caselaws.org

Supreme Court of India
Khatema Fibres Ltd. vs New India Assurance Company Ltd. on 28 September, 2021Author: V. Ramasubramanian

Bench: Hemant Gupta, V. Ramasubramanian

REPORTABLE

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.9050 OF 2018

Khatema Fibres Ltd. … Appellant (s)

Versus

New India Assurance Company Ltd. & Anr. … Respondent(s)

JUDGMENT

V. Ramasubramanian, J.

1. Aggrieved by the Judgment of the National Consumer Disputes

Redressal Commission (for short “National Commission”) confining the

compensation payable to them only to the extent of the assessment as

made by the final Surveyor, the complainant before the National
Signature Not Verified

Commission has come up with the above appeal.
Digitally signed by
Jayant Kumar Arora
Date: 2021.09.28
16:36:45 IST
Reason:

1
2. We have heard Ms. Meenakshi Arora, learned senior counsel for

the appellant and Mr. Joy Basu, learned senior counsel for the

respondent­Insurance Company.

3. The appellant took a “Standard Fire and Social Perils” policy for the

period from 7.05.2007 to 6.05.2008, for a sum of Rs.42,40,00,000/­.

When the policy was in force, a fire broke out in the factory premises of

the appellant on 15.11.2007.

4. The appellant submitted a claim on 19.11.2007, estimating the

quantity of waste paper destroyed by fire at 8500 MT and its value at

Rs.13,00,00,000/­.

5. One M/S Adarsh Associates, appointed by the respondent­

Insurance Company, conducted a survey, sought documents from the

appellant, raised queries and received clarifications from the appellant

and submitted a final report dated 9.01.2009, assessing the loss

suffered by the appellant on account of the fire accident as

Rs.2,86,17,942/­.

6. Though the appellant, vide their letter dated 2.5.2009, objected to

the survey and assessment report and sought the appointment of

2
another surveyor, the respondent informed the appellant by their letter

dated 21.08.2009 that the claim of the appellant has been approved

only to the extent of Rs.2,85,76,561/­, in full and final settlement. The

appellant, through letter dated 14.09.2009, again raised objections to

the Survey Report, but the respondent informed the appellant by their

letter dated 7.10.2009 that the claim could be finalized only for the

amount indicated in the letter dated 21.08.2009.

7. Therefore, the appellant filed a consumer complaint before the

National Commission under Section 21(a)(i) of the Consumer Protection

Act, 1986, claiming: (i) compensation in a sum of Rs.1364.88 lakhs

towards the loss suffered in the fire accident; (ii) compensation in a sum

of Rs.2095.52 lakhs, for the financial stress caused by the respondent

by delaying the processing of the claim; (iii) interest @ 18% p.a. on the

compensation amount of Rs.1364.88 lakhs from November, 2007 till

31.12.2009; and (iv) the cost of litigation estimated at Rs.1,00,000/­.

8. The National Commission, by its Judgment dated 3.07.2018

rejected the claim of the appellant under both the heads, but directed

the respondent to pay only the amount of Rs.2,85,76,561/­ as admitted

3
by them. This amount was directed to be paid to the appellant with

interest @ 9% p.a. from 15.11.2007, only till the date the Insurance

Company had made the offer. It is against the said Judgment of the

National Commission that the appellant has come up with the above

appeal under Section 23 of the Consumer Protection Act, 1986.

9. Admittedly, the respondent­Insurance Company appointed one

Shri Kapil Vaish, a Chartered Accountant, on 16.11.2007 itself (the day

following the date of fire accident), to conduct a spot inspection and file a

status report. When he visited the factory premises, the fire fighting was

still going on and it was found that the fire had taken place only in the

waste paper yard of the factory. In the status report submitted by

Shri Kapil Vaish on 16.11.2007, he indicated that the fire had affected

waste paper bales lying in an area measuring 27 mtrs. X 55 mtrs. =

1485 sq.mtrs. in open compound. Presuming that waste paper would

have been stacked in bunches of six bales, one on top of the other and

that the quantity of affected waste paper could be around 5000 MT,

whose cost may be around Rs.20­22 per kg., Shri Kapil Vaish roughly

estimated the loss to be around Rs.10­11 crores. The appellant

4
themselves estimated the quantity of waste paper burnt in the fire to be

8500 MT valued at Rs.13,00,00,000/­.

10. M/s Adarsh Associates who conducted the actual survey with

reference to the records and other evidence available with the appellant,

had two options before them for arriving at the quantity of material

destroyed by fire. The first option was to proceed on the basis of the

stock registers and other records of the appellant company to fix the

quantum of loss. The next option was to proceed on the basis of

volumetric analysis, by taking the measurement of the open yard in

which the fire broke out, finding out the optimum capacity of the yard

with reference to the measurement of the bales of paper stored therein

and then working out the quantum of material destroyed.

11. The Surveyor adopted the second option namely that of volumetric

analysis and assessed the quantity of raw material damaged at

2264.400 MT. He valued this raw material @ Rs.15137.35/­ per MT,

inclusive of CENVAT. Thus, he arrived at the value of the material

damaged to be Rs.3,42,77,015.34/­. Then the Surveyor fixed the salvage

value at Rs.18,92,200/­ and deducted the same from the value of the

5
raw material, to arrive at the gross assessed loss at Rs.3,23,84,815.34/­

From out of this amount the Surveyor deducted the CENVAT as well as

1% towards soiled goods. After so doing, the surveyors arrived at the

value of loss at Rs.2,86,17,942/­.

12. For proceeding on volumetric analysis method, the Surveyor took

the measurement of the open yard as 27 mtrs. X 55 mtrs. = 1485 sq.

mtrs. This was on the basis of the Status Report of the Chartered

Accountant who made the spot inspection on 16.11.2007 when the fire

fighting was still in progress. There was a finding in the status report of

the Chartered Accountant that the material affected by the fire was lying

in the yard measuring 27 mtrs. X 55 mtrs. = 1485 sq. mtrs. Therefore,

the Surveyor took this measurement as the starting point and proceeded

as detailed above.

13. Keeping the above background in mind, let us now come to the

grievance of the appellant, against the Judgment of the National

Commission. Ms. Meenakshi Arora, learned senior counsel for the

appellant contended that the National Commission committed a serious

error first in taking the net weight of waste paper bales burnt/damaged

6
during the incident as 2264.400 MT, as against the claim of the

appellant that the net weight of the material damaged was 8332 MT.

According to the learned senior counsel, there were no discrepancies in

the various records and stock registers maintained by the appellant with

respect to the quantity and weight of material stored in the open yard,

but the Surveyor chose to reject the same arbitrarily and proceeded on

volumetric analysis basis. The learned senior counsel further contended

that even while proceeding on volumetric analysis basis, the Surveyor

did not do justice. Though, the total area of the open yard was 27 mtrs.

X 100 mtrs. = 2700 sq. mtrs., the Surveyor took the measurement as 27

mtrs. X 55 mtrs = 1485 sq. mtrs., despite they themselves finding that

the area was 22.5 mtrs. X 105 mtrs. = 2362 mtrs. This, according to the

learned senior counsel for the appellant, resulted in gross injustice to

the appellant in the matter of assessment of the quantum of loss.

14. Another gross error committed by the Surveyor, according to the

learned senior counsel for the appellant, is that despite finding the net

weight per bale as 988.889 kgs. as per Annexure A­3 to the Survey

Report dated 9.01.2009, the Surveyor took the net weight as 900 kgs.

7
per bale, merely because the complainant had indicated the same to be

900 kg. per bale. The Surveyor had thus adopted double standards, in

taking either what is found by them or what is claimed by the appellant,

whichever was less. This according to the learned senior counsel for the

appellant resulted in the Insurance Company eventually admitting the

claim only to the extent of less than 25% of the total amount of loss

suffered by the appellant.

15. Justifying the judgment of the National Commission, it is

contended by Mr. Joy Basu, learned senior counsel for the respondent

that M/S Adarsh Associates were appointed by the respondent as

Surveyors to act as such in terms of Section 64UM(2) of the Insurance

Act, 1938 and that they have assessed the loss in a scientific manner.

As the Surveyors appointed by the respondent are experts in the field,

who have gone into every minute detail by examining the records of the

appellant scientifically, their report is unassailable. In the case on hand,

it was admitted even by the appellant, to Shri Kapil Vaish who

conducted spot inspection that there was no physical verification of the

stock of raw material in the recent past and that the consumption of

8
raw material was recorded only on estimated yield basis. Therefore, the

learned senior counsel for the respondent contended, by drawing our

attention to the letter dated 5.12.2007 sent by the appellant that the

appellant themselves were adopting volumetric analysis for the

quantification of the stock. The learned senior counsel relied upon the

decisions of this Court in (i) United India Insurance Company Ltd.

And Others vs. Roshan Lal Oil Mills Ltd. And others1; (ii) Sikka

Papers Limited vs. National Insurance Company Limited And

Others2; and (iii) New India Assurance Company Limited vs. Luxra

Enterprises Private Limited And Another.3, in support of his

contention that the report of the surveyor is an important document and

that Courts may have to show deference to the report of the surveyor

appointed in terms of section 64UM(2) of the Act.

16. We have carefully considered the rival contentions.

17. As could be deciphered from the grounds of appeal and the

submissions made at the time of hearing, the grievance of the appellant

1 2000 (10) SCC 19
2 2009 (7) SCC 777
3 2019(6) SCC 36

9
is primarily with respect to the quantification of the net weight of the

raw material destroyed in the fire accident. The price of the material,

fixed by the Surveyor at Rs.15137.35/­ per MT, is not seriously

disputed. Though a dispute is raised with regard to the salvage value,

the contention relating to the same is very weak and feeble and hence

we would not get into the same.

18. Insofar as the quantification of the weight of raw material damaged

in the fire is concerned, the Surveyor had, in fact, worked out the

quantity, as seen from paragraph 9.7 of his Report, both on the basis of

the appellants’ stock records and also on the basis of volumetric

analysis of the area involved.

19. After extensively analyzing what is reflected in the stock records of

the appellant, the Surveyor came to the conclusion that there were

discrepancies which could not be reconciled. It is recorded by the

Surveyor in paragraph 9.8.2 of the Report that the appellant initially

submitted one set of documents, which reflected a huge quantity of

imported waste paper both for general use and for newsprint. Therefore,

the Surveyors requested the appellant to submit documents in support

10
of reversal of CENVAT, on the damaged quantity of waste paper.

Immediately the appellant submitted a revised claim bill along with a

fresh set of documents. In fact imported waste paper for newsprint is

exempt from payment of customs duty subject to submission of end use

certificate. In the revised set of documents, the quantity of closing

stocks of imported waste paper meant for newsprint was substantially

increased. The Surveyor also found in paragraph 9.8.7.7 of their Report

that there was a huge difference between the overall quantity of burnt/

damaged stock of waste paper arrived at on the basis of the initial set of

records and the overall quantity of burnt/damaged stock of waste paper

arrived at on the basis of the revised set of records. Therefore, the

Surveyor decided to adopt volumetric analysis method rather than rely

upon the stock records of the insured.

20. We fail to understand how the Surveyors could be found fault with,

for rejecting the stock records of the insured, especially in the light of

the circumstances narrated above. When the insured produced 2 sets of

records and the quantum of material destroyed by fire arrived on the

basis of these records showed huge discrepancies, the Surveyor had no

11
alternative except to reject these records and proceed on volumetric

analysis. In any case, as rightly pointed out by the learned counsel for

the respondent, the appellant themselves have admitted to Shri Kapil

Vaish, who went for spot inspection when the fire was still raging, that

the appellant had not conducted physical verification of its raw material

stock in the recent past and that the consumption was recorded on

estimated yield basis. In their own letter dated 5.12.2007, the appellant

had conceded that stock taking was done on the basis of receipts and

consumptions as well as physical verification on volumetric basis. The

following extract from the appellant’s letter dated 5.12.2007 would

clinch the issue in this regard; “the estimates for stocks and burnt

quantities may not be appearing close to stock inventory maintained in

the books, since the estimates prepared for burnt material was not on

weighment basis but on volumetric basis”. Therefore, we find that the

refusal of the Surveyor to go by the stock records of the appellant, but to

adopt volumetric analysis, was fully justified and no exception can be

taken to the same.

21. On the method of volumetric analysis adopted by the Surveyor, the

12
first grievance of the appellant is that the physical measurement of the

stockyard was 27 mtrs. X 100 mtrs. = 2700 sq. mtrs. But the Surveyor

took the measurement as given by Shri Kapil Vaish, namely, 27 mtrs. X

55 mtrs. = 1485 sq. mtrs., despite finding in para 4.7 of the Survey

Report that the actual measurement was 22.5 mtrs. X 105 mtrs. = 2362

sq. mtrs. Such a drastic reduction in the total measurement of the area

of the open stock yard, according to the appellant, led to the quantum of

the material burnt/damaged getting substantially reduced.

22. But it is seen from paragraph 9.4 and 9.5 of the Surveyors’ Report

that there were actually three different measurements available with the

Surveyor, with a huge variation between one another. The Status Report

dated 16.11.2007 filed by Shri Kapil Vaish, about which the appellant

did not have any serious grievance, recorded clearly as follows “it was

estimated that the fire had affected waste paper bales lying in the area of

27 mtrs. X 55 mtrs. = 1485 sq. mtrs. in the open compound.” The

appellant claimed in their letter dated 13.12.2007 addressed to the

Surveyor that the total affected area was 27 mtrs. X 100 mtrs. = 2700

sq. mtrs. These two documents, namely, the Status Report of Shri Kapil

13
Vaish and the measurement given by the appellant in their letter dated

13.12.2007 were in contrast to the measurement given by the Tehsildar,

Khatima, relied upon by the appellant themselves, according to which

the measurement was 90 mtrs. X 23 mtrs. = 2070 mtrs.

23. Faced with three different measurements as aforesaid, the

Surveyor reconciled the same by holding that despite the measurement

of the open stockyard being 22.5 mtrs. X 105 mtrs. = 2362 mtrs., the

area affected by fire could only be 1485 sq. mtrs. This is for the reason

that during their visit to the site, the damaged/burnt bales as well as

loose waste papers were found spread over an area of 22.5 mtrs. X 105

mtrs. and the insured was carrying out salvaging/segregation in the

said area after the extinction of the fire. In other words, what was

witnessed by Shri Kapil Vaish personally on 16.11.2007 was that the

fire was confined to an area of 1485 sq.mtrs, but what was seen by the

Tehsildar and the Surveyor was of a larger area where the salvage

operation was going on. Therefore, the Surveyor chose to go by the

measurement of the area mentioned in the Status Report of Shri Kapil

Vaish, who had the benefit of witnessing what was happening when fire

14
fighting was still in progress. In such circumstances, we find nothing

wrong in the Surveyor taking the measurement of the area of the

stockyard affected by fire, as 27 mtrs. X 55 mtrs. = 1485 sq. mtrs. for

the purpose of volumetric analysis.

24. At this stage it will be useful to extract the table given by the

Surveyor in paragraph 9.9.2 of his Report, where detailed calculations

are provided as to how the net weight of waste paper burnt/damaged

during the incident was arrived at:

1. Total area considered for storage bales Sq Mtr 1485
in open
2. Less: 20% are considered for gaps/open Sq Mtrs 297
spaces while storing bales and other
open space for movement etc.
3. Total affected area, considered for Sq Mtr 1188
storage (1­2)
4. Average area per bale, as considered by Sq Mtr 2.007
us
5. Therefore no. of bales stored in one layer Nos. 592
of local area (1188 divided by 2.007)
6. Total nos of bales in the affected stacks, Nos 2960
considering 5 bales in height (592 x 5)
7. Av weight per bale as considered by us. Kgs 900
8. Therefore, total weight of bales stored in Kgs 2664000
affected area/volume (2960 x 900)
9. Less: 15% of above bales / weight Kgs 399600
considered as shifted / save during fire
fighting
10. New weight of waste paper bales burnt/ Kgs 2264400
damaged during the incident (8­9)

15
25. An objection was raised by Ms. Meenakshi Arora, learned senior

counsel for the appellant about 20% reduction made by the Surveyor in

the measurement of the area. Such a reduction was made by the

Surveyor, on the ground that gaps/space was required for the

movement of men and material. It is her contention that when

admittedly the appellant was using forklifts to move and store material,

there was no question of leaving any vacant space.

26. But we do not agree. The allowance of some space within the open

stockyard, for the purpose of movement of men and material is logical. It

is not possible for us to accept that the whole space in the stockyard

was completely stacked by material without any space for movement.

Without providing adequate gaps and spaces within the open courtyard,

it would not have been possible for the appellant to remove the material

for the purpose of processing, even if forklifts were used. Therefore, the

objection to the provision for open space/gaps is unfounded.

27. The next crucial objection of the appellant is to the adoption of the

overall weight per bale at 900 kgs. According to the appellant, the

Surveyors themselves calculated the average weight per bale in

16
Annexure A­3 to their report as 988.889 kgs. and that, therefore, this

could not have been reduced to 900 kgs. per bale.

28. But the appellant has to blame themselves for this. In the

calculation sheet annexed to the letter dated 13.12.2007 addressed to

the Surveyor, the appellant themselves estimated the average weight per

bale to be 900 kgs. What is arrived at by the Surveyor, in Annexure A­3

to their Report is based only upon the sizes of different types of bales

and the areas occupied by different types of bales. Annexure A­3 to the

Surveyors’ Report arrives at the average weight per bale by multiplying

the size of the bales by the area occupied. There was no reason for the

Surveyor to be more royal than the king by adopting the average weight

per bale on the basis of paper calculations, when the party himself has

provided the average weight to be 900 kgs. per bale.

29. Thus, we find that all the objections of the appellant to the

Surveyors’ Report are wholly unsustainable and the National

Commission rightly rejected those objections. As a matter of fact we

have taken pains to go into elaborate factual details, as this is a first

appeal under Section 23 of the Consumer Protection Act, 1986.

17
30. As correctly pointed out by the National Commission, the appellant

was not entitled to succeed unless they were able to establish any

deficiency in service on the part of the Insurance Company. The

expression deficiency is defined in Section 2(1)(g) of the Consumer

Protection Act, 1986, as follows:

“2(1)(g) deficiency” means any fault, imperfection, shortcoming
or inadequacy in the quality, nature and manner of
performance which is required to be maintained by or under
any law for the time being in force or has been undertaken to
be performed by a person in pursuance of a contract or
otherwise in relation to any service”

31. This is not a case where the Insurance Company has repudiated

the claim of the appellant arbitrarily or on unjustifiable grounds. This is

a case where the claim of the appellant has been admitted, to the extent

of the loss as assessed by the Surveyor. In cases of this nature the

jurisdiction of the special forum constituted under the Consumer

Protection Act, 1986 is limited. Perhaps if the appellant had gone to the

civil court, they could have even summoned the Surveyor and cross

examined him on every minute detail. But in a complaint before the

Consumer Forum, a consumer cannot succeed unless he establishes

deficiency in service on the part of the service provider.

18
32. It is true that even any inadequacy in the quality, nature and

manner of performance which is required to be maintained by or

under any law or which has been undertaken to be performed

pursuant to a contract, will fall within the definition of the expression

‘deficiency’. But to come within the said parameter, the appellant

should be able to establish (i) either that the Surveyor did not comply

with the code of conduct in respect of his duties, responsibilities and

other professional requirements as specified by the regulations made

under the Act, in terms of Section 64UM(1A) of the Insurance Act, 1938,

as it stood then; or (ii) that the insurer acted arbitrarily in rejecting the

whole or a part of the Surveyor’s Report in exercise of the discretion

available under the Proviso to section 64UM(2) of the Insurance Act,

1938.

33. Section 64UM (2) of the Insurance Act, 1938, before its amendment

by Act 5 of 2015, mandated that no claim equal to or exceeding a sum of

rupees twenty thousand only shall be admitted for payment unless the

insurer had obtained a report from an approved surveyor or loss

19
assessor.4 This provision read as follows:

“(2) No claim in respect of a loss which has occurred in India
and requiring to be paid or settled in India equal to or
exceeding twenty thousand rupees in value on any policy of
insurance, arising or intimated to an insurer at any time after
the expiry of a period of one year from the commencement of
the Insurance (Amendment) Act, 1968, shall, unless otherwise
directed by the [Authority], be admitted for payment or settled
by the insurer unless he has obtained a report, on the loss
that has occurred, from a person who holds a licence issued
under this section to act as a surveyor or loss assessor
(hereafter referred to as “approved surveyor or loss
assessor”):

34. But the Proviso to sub­section (2) of section 64UM also recognized

the right of the insurer to pay any amount different from the amount as

assessed by the approved surveyor or loss assessor. The proviso reads

as follows:

“Provided that nothing in this sub­ section shall be deemed
to take away or abridge the right of the insurer to pay or settle
any claim at any amount different from the amount assessed
by the approved surveyor or loss assessor.”

35. This is why the law is settled that the surveyor’s report is not the

last and final word. It has been held by this Court in several decisions,

that the surveyor’s report is not so sacrosanct as to be incapable of

4 After amendment through Act 5 of 2015, what was sub­section (2) earlier, has become sub­section (4) with the
modification
that the words “twenty thousand rupees” have been substituted by the words “amount specified in the Regulations by the
Authority”.

20
being departed from. A useful reference can be made in this regard to

the decision of this court in New India Assurance Company Limited

vs. Pradeep Kumar5.

36. The Insurance Act, 1938 even while assigning an important role for

the surveyor, casts an obligation on him under sub­section (1A) of

section 64UM6 to comply with the code of conduct in respect of his

duties, responsibilities and other professional requirements as specified

by the regulations made under the Act. This provision reads as follows:

“(1A) Every surveyor and loss assessor shall comply with the
code of conduct in respect of their duties, responsibilities and
other professional requirements as may be specified by the
regulations made by the Authority.”

37. Two things flow out of the above discussion, They are (i) that the

surveyor is governed by a code of conduct, the breach of which may give

raise to an allegation of deficiency in service; and (ii) that the discretion

vested in the insurer to reject the report of the surveyor in whole or in

part, cannot be exercised arbitrarily or whimsically and that if so done,

there could be an allegation of deficiency in service.

5 (2009) 7 SCC 787
6 Now sub-section (2) of section 64 UM after amendment under Act 5 of 2015

21
38. A Consumer Forum which is primarily concerned with an

allegation of deficiency in service cannot subject the surveyor’s report to

forensic examination of its anatomy, just as a civil court could do. Once

it is found that there was no inadequacy in the quality, nature

and manner of performance of the duties and responsibilities of

the surveyor, in a manner prescribed by the Regulations as to

their code of conduct and once it is found that the report is not

based on adhocism or vitiated by arbitrariness, then the

jurisdiction of the Consumer Forum to go further would stop.

39. In the light of the above we are of the considered view that the

Judgment of the National Commission does not call for any interference.

Hence the appeal is dismissed. No costs.

…..…………………………..J.
(Hemant Gupta)

.…..………………………….J.
(V. Ramasubramanian)

NEW DELHI
SEPTEMBER 28, 2021

22

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.