Punjab-Haryana High Court
M/S Impact Projects Private … vs Punjab State Power Corporation … on 7 April, 2021CWP No.23009 of 2019 -1-

IN THE HIGH COURT OF PUNJAB AND HARYANA
AT CHANDIGARH

CWP No.23009 of 2019(O&M)
Date of Decision:07.04.2021

M/S IMPACT PROJECTS PRIVATE LIMITED
AND ANOTHER

…Petitioners

Versus

PUNJAB STATE POWER CORPORATION LIMITED
AND OTHERS

…Respondents

CORAM: HON’BLE MR. JUSTICE ANIL KSHETARPAL

Present: Mr. Gurminder Singh, Sr. Advocate with
Mr. J.S.Gill, Advocate,
for the petitioners.

Mr. Naveen S. Bharadwaj, Advocate
for the respondents.

ANIL KSHETARPAL, J.

1. Through this writ petition, filed by two separate companies

having a common management, the following substantive reliefs have been

sought:-

“i. Summon the entire record of the case. i. Issue of writ in
nature of Mandamus directing the respondent no. 1 to
release the electricity connections to the residents of the
colonies established/built by the petitioners as in relation
to two colonies namely Garden Enclave Extension-1 and
Garden Enclave Extension I the petitioners have already
completed the installation of LD system and as far as the
remaining colonies, wherein NOCS have been issued by
Corporation, are concerned the petitioners are ready to
deposit the bank guarantee in relation to incomplete LD
system as per the letter dated 06.06.2019 (Annexure

1 of 15
::: Downloaded on – 05-06-2021 06:14:06 :::
CWP No.23009 of 2019 -2-

P-22).

ii. With further prayer for issuance of writ in the nature
certiorari for quashing the letter dated 15.01.2018
(Annexure P-16), and 22.08.2019 (Annexure
P-20)whereby the respondents in a completely illegal and
arbitrary manner has directed the petitioners to obtain
the NOC from respondent no. 1 afresh by treating six
different approved colonies as one and by considering
their combined load under Punjab State Electricity
Commission (Electricity Supply Code and Related
Matters Regulations 2014, whereas, these regulations
are not applicable to the colonies of the petitioners as
different colonies set up by the petitioner were approved
by way of separate schemes and orders between 2002 to
2006 and all the six colonies were separately registered
by the PUDA/Competent Authority under PAPR Act,
1995 and separate NOCS were already granted by the
respondent no. 1 earlier i.e. between 2007 to 2008.”

In the considered opinion of this Bench, the question which

arises for consideration is:-

“If the Electricity Distribution licensee gives No
Objection Certificate to set up a colony under Section 5
of the Punjab Apartment and Property Regulation Act,
1995 (hereinafter referred to as ‘the Regulation Act,
1995’), then subsequently, whether it is bound to supply
the power/electricity under the Supply Code applicable
at the time of issuance of the NOC irrespective of the
time/period which has elapsed from the date of issuance
of the NOC to the completion of the colony?
FACTS

2. The petitioners are developers and colonizers. They got the

2 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -3-

approval/licence to develop various contiguous pieces of vacant land. The

first project i.e. Garden Enclave with respect to land measuring 49.78 acres

was approved on 04.01.2002 by the Punjab Urban Development Authority

(hereinafter referred to as PUDA) for carving out 513 residential plots.

Thereafter, on 28.07.2003, the petitioners got the approval of the second

project i.e ‘Garden Enclave Extension-I’ with respect to the land measuring

18.83 acres. Subsequently, on the application of the petitioner, PUDA

granted approval to develop 4.84 acres of land vide a communication dated

10.09.2004. Thereafter, on 30.06.2006, the fourth project i.e. ‘Impact Park’

comprising an area of 8.84 acres was approved by the PUDA. Thereafter,

on 11.08.2006, the fifth project under the name of ‘Impact Estates’ with

respect to a land measuring 9.64 acres was also approved by the PUDA.

Lastly, petitioner no.2 also got an approval to develop a project (Garden

Estates) with respect to a land measuring 9.04 acres, on 14.08.2006.

2.1 The respondents in their written statements have tabulated the

aforesaid information which is extracted as under:-Sr. Name of Licence Licence Licence NOC Date of NOC valid
No. Colony issued by date of valid upto issued by issue upto
PUDA issue PSEB (NOC)
(PSPCL)
1. Garden LDC2002/88 04.01.2002 03.01.2005 No NOC – –
Enclave applied.
2. Garden LDC2004/136 28.07.2004 27.07.2007 3420 28.12.2007 –
Enclave
Ext.1
3. Garden LDC2004/143 10.09.2004 09.09.2009 3423 28.12.2007 –
Enclave
Ext. 2
4. Impact 26/2006 30.06.2006 29.06.2009 1223 21.07.2008 20.07.2010
Park
5. Impact 30/2006 11.08.2006 10.08.2009 1220 21.07.2008 20.07.2010
Extate
6 Garden 31/2006 14.08.2006 130.08.2009 1226 21.07.2008 20.07.2010
Estate

2.2 It would be appropriate to notice that various No Objection

3 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -4-

Certificates (hereinafter referred to as ‘NOC’) have been granted by the

Punjab State Electricity Board (now re-named as Punjab State Power

Corporation Limited) (hereinafter referred to as PSPCL) under Section 5 of

the Regulation Act, 1995. The petitioners claim that when they approached

the PSPCL to take over the complete management of the electricity supply

of the afore-stated six projects, the same was refused and they have been

directed on 15.01.2018 to apply for yet another NOC, by taking the

combined load of all the six projects. This communication and other similar

communications are the subject matter of challenge in the writ petition. The

stand of the respondents is that these six areas form a part of an integrated

colony being contiguous to each other, having common facilities with a

single entry and exit gate. Even the developers are common and therefore,

the entire area developed by the petitioners is required to be considered as

one integrated unit as per regulation 6.7.1 of the Punjab State Electricity

Regulatory Commission (Electricity Supply Code and Related Matters)

Regulations 2014 (hereinafter referred to as ‘the supply code 2014) and

hence, the petitioners are liable to obtain a fresh ‘NOC’.

This Bench has heard the learned counsel for the parties at

length and with their able assistance perused the paper book. On liberty

having been granted, the learned counsel for the petitioners has filed written

synopsis along with a summary of the submissions.

ARGUMENTS

3. Learned senior counsel representing the petitioners while

drawing the court’s attention to the various permissions granted by the

PUDA and the ‘NOC'(s) issued by the PSPCL submits that these six projects

are independent colonies in terms of Section 2(1)(i) of the ‘Regulation Act,

4 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -5-

1995’ and therefore, clubbing of the expected demand of the electricity of all

the six colonies is not permissible. He further submits that the petitioners

cannot be directed to comply with the supply code, 2014, particularly when

the ‘NOC'(s) with respect to 5 colonies have already been granted to the

petitioners before the year 2014. Further, with respect to the first colony,

there was no requirement of obtaining a ‘NOC’ from the PSPCL at the

relevant time. He further submits that the impugned communications do not

have any statutory basis and therefore, the respondents cannot insist upon its

compliance. Learned senior counsel, in support of his arguments, relies

upon the judgment passed in M/s Ansal Properties and Industires Limited

vs. State of Haryana and another, (2009) 3 SCC 553.

3.1 Per contra, learned counsel representing the PSPCL contends

that the petitioners were granted the various ‘NOCs’ only for developing

various projects from time to time. In the ‘NOC’ itself, it was indicated that

the electricity connection shall be released as per the prevalent policy-

regulations at the time of release of the actual electricity connection. He

further submits that in more than one paragraphs of each ‘NOC’, it was

specified that the electricity connection to the houses/buildings in the

proposed projects shall be governed by the prevalent supply code at the time

of actual release of the connection. He further submits that the petitioners

did not complete the projects for a long time and therefore, various ‘NOCs’

do not confer any indefeasible right. He, while referring to Regulation 6.7

of the Supply Code, 2014, submits that the respondent-Power Distribution

licensee has only directed the petitioners to comply with the regulations

which have been framed by the Regulatory Commission. He further content

that once it is shown that the developers are common and the land of all the

5 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -6-

areas/projects is contiguous without any bifurcation or independent

identification and all the projects have common facilities including a single

entry and exit gate, then, the respondents are justified in clubbing the

expected demand and requiring the petitioners to comply with the Supply

Code, 2014.

This Bench has analyzed the arguments of the learned counsel

for the parties and proceeds to adjudicate the dispute.

DISCUSSION

4. Section 82 of the Electricity Act, 2003 mandates that every

State Government shall, within six months from the appointed date, by

notification, constitute for the purpose of this Act, a Commission for the

State. In exercise of the aforesaid powers, the Punjab State Electricity

Regulatory Commission (hereinafter referred to as the ‘Regulatory

Commission’) has been constituted. Further, Section 86 of the Electricity

Act, 2003, enlists the functions of the ‘Regulatory Commission’. There are

various other provisions in the 2003 Act which enables the ‘Regulatory

Commission’ to make regulations. The ‘Regulatory Commission’ has notified

‘The Punjab State Electricity Regulatory Commission (Electricity Supply

Code and Related Matters) Regulation, 2014 (in short the ‘supply code

2014′). These Regulations have been made in exercise of the powers

conferred under Section 181 read with Sections 43, 44, 45, 46, 47, 48, 50,

55, 56, 57, 58, 59, 126, 127, 135, 152, 154 and 163 of the Electricity Act,

2003. Regulation 6.7 lays down the procedure for supply of electricity to the

individual consumers in the residential/multi-storey residential complexes

developed under the by-laws/rules of the State Government. Clause 6.7 of

the Supply Code 2014 is extracted as under:-

6 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -7-

“6.7 Supply of Electricity to Individual Consumers in
the Residential Colonies/Multi-Storey Residential
Complexes Developed under bye-laws/rules of the State
Govt.

6.7.1 In the event of residential colonies/complexes
developed by developers /builders /societies /owners
/associations of residents/occupiers under bye-laws/rules
of the State Govt. not covered under Regulation 6.6.
above, the residents/occupiers of such
colonies/complexes shall obtain individual connections
directly from the distribution licensee.
The release of such connections shall be governed by the
following terms and conditions:-

a) The developer/ builder/society/owners/ association of
residents/ occupiers shall submit the complete lay out
plan of the electrical network proposed to be erected in
the colony and other documents prescribed by the
licensee along with the processing fee as per Schedule of
General Charges and obtain the preliminary NOC from
the licensee. The NOC shall be issued by the licensee
within 45 days of the receipt of proposal complete in all
respects along with requisite documents. In case the
developer/ builder/ society/ owners/ association of
residents/ occupiers withdraw his request or fails to
comply with the conditions within stipulated time, the
processing fee shall be forfeited.

Note: The developer/builder/society/owner/association
includes any agency whether Govt./ Local body or
private that constructs the colony/ complex.

b) For planning the L.D system of such
colonies/complexes or to issue NOC, the following
guidelines may be adopted by distribution licensee for
assessment of expected connected load/ demand of such
colonies/complexes:-
S.No. Name of category Load(KW)
Residential plots
1. Up to 100 (Sq. Yards) 5
2. From 101- 200 (Sq. Yards) 8
3. From 201-250 (Sq. Yards) 10
4. From 251 -350 (Sq. Yards) 12
5. From 351- 500 (Sq. Yards) 20
1 6. Above 500(Sq. Yards) 30

7 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -8-

S.No. Name of category Load(KW)
Residential flats
1. One Bedroom Set 5
2. Dwelling unit (single room flat) 1.5
under basic service to urban poor
under JnNURM/EWS flats.
3. Two Bedroom Set 7
4. Three Bedroom Set 10
5. Four Bedroom Set 12
2 6. Five Bedroom Set 15
Commercial Area 10
1. Shop
2. Other Commercial plot(s) for 35 Watts per sq.
dispensary, school, hospital etc. yard
including other common services
3 falling under commercial category
4 Other load for common services As per requirement

Note: One third of the total residential load and 40% of
all commercial load as calculated above will be taken as
colony load, which will be further increased by 40% to
take into account future growth of load. The load shall be
converted in kVA by using a power factor of 0.90.

c) The developer/builder/society/owners/association of
residents/occupiers shall deposit the estimated cost of LD
system of the colony as per approved layout sketch & get
it executed from the distribution licensee. The
expenditure incurred by the distribution licensee for
erection of 11 kV feeder(s) including breaker from the
feeding sub-station to the connection point of the internal
distribution system shall also be borne by the
developer/builder/society/ owners/association occupiers.
The expenditure of L.D system including service cable up
to the metering point of each consumer & 11 kV system
shall include cost of the material, labour plus 16%
establishment charges there on. If the connection is
released to of residents/ the colony/complex by tapping
the existing 11kV feeder, the cost of service line and
proportionate cost of common portion of line including
breaker shall be recoverable. The phase wise
development of LD system may be carried out by licensee
as per requirement but any cost escalation over a period
of time shall be borne by the licensee. The distribution
licensee shall be responsible to release individual
connections within the time frame specified in regulation
8. However, the developer/builder society/ owners/
association of residents/occupiers shall have the option
to execute the works of internal L.D system of the colony/
complex of its own in accordance with the approved
layout plan/sketch approved by the distribution licensee
subject to payment of 15% supervision charges on the

8 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -9-

labour cost to the licensee. After its completion and
inspection by the Chief Electrical Inspector to Govt. of
Punjab, the distribution licensee will take over the L.D
system which will be connected to its distribution system.
The distribution licensee shall thereafter maintain L.D
system at its own cost. In case the developer requests for
energisation of incomplete LD system, the same shall be
allowed provided the developer furnish a Bank
Guarantee (BG valid for 5 years) equivalent to 150% of
the estimated cost of balance works. This amount of Bank
Guarantee shall keep on reducing with the completion of
remaining works of the L.D system. After submission of
Bank Guarantee to the satisfaction of licensee, it shall be
the responsibility of the licensee to release connections to
the residents/occupiers of the colony/complex according
to the time frame specified in regulation 8.

d) In case the expected demand of the colony/complex
computed as per (b) above exceeds 4000 kVA, the
developer/ builder/ society/ owners/ association of
residents/occupiers shall also pay the “System Loading
Charges’ as provided in the cost data approved by the
Commission in addition to the charges payable as per
regulation (c) above. In such a case, the erection or
augmentation of grid sub-station, if required, shall be
carried out by the licensee at its cost. However, in case
the grid sub-station is required to be erected in the
colony, the developer/ builder/ society/
owners/association of residents/ occupiers shall provide
the space and right of way free of cost, if permissible or
at nominal token money @ of Rs.1 per sq. metre. In case
the cost of grid sub-station and/or HT/EHT line including
bay/breaker has been deposited by an authority under the
State Act viz. PUDA/GMADA/GLADA etc., the “System
Loading Charges’ for the same shall not be recovered
from the developer of such colony/complex.”

4.1 As already noticed the aforesaid supply code 2014 has been

made in exercise of the powers conferred under the Electricity Act, 2003 and

hence it is a subordinate legislation/delegated legislations. The

communications under challenge have been issued in accordance with the

aforesaid Supply Code 2104. Therefore, the learned senior counsel is not

correct in contending that the communications have been issued without any

statutory basis.

9 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -10-

4.2 Now, let’s examine whether it is permissible to club the

expected electricity demand of the various projects or not?

On careful reading of Regulation 6.7.1(c), it is apparent that the

developer/builder/society/owners/association of residents/occupiers are

required to lay down a local distribution system themselves or deposit the

charges with the PSPCL to lay down the local distribution system for them.

It is further provided that such area/colony would be given supply from

11KV feeder. The expenditure incurred by the distribution licensee for

erection of 11KV feeder(s) including from feeding substation to the

connection point shall also be born by the developer. It is further provided

under clause (d) that in case the expected demand of the colony/complex,

computed as per Clause (b) mentioned above, exceeds 4000 KVA, the

developer /builder/ society/ owners/association of residents/occupiers shall

also pay the system loading charges. In other words, if the premises in the

colony developed is expected to have a demand exceeding 4000 KVA, the

colonizers are also not only liable to pay the necessary charges but also

required to comply with the requirements of the supply code 2014.

4.3 With regard to the first argument of learned counsel for the

petitioners that there is no provision for clubbing, it may be noted that

Regulation 6.6 provides that the distribution licensee shall provide a single

point supply for residential colonies/complexes developed by developers

/builders /societies /owners /associations of residents/occupiers under bye-

laws/rules of the State Govt. not covered under Regulation 6.6. above on 11

Kv. feeder.. Clause 6.7 further lays down the manner in which the supply of

electricity of individual consumers in the new residential colonies/multi-

storey residential complexes, developed under the bye-laws and rules of the

10 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -11-

State Government, shall be released. Regulation 6.7.1 do grant liberty to the

residents/occupiers of such colonies/complexes to obtain individual

connections directly from the distribution licensee. However, it obliges the

developers/builders to make an arrangement for the compliance of the

requirements specified in the Supply Code, 2014.

4.4 On careful reading of Regulation 6.7, it becomes clear that the

supply of electricity to the individual consumers in the residential colonies/

multi-storey residential complexes developed by developers /builders/

societies/ owners/associations of residents/occupiers who are not covered

under Regulation 6.6, shall be issued by the Distribution Licensee.

However, before such connections are released, the developer has been

given two options under Clause ‘c’ of Regulation 6.7.1. One is to deposit the

estimated cost of laying the local distribution system of the colony with the

Distribution Licensee. The expenditure incurred by the Distribution

Licensee for erection of 11 KVA feeder including breaker from the feeding

substation to the connection point of the internal distribution system shall

also be born by the developer. Second option is that the developer can get

the work of internal local distribution system executed at his own level. In

that case, the developer would be required to pay 15% of the supervision

charges on the labour cost to the licensee and thereafter get it inspected and

approved from the Chief Electrical Inspector to the Government of Punjab.

Clause-‘d’ provides that in case the expected demand of the colony/complex

computed as per Clause ‘b’ exceeds 4000 KVA, the developer is also

required to pay the system loading charges as provided. However, if a grid

substation is required to be erected in the colony, the developer shall provide

the space and the right of way free of cost. In other words, as per the supply

11 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -12-

code, it is the duty/responsibility of the developer to bear the cost of not only

of the local distribution system but also to pay the system loading charges. It

may be noted here that the respondents have taken a specific stand that

although six separate projects were got approved by the petitioners,

however, this entire developed area is contiguous and there is no physical

separation between the houses/buildings of these six projects. The entire

area has common facilities. There is neither any separate entry or exit gate

for the houses of each project nor the plots in these projects are separated by

a boundary wall. In these circumstances, particularly when the distribution

licensee is required to supply the electricity in the area, in which the

expected demand is likely to exceed 4000 KVA, the petitioners, who are

developers/colonizers, cannot be permitted to shy away from providing the

infrastructure required for the supply of the electricity. As already noticed,

the petitioners-society initially got the project approved for 49.781 acres and

thereafter, kept expanding the same by getting the additional projects

approved for contiguous area in a phased manner. As per the stand of

respondents, the petitioners/developers have also not submitted any separate

completion/occupancy certificates. Now, since the petitioners want to hand

over the management of the electricity supply to a distribution licensee

without completing the work as required under the supply code, therefore

the respondents are justified in insisting the petitioners to comply with the

requirements.

4.5 It may be noted here that the learned counsel appearing for the

petitioners has emphasized on the definition of the word ‘colony’ as defined

in Section 2(i) of the Regulation Act, 1995. No doubt, the colony as defined

means an area of land not less than 1000 Sq. Mtr. divided or proposed to be

12 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -13-

divided into plots/residents/ commercial/industrial purpose plots. However,

the requirement is that the area of land should not be less than 1000 Sq.

Mtrs. but there is no upper limit. Once, the colonizer/developer has

converted agricultural land into a residential complex, then such developer

cannot be permitted to avoid its responsibility as provided in the supply code

2014.

4.6 Learned counsel for the petitioners has relied upon the

judgment in Ansal Properties and Industries Ltd.(supra). In the aforesaid

case, the State had called upon the developer to pay an amount of

Rs.61,000/- per gross acre towards the construction of internal community

buildings. The Supreme Court, after examining the statutory provisions,

found that there was neither any statutory basis nor there was any

requirement under the licence to pay the amount. Hence, it was held that the

demand of s.61,000/- per gross acre towards the construction of community

buildings was unjustified. With greatest respect, the aforesaid judgment has

no applicability, particularly when in the present case, the supply code, 2014

enables the distribution licensee to insist the developer/builder to fulfill its

requirements.

4.6.1 There is also no substance in the next argument of the learned

counsel for the petitioners that once the various ‘NOCs’ were issued for the 5

colonies, then the supply Code of 2014 shall not be applicable. The various

‘NOCs’ were issued to the petitioners under Section 5 of the Regulation Act,

1995. It is with reference to the proposal to develop the plain land into a

complex. In exercise of the powers conferred by the Regulation Act, 1995,

the Punjab Apartment and Property Regulation Rules, 1995 have been

notified. Rule 10(1)(e)(xii) thereof requires a builder to obtain a ‘NOC’ from

13 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -14-

the distribution licensee. This ‘NOC’ is granted only to take the opinion of

the distribution licensee with respect to feasibility of the supply of electricity

at the location where the project is proposed to be developed. The issuance

of ‘NOC’ does not confer any right on the developer to get the electricity

supply on the basis of the supply code applicable at its issuance. Still

further, on careful reading of the ‘NOC’, it is apparent that the distribution

licensee did notify that the instructions amended from time to time shall be

applicable. In these circumstances, this Bench expresses its inability to

accept the arguments of the learned counsel for the petitioners.

4.7 The learned counsel for the respondents is also correct while

contending that the petitioners who got the ‘NOC’ in the year 2007-2008, but

thereafter took 10-11 years to complete the projects cannot insist for supply

of the electricity as per the supply code applicable in the year 2007-08. He

is further correct in contending that while issuing the ‘NOC’, the distribution

licensee had nowhere bound itself to supply electricity as per the old supply

code.

4.8 It may be noted here that it is not disputed by the petitioners

have failed to completely develop the local distribution networks in most of

the projects as the occupancy is low. The petitioners want to hand over the

incomplete projects to the distribution licensee and walk away. In such

circumstances, the distribution licensee is entitled to insist upon the

petitioners to comply with the necessary requirements, so that the

infrastructure for the expected demand of electricity is in place before the

petitioners hand over the management of the electricity distribution to the

PSPCL. No doubt, individual electricity connections have been issued to the

occupiers/buyers/individual owners of the residential premises, however,

14 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::
CWP No.23009 of 2019 -15-

that would not absolve the petitioners from fulfilling the requirements of the

supply code, 2014.

4.9 This matter can be examined from yet another perspective. If in

the absence of complete infrastructure, the distribution licensee is forced to

take over the incomplete local electricity distribution network, the

consumers are likely to suffer. The developer after handing over the

complete management would walk away from the project and the

distribution licensee would be then either be unjustifiably required to invest

in the infrastructure which is the responsibility of the developer as per

supply code, 2014 or the occupier will get proper supply of the electricity.

In these circumstances, the petitioners-developers are not

entitled to the writ as prayed for.

Hence, dismissed.

7th April, 2021 (ANIL KSHETARPAL)
JUDGE
Whether speaking/reasoned :YES/NO
Whether reportable :YES/NO

15 of 15
::: Downloaded on – 05-06-2021 06:14:07 :::

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.