ultimate analysis suffers, is public interest.  The expression “sufficient cause” should, therefore, be considered with  pragmatism in justice-oriented approach rather than the technical detection  of sufficient cause for explaining every day’s delay. The factors which are  peculiar to and characteristic of the functioning of the governmental  conditions would be cognizant to and requires adoption of pragmatic  approach in justice-oriented process. The court should decide the matters on  merits unless the case is hopelessly without merit. No separate standards to  determine the cause laid by the State vis-à-vis private litigant could be laid to  prove strict standards of sufficient cause. The Government at appropriate level  should constitute legal cells to examine the cases whether any legal principles  are involved for decision by the courts or whether cases require adjustment  and should authorise the officers to take a decision or give appropriate  permission for settlement. In the event of decision to file appeal needed  prompt action should be pursued by the officer responsible to file the appeal  and he should be made personally responsible for lapses, if any. Equally, the  State cannot be put on the same footing as an individual. The individual would  always be quick in taking the decision whether he would pursue the remedy by way of an appeal or application since he is a person legally injured while State  is an impersonal machinery working through its officers or servants. Considered  from this perspective, it must be held that the delay of 109 days in this case has  been explained and that it is a fit case for condonation of the delay.” 

8. Per contra, Mr. Nair has submitted that the law of limitation is applicable to the  government departments like a private person. Mr. Nair has strenuously submitted  that in this century of internet revolution, the government departments are not  entitled to privilege in the matter of condonation of delay. The learned senior counsel has relied upon the decision of the Supreme Court that was rendered in Postmaster  General v. Living Media India Ltd., (2012) 3 SCC 563. In this case, the Supreme Court  has held as under:  

“28. Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or  lack of bona fides, a liberal concession has to be adopted to advance  substantial justice, we are of the view that in the facts and  

circumstances, the Department cannot take advantage of various  earlier decisions. The claim on account of impersonal machinery and  inherited bureaucratic methodology of making several notes cannot be  accepted in view of the modern technologies being used and available. The law of limitation undoubtedly binds everybody, including the  Government. 

29. In our view, it is the right time to inform all the government bodies,  their agencies and instrumentalities that unless they have reasonable  and acceptable explanation for the delay and there was bona fide  

effort, there is no need to accept the usual explanation that the file was  kept pending for several months/years due to considerable degree of  

Page No.# 8/9 

procedural red tape in the process. The government departments are  under a special obligation to ensure that they perform their duties with  diligence and commitment. Condonation of delay is an exception and  should not be used as an anticipated benefit for the government  departments. The law shelters everyone under the same light and should  not be swirled for the benefit of a few”.  

9. I have given my anxious consideration to the submissions made by the learned  counsels for both sides.  

10. “Equity aids the vigilant, not those who slumber on their rights.”This doctrine is the foundation, on the basis of which, the Law of Limitation stands. This doctrine  recognizes the fact that an adversary might lose a fair chance to defend himself or  herself after expiry of time from the date when the wrong was committed. The law  encourages a speedy resolution for every dispute. It does not favour the cause of  someone who suddenly wakes up to enforce his or her rights long after discovering  that they exist.  

11. Law is already settled that the law of limitation undoubtedly binds everybody,  including the Government. In a matter of condonation of delay when there was no  gross negligence or deliberate inaction or lack of bona fides, a liberal concession has to be adopted to advance substantial justice, but the Government Department  cannot take advantage of various earlier decisions at least in this age of electronic  communication. The claim on account of impersonal machinery and inherited  bureaucratic methodology of making several notes cannot be accepted in view of  the modern technologies being used and available. In Postmaster General’s case  (supra), the Supreme court has held that it is the right time to inform all the  government bodies, their agencies and instrumentalities that unless they have  reasonable and acceptable explanation for the delay and there was bona fide  effort, there is no need to accept the usual explanation that the file was kept  pending for several months/years due to considerable degree of procedural red  tape in the process. 

12. In the case in hand, I have decided to agree with the view taken by the court  below that the appellant has failed to explain the reasons for delay in a satisfactory  manner. The learned trial court has rightly held that since the date of filing of the  appeal was to be calculated from 11.05.2018 and the prayer for condonation of  delay should have been filed before 09.08.2018. The trial court has correctly  appreciated the legal provisions and arrived at a correct finding. 

13. The present appeal is found to be devoid of merit and stands dismissed  accordingly.  

 JUDGE 

Page No.# 9/9 

Comparing Assistant 

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.