caselaws.org

Supreme Court of India
Chief General Manager (Ipc) M.P. … vs Narmada Equipments Pvt Ltd on 23 March, 2021Author: Hon’Ble Dr. Chandrachud

Bench: Hon’Ble Dr. Chandrachud, M.R. Shah, Sanjiv Khanna

1

Reportable

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

Civil Appeal No 1051 of 2021
(Arising out of SLP(C) No 5750 of 2017)

Chief General Manager (IPC)
M P Power Trading Co Ltd & Anr …. Appellant(s)

Versus

Narmada Equipments Pvt Ltd ….Respondent(s)

JUDGMENT

Dr Dhananjaya Y Chandrachud, J

1 Leave granted.

2 This appeal arises from a judgment and order of a learned Single Judge of the High

Court of Madhya Pradesh dated 30 November 2016 where it appointed an

Arbitrator in the dispute between the parties, in an application 1 filed by the

respondent under Section 11(6) of the Arbitration and Conciliation Act 1996 2.

3 The genesis of the matter is from when the Madhya Pradesh Electricity Board 3,
Signature Not Verified
entered into a Power Purchase Agreement 4 on 20 May 1999 with the respondent.
Digitally signed by
Sanjay Kumar
Date: 2021.03.25
12:19:03 IST
Reason:

1 “AC No 1 of 2015”
2 “1996 Act”
3 “Board”
4 “PPA”
2

Under the PPA, the respondent was to establish a mini hydro-electric project on a

built and operate basis. However, the PPA was terminated on 27 September 2001

by the Board. The respondent initially filed a writ petition 5 challenging the

termination of the PPA. The High Court, by its order dated 4 November 2009,

declined to entertain the petition in view of an arbitration agreement contained in

Clause 12.3 6 of the PPA. Thereafter, the respondent filed a review petition 7which

was dismissed by the High Court by an order dated 10 December 2009.

4 As a consequence of the orders dated 4 November 2009 and 10 December 2009,

on 28 December 2009, the respondent issued a notice to the Board under Clause

12.1 of the PPA, seeking to resolve the dispute by mutual discussion. Since the

respondent did not receive a reply to the notice dated 28 December 2009 from the

Board, on 30 May 2011, the respondent issued another notice to the Board invoking

arbitration under Clause 12.3 of the PPA. In the notice, the respondent stated that if

the Board did not act upon the notice within 30 days of its receipt, it would

approach the High Court under Section 11(6) of the 1996 Act.

5 Having received no reply from the Board, an application 8 was filed under Section

11(6) of the 1996 Act by the respondent seeking the appointment of an arbitrator.

The High Court, by its order dated 21 January 2014, recorded that the respondent

5 “WP No 2642 of 2002”
6 “12.3 Arbitration:

(a) If dispute cannot be salted within Thirty (30)days mutual discussions as (sic) by section 12.1 and (sic)
to Conciliation is not elected by the Parties pursuant to Section 12.2 of if a Parties so requests in
accordance with Section 12.2 the Dispute shall in dally be settled by an Umpire to be appointed by
two arbitrators one to be appointed by the Board and other by the Company Provisions of the Indian
Arbitration and Conciliation Act 1996 9or any enactment that replaces the said Act) shall apply in such
arbitrator. The arbitration proceedings shall be held at head Quarter of the Board i.e. at Jabalpur.

(b) The award rendered shall apportion the costs of the arbitration.

(c) The award rendered in any arbitration commended here under shall be final conclusive and
binding upon the Parties and award may be entered in any Court having jurisdiction as darned under
article 15.1.”
7 “Review Petition No 716 of 2009”
8 “AC No 76 of 2011”
3

and the appellant had agreed to nominate their arbitrators, and observed that the

two arbitrators would proceed to appoint a third arbitrator, in accordance with the

procedure in Clause 12.3(a) of the PPA. The nominated Arbitrators fixed their first

meeting on 7 May 2014, when both parties appeared and the Arbitrators’ fee was

fixed. However, the Arbitrators, by a letter dated 7 July 2014, highlighted their

inability to proceed with the arbitration proceedings on the ground that their fees

had not been paid.

6 Thereafter, the respondent filed AC No 1 of 2015 on 8 December 2014, seeking the

appointment of an arbitrator under Section 11(6) of the 1996 Act. This application

was opposed by the appellant on the ground that, in view of the provisions of

Section 86(1)(f) of the Electricity Act 2003 9, it was the State Electricity Commission

which was vested with the exclusive jurisdiction to adjudicate upon disputes

between licensees and generating companies. By the impugned judgment and

order dated 30 November 2016, the Single Judge of the High Court allowed the

application filed by the respondent under Section 11(6) of the 1996 Act. The Single

Judge held that the remedies under Section 86(1)(f) of the 2003 Act and under

Section 11(6) of the 1996 Act are independent of each other, and it was open to

the High Court to exercise its jurisdiction under Section 11(6). The appellant now

comes before this Court in appeal.

7 The submission of the appellant, which has been urged before this Court by Mr

Varun Chopra, learned counsel, is that the view which has been taken by the High

Court is contrary to the law which has been laid down by a two-Judge Bench of this

Court in Gujarat Urja Vikas Nigam Limited v Essar Power Limited 10.

9 “2003 Act”
10 (2008) 4 SCC 755, hereinafter referred to as “Gujarat Urja Vikas Nigam Limited”
4

8 Controverting the submissions, Mr Sanjay K Agrawal, learned counsel appearing on

behalf of the respondent, however, urged that the decision in Gujarat Urja Vikas

Nigam Limited (supra) would not apply to the facts of the present case since the

PPA was executed on 20 May 1999 and the termination by the Board was on 27

September 2001; both of these events have taken place before the enforcement of

the 2003 Act on 10 June 2003. It was further urged that the appellant did not raise

its objection stemming from Section 86(1)(f) of the 2003 Act when the High Court

appointed Arbitrators by the consent of both parties in its order dated21 January

2014 in AC No 76 of 2011 and also before the Arbitrators so appointed, and hence it

cannot be raised at this stage.

9 In the present case, the notice for the initiation of arbitration under Clause 12.3 of

the PPA was issued by the respondent on 30 May 2011. The commencement of the

arbitral proceedings by the invocation of the arbitration agreement would,

therefore, relate to 30 May 2011, when the notice invoking Clause 12.3 was issued.

Hence, the fact that the PPA and the notice of termination predate the 2003 Act

would not constitute material circumstances. Section 21 11 of the 1996 Act specifies

that unless otherwise agreed by the parties, the arbitral proceedings in respect of a

particular dispute would commence on the date on which a request for that

dispute to be referred to arbitration is received by the respondent. Hence, there

can be no manner of doubt that 30 May 2011 would be the material date, since it is

on this date that the notice invoking Clause 12.3 was issued by the respondent to

the appellant.

11 “21. Commencement of arbitral proceedings.—Unless otherwise agreed by the parties, the arbitral
proceedings in respect of a particular dispute commence on the date on which a request for that
dispute to be referred to arbitration is received by the respondent.”
5

10 The first issue which is raised in this appeal is governed by Gujarat Urja Vikas Nigam

Limited (supra). In that case, the power purchase agreement between the parties

was entered into on 30 May 1996, and the notice for referring the dispute to

arbitration was sent by one of the parties on 14 November 2005. The other party

opposed the notice by stating that the State Electricity Commission had exclusive

jurisdiction in accordance with Section 86(1)(f) of the 2003 Act. The Gujarat High

Court thereafter appointed an Arbitrator in an application under Section 11(6) of

the 1996 Act, which was impugned before this Court. Speaking for the two-Judge

bench, Justice Markandey Katju settled the position of law in paragraphs 26, 27 and

28 of the judgment, which are extracted below for convenience of reference:

“26. It may be noted that Section 86(1)(f) of the Act of
2003 is a special provision for adjudication of disputes
between the licensee and the generating companies.
Such disputes can be adjudicated upon either by the
State Commission or the person or persons to whom it is
referred for arbitration. In our opinion the word “and” in
Section 86(1)(f) between the words “generating
companies” and “to refer any dispute for arbitration”
means “or”. It is well settled that sometimes “and” can
mean “or” and sometimes “or” can mean “and” (vide
G.P. Singh’s Principles of Statutory Interpretation, 9th
Edn., 2004, p. 404).

27. In our opinion in Section 86(1)(f) of the Electricity Act,
2003 the word “and” between the words “generating
companies” and the words “refer any dispute” means
“or”, otherwise it will lead to an anomalous situation
because obviously the State Commission cannot both
decide a dispute itself and also refer it to some
arbitrator. Hence the word “and” in Section 86(1)(f)
means “or”.

28. Section 86(1)(f) is a special provision and hence will
override the general provision in Section 11 of the
Arbitration and Conciliation Act, 1996 for arbitration of
disputes between the licensee and generating
6

companies. It is well settled that the special law
overrides the general law. Hence, in our opinion, Section
11 of the Arbitration and Conciliation Act, 1996 has no
application to the question who can
adjudicate/arbitrate disputes between licensees and
generating companies, and only Section 86(1)(f) shall
apply in such a situation.”

This position has subsequently also been approved by two three-Judge benches of

this Court in Hindustan Zinc Limited v Ajmer Vidyut Vitran Nigam Limited 12 and NHAI

v Sayedabad Tea Company Limited 13.

11 From the above judgment, it is evident that this Court has held that Section 86(1)(f)

of the 2003 Act is a special provision which overrides the general provisions

contained in Section 11 of the 1996 Act. Section 86(1)(f) vests a statutory jurisdiction

with the State Electricity Commission to adjudicate upon disputes between

licensees and generating companies and to refer any dispute for arbitration. The

“and” between “generating companies” and “to refer any dispute for arbitration” is

to be read as an “or”, since the State Electricity Commission cannot obviously

resolve the dispute itself and also refer it to arbitration. Section 86(1)(f) is extracted

below:

“86.Functions of State Commission.— (1) The State
Commission shall discharge the following functions,
namely:-

*** ***
***

(f) adjudicate upon the disputes between the
licensees and generating companies and to
refer any dispute for arbitration;”

12 (2019) 17 SCC 82; hereinafter, referred to as “Hindustan Zinc Limited”
13 (2020) 15 SCC 161
7

12 Section 174 of the 2003 Act provides overriding effect to the 2003 Act

notwithstanding anything inconsistent contained in any other law for the time being

in force or in any instrument having effect by virtue of any law other than the

2003Act itself. Section 174 provides thus:

“174. Act to have overriding effect. — Save as otherwise
provided in Section 173, the provisions of this Act shall
have effect notwithstanding anything inconsistent
therewith contained in any other law for the time being
in force or in any instrument having effect by virtue of
any law other than this Act.”

13 We refer now to the second argument raised on behalf of the respondent, that the

appellant cannot raise an objection relying on Section 86(1)(f) of the 2003 Act in the

second application filed by it under Section 11(6) of the 1996 Act, when it had not

raised the same objection in the first application under Section 11(6) of the 1996 Act

or before the Arbitrators so appointed. It is pertinent to note that this argument was

rejected by the Single Judge of the High Court in the impugned judgment and

order dated 30 November 2016 in the following terms”

“9. I will be failing in my duty if the basic objection raised
by Shri Manoj Dubey about maintainability of this
application is not dealt with. Merely because in earlier
round of litigation, the objection of maintainability was
not taken, it will not preclude the other side to raise such
objection if it goes to the root of the matter. This is trite
law that jurisdiction cannot be assumed by consent of
the parties. If a statute does not provide jurisdiction to
entertain an application/petition, the petition cannot
be entertained for any reason whatsoever. Thus, I am
not inclined to hold that since for the reason that in the
earlier round of litigation i.e. A.C. No.76/2011 parties
reached to a consensus for appointment of Arbitrators,
this application is also maintainable. I deem it proper to
examine whether because of operation of Section 174
of the Act of 2003, the present application under the
Act of 1996 is not maintainable.”
8

14 A similar issue was raised before a three-Judge bench of this Court in Hindustan Zinc

Limited (supra), where an arbitrator was appointed by the State Electricity

Commission under Section 86(1)(f) of the 2003 Act with the consent of the parties.

Subsequently, the arbitral award was challenged under Section 34 of the 1996 Act

before a Commercial Court, and the Commercial Court’s decision was challenged

in an appeal under Section 37 of the 1996 Act where it was held that the State

Electricity Commission had no jurisdiction to appoint the arbitrator since Section

86(1)(f) refers to disputes only between licensees and generating companies, and

not licensees and consumers. When the matter reached this Court, the contention

was that the objection to jurisdiction could not have been raised in a proceeding

under Section 37 of the 1996 Act once the parties had consented to arbitration

earlier. Speaking for the Court, Justice Rohinton F Nariman held that if there is

inherent lack of jurisdiction, the plea can be taken at any stage and also in

collateral proceedings. He highlighted the well-established principle that a decree

passed by a court without subject matter jurisdiction is a nullity, and that its invalidity

could be set up whenever and wherever it is sought to be enforced or relied upon.

Such a defect of jurisdiction cannot be cured even by the consent of the parties.

The above dictum would apply to the present case.

15 In the above view of the matter, the order of the High Court appointing an

arbitrator under Section 11(6) of the 1996 Act is unsustainable. We accordingly

allow the appeal and set aside the impugned judgment and order of the High

Court dated 30 November 2016 in AC No 1 of 2015. However, this will not come in

the way of the respondent in taking recourse to such remedies as are available in

law. However, we have expressed no opinion either on the merits or the
9

objections of the appellant which, when urged, would be considered by the

appropriate forum. There shall be no order as to costs.

16 Pending application, if any, stands disposed of.

………..……………………….……………………..J.
[Dr Dhananjaya Y Chandrachud]

…..………….…….………..……………….………..J.
[M R Shah]

…………….…..…….………..……………….………..J.
[Sanjiv Khanna]

New Delhi;
March 23, 2021
-S-

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.