caselaws.org

Supreme Court of India
Garg Builders vs Bharat Heavy Electricals Limited on 4 October, 2021Author: S. Abdul Nazeer

Bench: S. Abdul Nazeer, Krishna Murari

REPORTABLE

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.6216 OF 2021
(Arising out of S.L.P. (C.) No. 16320 of 2018)

GARG BUILDERS …APPELLANT(S)

VERSUS

BHARAT HEAVY ELECTRICALS LIMITED …RESPONDENT(S)

JUDGMENT

S. ABDUL NAZEER, J.

Leave granted.

2. This appeal is directed against the Order of the Division Bench

of the High Court of Delhi dated 19.09.2017 in FAO(OS)

(COMM)No.120/2017 whereby it has upheld the judgment of the

learned Single Judge in OMP (COMM) No.28 of 2017 dated
Signature Not Verified

10.03.2017, resulting in denial of pendente lite interest on the
Digitally signed by
Anita Malhotra
Date: 2021.10.04
16:45:27 IST
Reason:

award amount to the appellant.

1
3. The respondent floated a tender for construction of boundary

wall at its 2×750 MW Pragati III Combined Cycle Power at Bawana,

Delhi (hereinafter referred to as ‘the project’). The appellant

submitted its bid for the project which was accepted by the

respondent. Pursuant to which, the respondent issued a Letter of

Intent (LOI) to the appellant dated 09.09.2008. Subsequently, on

24.10.2008 the parties entered into a contract which, inter alia,

contained the interest barring clause which is reproduced

hereunder:

“Clause 17: No interest shall be payable by BHEL on
Earnest Money Deposit, Security Deposit or on any
moneys due to the contractor.”

4. The disputes arose between the parties with respect to the

aforesaid contract and subsequently the appellant filed a petition

under Section 11 of the Arbitration and Conciliation Act, 1996 (for

short, “the 1996 Act”) before the Delhi High Court wherein the

Court vide Order dated 16.09.2011 appointed Hon’ble Mr. Justice

M.A. Khan (Retd.) as the sole Arbitrator to adjudicate the disputes.

The appellant in the claim petition, apart from claiming various

amounts under different heads, inter alia claimed pre­reference,

2
pendente lite and future interest at the rate of 24% on the value of

the award. Learned Arbitrator after hearing the contentions of both

the parties concluded that there is no prohibition in the contract

dated 24.10.2008 and LOI dated 09.09.2010 about payment of

interest for the pre­suit, pendente lite and future period. Therefore,

he awarded pendente lite and future interest at the rate of 10% p.a.

to the appellant on the award amount from the date of filing of the

claim petition i.e. 02.12.2011 till the date of realization of the award

amount.

5. The respondent challenged the said award under Section 34 of

the 1996 Act before the Delhi High Court in O.M.P. (COMM.)

28/2017 on various grounds, inter alia, on the ground that the

learned Arbitrator being creature of the arbitration agreement

travelled beyond the terms of the contract in awarding pendente lite

interest on the award amount as the same was expressly barred in

terms of the contract. The learned Single Judge vide his final

judgment and order dated 10.03.2017 held as under:

“The Arbitrator fell in error in holding that the
aforesaid clause only prescribed pre­reference
interest and not pendente lite interest. As stated
earlier, in terms of Section 31(7)(a) of the Act, the
3
power of the arbitral tribunal to award pre award
interest is contingent to the parties not agreeing to
the contrary. Pre­award interest includes both pre­
reference interest as well as pendente lite interest.
Thus, the conclusion of the Arbitrator that award of
pendente lite interest was not prescribed by clause
17 of the Agreement is not sustainable.

Accordingly, the impugned award to the extent
of award of pendente lite interest is set aside. The
petition is disposed of. No orders as to costs.”

6. As noticed above, the Division Bench of the High Court has

upheld the judgment and order of the Learned Single Judge in the

impugned order.

7. On 03.07.2018, this Court issued notice observing as under:

“Learned counsel for the petitioner has placed
reliance on an order of this Court in Ambica
Construction v. Union of India, (2017) 14 SCC 323.”

8. We have heard learned counsel for the parties and perused the

materials on record. Mr. Sanjay Bansal, learned counsel for the

appellant, contended that the learned Arbitrator had taken a

plausible view, in terms of the Clause 17 of the Contract and held

that the said clause does not bar the payment of interest for

pendente lite period. This argument was advanced in view of

4
judgment of this Court in Ambica Construction v. Union of

India1, wherein the appellant was entitled for the payment of

interest for the pendente lite period. He has also relied on another

judgment of this Court in Raveechee and Company v. Union of

India2 in support of his contentions. Further, it was argued by the

learned counsel that the Clause 17 of the Contract barring payment

of interest to the contractor on any sum due to the contractor, is

ultra vires and against the provisions of Section 28 of the Indian

Contract Act, 1872.

9. On the other hand, Mr. Pallav Kumar, learned counsel for the

respondent, submitted that Section 31(7)(a) of the 1996 Act gives

paramount importance to the contract entered into between the

parties and categorically restricts the power of an arbitrator to

award pre­reference and pendente lite interest when the parties

themselves have agreed to the contrary. He argued that if the

contract itself contains a specific clause which expressly bars the

payment of interest, then it is not open for the arbitrator to grant

pendente lite interest. It was further argued that Ambica

1 (2017) 14 SCC 323

2 (2018) 7 SCC 664
5
Construction (supra) is not applicable to the instant case because

it was decided under the Arbitration Act, 1940 whereas the instant

case falls under the 1996 Act. It was further argued that Section 3

of the Interest Act confers power on the Court to allow interest in

the proceedings for recovery of any debt or damages or in

proceedings in which a claim for interest in respect of any debt or

damages already paid. However, Section 3(3) of the Interest Act

carves out an exception and recognizes the right of the parties to

contract out of the payment of interest arising out of any debt or

damages and sanctifies contracts which bars the payment of

interest arising out of debt or damages. Therefore, Clause 17 of the

Contract is not violative of any the provisions of the Indian Contract

Act, 1872. In light of the arguments advanced, the learned counsel

prays for dismissal of the appeal.

10. We have carefully considered the submissions of the learned

counsel for both the parties made at the Bar. The law relating to

award of pendente lite interest by Arbitrator under the 1996 Act is

no longer res integra. The provisions of the 1996 Act give

paramount importance to the contract entered into between the

6
parties and categorically restricts the power of an arbitrator to

award pre­reference and pendente lite interest when the parties

themselves have agreed to the contrary. Section 31(7)(a) of the

1996 Act which deals with the payment of interest is as under :

“31(7)(a) Unless otherwise agreed by the parties,
where and insofar as an arbitral award is for the
payment of money, the arbitral tribunal may include
in the sum for which the award is made interest, at
such rate as it deems reasonable, on the whole or
any part of the money, for the whole or any part of
the period between the date on which the cause of
action arose and the date on which the award is
made.”

11. It is clear from the above provision that if the contract

prohibits pre­reference and pendente lite interest, the arbitrator

cannot award interest for the said period. In the present case,

clause barring interest is very clear and categorical. It uses the

expression “any moneys due to the contractor” by the employer

which includes the amount awarded by the arbitrator.

12. In Sayeed Ahmed and Company v. State of Uttar Pradesh &

Ors.3 this Court has held that a provision has been made under

Section 31(7)(a) of the 1996 Act in relation to the power of the

3 (2009) 12 SCC 26
7
arbitrator to award interest. As per this section, if the contract bars

payment of interest, the arbitrator cannot award interest from the

date of cause of action till the date of award.

13. In Sree Kamatchi Amman Constructions v. Divisional

Railway Manager (Works), Palghat & Ors. 4 it was held by this

Court that where the parties had agreed that the interest shall not

be payable, the Arbitral Tribunal cannot award interest between the

date on which the cause of action arose to the date of the award.

14. Bharat Heavy Electricals Limited v. Globe Hi­Fabs Limited 5

is an identical case where this Court has held as under :

“16. In the present case we noticed that the clause
barring interest is very widely worded. It uses the
words “any amount due to the contractor by the
employer”. In our opinion, these words cannot be
read as ejusdem generis along with the earlier words
“earnest money” or “security deposit”.”

15. In Sri Chittaranjan Maity v. Union of India6 it was

categorically held that if a contract prohibits award of interest for

pre­award period, the arbitrator cannot award interest for the said

period.

4 (2010) 8 SCC 767

5 (2015) 5 SCC 718

6 (2017) 9 SCC 611
8
16. Therefore, if the contract contains a specific clause which

expressly bars payment of interest, then it is not open for the

arbitrator to grant pendente lite interest. The judgment on which

reliance was placed by the learned counsel for the appellant in

Ambica Construction (supra) has no application to the instant

case because Ambica Construction was decided under the

Arbitration Act 1940 whereas the instant case falls under the 1996

Act. This has been clarified in Sri Chittaranjan Maity (supra) as

under :

“16. Relying on a decision of this Court in Ambica
Construction v. Union of India, (2017) 14 SCC 323,
the learned Senior Counsel for the appellant
submits that mere bar to award interest on the
amounts payable under the contract would not be
sufficient to deny payment on pendente lite interest.
Therefore, the arbitrator was justified in awarding
the pendente lite interest. However, it is not clear
from Ambica Construction (supra) as to whether it
was decided under the Arbitration Act, 1940 (for
short “the 1940 Act”) or under the 1996 Act. It has
relied on a judgment of Constitution Bench in State
of Orissa v. G.C. Roy, (1992) 1 SCC 508. This
judgment was with reference to the 1940 Act. In the
1940 Act, there was no provision which prohibited
the arbitrator from awarding interest for the pre­
reference, pendente lite or post­award period,
whereas the 1996 Act contains a specific provision
which says that if the agreement prohibits award of
interest for the pre­award period, the arbitrator
9
cannot award interest for the said period. Therefore,
the decision in Ambica Construction (supra) cannot
be made applicable to the instant case.”

17. The decision in Raveechee and Company (supra) relied on by

the learned counsel for the appellant is again under the Arbitration

Act 1940 which has no application to the facts of the present case.

18. Having regard to the above, we are of the view that the High

Court was justified in rejecting the claim of the appellant seeking

pendente lite interest on the award amount.

19. This takes us to the next question as to whether Clause 17 of

the Contract is ultra vires in terms of Section 28 of the Indian

Contract Act, 1872. According to Section 28, a contract is void to

the extent it restricts absolutely a party from enforcing his rights by

usual proceedings in ordinary courts or if it limits the time within

which he may enforce his rights. Exception I to this section

contains a rule that a contract by which two or more persons agree

that any dispute which has arisen or which may arise between

them in respect of any subject or class of subjects shall be referred

to arbitration is not illegal. The question, therefore, is whether the

10
contracts barring payment of interest extinguish the rights of the

parties. Exception 1 to Section 28 reads as under :

“Exception 1: Saving of contract to refer to
arbitration dispute that may arise. – This section
shall not render illegal a contract, by which two or
more persons agree that any dispute which may
arise between them in respect of any subject or
class of subjects shall be referred to arbitration, and
that only the amount awarded in such
arbitration shall be recoverable in respect of the
dispute so referred.”

20. Exception I to Section 28 saves contracts where the right to

move the Court for appropriate relief is restricted but where the

parties have agreed to resolve their dispute through arbitration.

Thus, a lawful agreement to refer the matter to arbitration can be

made a condition precedent before going to courts and it does not

violate Section 28. No cause of action then accrues until the

Arbitrator has made the award and the only amount awarded in

such arbitration is recoverable in respect of the dispute so referred.

Section 31(7)(a) of the 1996 Act which allows parties to waive any

claim to interest including pendente lite and the power of the

11
Arbitrator to grant interest is subject to the agreement of the

parties.

21. It is pertinent to note that interest payments are governed in

general by the Interest Act, 1978 in addition to the specific statutes

that govern an impugned matter. Section 2 (a) of the Interest Act

defines a “Court” which includes both a Tribunal and an Arbitrator.

In turn, Section 3 allows a “Court” to grant interest at prevailing

interest rates in various cases. The provisions of Section 3 (3) of the

Interest Act, 1978 explicitly allows the parties to waive their claim

to an interest by virtue of an agreement. Section 3(3)(a)(ii) states

that the Interest Act will not apply to situations where the payment

of interest is “barred by virtue of an express agreement”.

22. Thus, when there is an express statutory permission for the

parties to contract out of receiving interest and they have done so

without any vitiation of free consent, it is not open for the Arbitrator

to grant pendent lite interest. We are of the considered opinion that

Clause 17 of the contract is not ultra vires in terms of Section 28 of

the Indian Contract Act, 1872.

12
23. In the result, the appeal fails and is accordingly dismissed.

Having regard to the facts and circumstances of the case, we direct

the parties to bear their own costs.

24. Pending application, if any, shall also stand disposed of.

…………………………………J.
(S. ABDUL NAZEER)

…………………………………J.
(KRISHNA MURARI)
New Delhi;
October 4, 2021.

13

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.