caselaws.org

Supreme Court of India
Shubhas Jain vs Rajeshwari Shivam on 20 July, 2021Author: Hon’Ble Ms. Banerjee

Bench: Hon’Ble Ms. Banerjee, V. Ramasubramanian

1

NON-REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 2848 OF 2021
(Arising out of SLP (C) No.1837 of 2021)

SHUBHAS JAIN Appellant(s)

VERSUS

RAJESHWARI SHIVAM & ORS. Respondent(s)

J U D G M E N T

INDIRA BANERJEE, J.

Leave granted.

2. This appeal is against a final judgment and order dated

24.11.2020 passed by the Bombay High Court, disposing of the writ

petition WP-LD-VC- No.163/2020 filed by the Respondent No.1, a

tenant of the Appellant, and giving liberty to the Respondent No.1

to remove an adjoining wall with the assistance of architects M/s.

Shetgiri and Associates, without damaging the property of the

Appellant.

3. The Appellant is the owner of the structure admeasuring 1069
Signature Not Verified

sqm. at Vishram (Mahavir) Baug Compound, Plot bearing CTS No.792,
Digitally signed by
SUNIL KUMAR
Date: 2021.08.09
16:57:22 IST
Reason:
P.L. Lokhande Marg, Chembur, Mumbai, hereinafter referred to as
2

the “premises in question”.

4. The Appellant states that the premises in question is

comprised of 3 three-storied interlinked structures, constructed

by the predecessors-in-interest of the Appellant in 1930. The

first structure has 6 rooms, the second structure has 10 rooms and

the third structure has 9 rooms. There were about 24 tenants at

the premises in question, including the Respondent No.1.

5. It is the case of the Appellant that the impugned order has

been passed, overlooking the submission of the Respondent-

Municipal Corporation with regard to the precarious condition of

the premises in question, the report dated 15.05.2015 of the

Technical Advisory Committee to whom the Respondent-Municipal

Corporation had made a reference, and the Structural Audit Report

prepared by M/s Manohar Ashatavadhani & Associate opining that

the building is in a critical and dangerous situation in C-1

category.

6. Buildings in Mumbai in need of repair are classified into C1,

C2-A, C2-B and C3 categories having regard to their condition.

Category C1 buildings are those which require immediate evacuation

and demolition, Category C2-A buildings are also required to be

evacuated. Category C-2A buildings require major structural

repairs and/or partial demolition. C-2B buildings are repairable
3

without eviction, but need structural repairs. C-3 buildings do

not require eviction. They need only minor repairs.

7. The Appellant says that the Petitioner has entered into

arrangements with all the tenants except 6 including the

Respondent No.1/writ petitioner who have not agreed to vacate the

premises in question. All the other tenants have duly vacated.

8. It is alleged that the structures at the premises in

question, which are in a dilapidated and dangerous condition, have

been declared as of the C-1 category. One of the structures is of

the C-2A category. The Appellant submits that, the structures

being interlinked, structural repair of any one structure would

affect the stability of the adjacent structure.

9. M/s. Manohar Ashthavadhani and Associates had prepared a

Structural Audit Report dated 25.5.2014 of the premises in

question, concluding:

“In view of the facts and conditions explained
above, it is noticed that the structural condition of
almost all buildings (particularly R.C.C. buildings) is
dangerous and critical. The buildings are beyond
economical repairs and repair is not financially viable.
The buildings are dangerous and unsafe to stay. Hence
buildings will have to be vacated urgently for safety of
occupants.
It is advised to do the propping to dangerous
4

portion of the building immediately for safety of the
occupants till the buildings are vacated.
The owner occupants and the local authority has to
take urgent decision on the action.”

10. On or about 19.07.2014, the Respondent-Municipal Corporation

issued a notice under Section 488 of the Bombay Municipal

Corporation Act, 1888 (now known as the Mumbai Municipal

Corporation Act) and hereinafter referred to as the Municipal

Corporation Act, for inspection of the structures at the premises

in question.

11. A notice under Section 354 of the Municipal Corporation Act

was issued, for demolition of the premises in question to

safeguard human life, as the building had been declared as of C-1

category.

12. According to the appellant, the notice under Section 354 of

the Bombay Municipal Corporation Act was challenged by the

Respondent No.1 in the City Civil Court, Bombay by filing LC Suit

No. 702 of 2015. However, by an order dated 13.3.2015, the City

Civil Court refused to grant stay of demolition.

13. On or about 08.04.2015, the Respondent No.1 challenged the

order of the City Civil Court in the High Court by filing an

appeal. The appeal was rejected.
5

14. Thereafter, on or about 15.05.2015, the Respondent-Municipal

Corporation referred the matter before the Technical Advisory

Committee as there were contrary reports. The Technical Advisory

Committee went through the different Structural Audit Reports and

thereafter opined that the building was temporarily repairable.

15. The Respondent No.1 and other tenants thereafter gave a

certificate of stability dated 13.11.2015 by M/s Crown

Consultants, stating that the structure was safe for the next five

years, subject to annual civil and structural maintenance work.

Over five years have already elapsed since the date of issuance of

the Certificate.

16. On 25.01.2019, the Respondent-Municipal Corporation issued a

notice to the Appellant under Section 353(B) of the Municipal

Corporation Act calling upon the Appellant to get the building

examined by a Licensed Structural Engineer.

17. On 19.02.2019, M/s Manohar Ashtavadhani & Associates

submitted a report stating that Structure No.1 and Structure No.2

were in critical and dangerous condition and fell under C-1

category and Structure No. 3 urgently required major repairs and

was classifiable in C2-A category.
6

18. On 22.04.2019, the Appellant forwarded the said report to the

Respondent-Municipal Corporation. On 16.10.2019, the Respondent

No.1 and other tenants submitted the Structural Audit Report dated

16.10.2019 issued by M/s Crown Consultant Architect to the

Respondent-Municipal Corporation. Thereafter, on 10.01.2020, the

Respondent-Municipal Corporation referred the matter to the

Technical Advisory Committee in view of contradictory reports.

19. The Technical Advisory Committee conducted hearing on

19.06.2020 and found the condition of the said buildings very

dangerous as the same were over 90 years old. The Technical

Advisory Committee found that no civil and structural maintenance

had been carried out in the last four years as advised by the

consultant in his Stability Certificate dated 13.11.2015.

Therefore, the structures were declared as of C-1 category.

20. On 02.07.2020, the Respondent-Municipal Corporation issued a

notice revoking the 50 days’ time earlier granted to file

objection on the decision of the Technical Advisory Committee,

since the Technical Advisory Committee had declared the structure

to be of C-1 category.

21. On 02.02.2020, a notice under Section 354 of the Municipal

Corporation Act was issued to the Appellant and to the tenants
7

including the Respondent No.1 directing them to vacate the

buildings in question. Thereafter, on 09.07.2020, the Appellant

sent letters to all the tenants including the Respondent No.1

informing them of the Technical Advisory Committee Report and

requesting them to vacate the premises in question. The

Respondent No.1 however filed writ petition WP-LD-VC- No.163 of

2020 challenging the notice issued by the Respondent-Municipal

Corporation under Section 354 of the Municipal Corporation Act.

22. On 29.9.2020, M/s Shetgiri and Associates, Architects

submitted a report to the effect that the life of the structure

could be enhanced for further 5 to 6 years after repairs, subject

to the condition of monitoring and periodic maintenance every

year.

23. On 24.11.2020, a Division Bench of the Bombay High Court

passed the impugned order granting liberty to the Respondent No.1

to commence the work of removal of adjoining wall with the

assistance of M/s Shetgiri and Associates, Architects, at his own

risk and costs. The said work was however to be carried out in

the presence of the officials of Corporation.

24. In our considered view, the High Court has committed a

serious error in directing removal of a wall with the assistance

of M/s. Shetgiri and Associates, when there were conflicting
8

reports including an earlier report of the Technical Advisory

Committee on the basis of the opinions of other Architects,

declaring the building to be of the C-1 category.

25. Even the Report of Shetgiri and Associates, relied upon by

the Respondent No. 1, provided: –

“13. Brief Description of Repairs
to be done: (c) External Plaster External Plaster &
Structural repairs:
External Plaster to be
replaced with new
plaster.

(d) Structural Repairs Structural Repairs:

Damaged Structural
members like load
bearing walls and its
plaster, brick pillars,
beams and slabs, where
ever exists, should be
strengthened and its
repairs should be
carried out immediately.

The said structural
repairs should be
carried out as per the
direction and under the
supervision of
registered structural
engineer.

14. Conclusions of Consultants- The structure has
suffered damages to the
external walls & RCC
elements at various
locations.
9

Leakages/capillary action
on external wall is due
to sub soil water
pressure. The said
external walls should be
repaired immediately with
PCC bedding and damp-
proof course under it so
as to protect it from sub
soil action. During the
course of repairs,
propping and barricading
is to be provided.
Damaged Structural
members like load bearing
walls and its plaster,
brick pillars, beams and
slabs, where ever exists,
should be strengthened
and its repairs should be
carried out immediately.
The said structural
repairs should be carried
out as per the direction
and under the supervision
of registered structural
engineer.
Many of the observations
mentioned above needs
immediate attention. Any
further delay even if
marginal to initiate the
major restoration and
repair works could lead
to a part or complete
failure and leading to
mishaps, even without
warning signals. This
could be serious & fatal
to both the occupants of
the building structure as
well as the passerbye’s
(sic passers by) in close
proximity to the
structure.”

26. It is well settled that the High Court exercising its
10

extraordinary writ jurisdiction under Article 226 of the

Constitution of India, does not adjudicate hotly disputed

questions of facts. It is not for the High Court to make a

comparative assessment of conflicting technical reports and decide

which one is acceptable.

27. Moreover, the High Court has overlooked the Notes and

Limitations mentioned in the report of Shetgiri and Associates,

set out hereinbelow:

“1) The report is based on visual inspection done as on
date, of an accessible area and data provided by client
and ND tests results. This report serves a basis of
preliminary health heck-up of structure and should not be
treated as stability certificate of the building.
2) ……..

3) Inspection of Substructure was not possible and
hence condition of structure below plinth cannot be
commented on.
4) The observations made in Structural Audit Report are
made during the time of Audit. We shall not be held
responsible for any changes in Structural condition and/or
damages to the structure and/or overloading, at any point
of time in case observed.
5) It is requested that the concerned authority must
carry out regular maintenance of the structures, sewer
lines & premises to avoid any further severe damage to the
structure at a later stage.
6) ……..

7) It is extremely important to add here that the
11

structure is almost more than 45 years old and has majorly
outlived its economic life. In olden days, especially in
1900’s, the Indian Standard codes were basic in nature as
compared with what is adopted in the present time. Even
if the decision of restoration is adopted, uplifting the
structure to an extent that it would be at part with
modern structure’s in terms of the strength, design &
safety standards and also the I.S codal provisions
especially seismic and wind analysis would be practically
ruled-out and possible only if entire structural
upliftment is carried out within each and every corner of
the structure, which is extremely difficult in case of
repair works considering the massive repairs cost
involved. Moreover, the foundations of the structure
cannot be restored.
8) ……..

9) The report is only limited to the captioned suit
building and no other Flat/s, building, structure or Plot
of land, premises, room, unit, site, area, division, sub-
division or any other surrounding area of the plot or
structure has been given any weightage or has been covered
in the report.
10) The documents presented before us, if any, are
considered while furnishing the said report as mentioned.
However, the supporting underlying documents, which are
not mentioned in our report and unknown to us, could not
be examined or analyzed. As such, our report is based
only on the documents if any perused by us and not on any
underlying supporting documents if any, not produced
before us.”

28. The High Court grossly erred in law as well as facts in
12

passing the impugned judgment and order overlooking the fact that

the report of Shetgiri and Associates was not a certificate of

stability as stated in the report itself in Note 1, extracted

above.

29. It is not understood how the High Court could have been

satisfied that the stability of the building could be restored by

repair in the manner directed. The High Court patently erred in

passing the impugned order. The impugned order cannot be

sustained.

30. It is recorded that the appellant being the land lord has

given a proposal to the Respondent No.1, similar to the proposal

offered to the other tenants. The proposal, as contained in

Annexure P-6 to the Additional documents filed on behalf of the

appellant, which is a very reasonable proposal, is extracted

hereinbelow for convenience: –

“A) I am the owner of the property which is
subject matter of the Special Leave
Petition No. 1837 of 2021 before the
Hon’ble Supreme Court of India. The
respondent No.1 is the occupant/tenant of
the room no.21 admeasuring 28 sq. Mtr. As
per the area statement issued by the MCGM.

B) Now the MCGM have issued orders dated
02.07.2020 to the owner and the Respondent
No.1 along with all other tenants /
occupants in the building to vacate their
houses and evict the building on the
Subject Property.
13

C) As per the area certificate issued by the
MCGM, it has protected the area of the
Respondent No.1 and all other tenants.

D) It is to be noted that out of 24 tenants,
15 tenants have executed letter of consent
with the petitioner owner and have already
vacated their subject premises. Out of 24
tenants, 15 tenants have entered in to MOU
with the petitioner for accepting the
alternate accommodation and undertaking to
vacate the subject premises.

E) In view of the aforesaid, Respondent No.1
should immediately hand over the possession
of its subject house to the Petitioner so
that the MCGM can demolish the subject
property and petitioner can start the
process of redevelopment of the subject
property.

F) I as the owner of the subject property
assure and undertake as under:-

1. that I am accepting Respondent No 1
as a legal tenant.

2. I undertake that “Subject Property”
will be redeveloped after all the
tenants have been evicted from their
rooms. I undertake that I will try
to complete the redevelopment work of
the new building to be constructed on
the Subject Property within 2 years
from the date of receipt of the
Commencement Certificate for
redevelopment. However, in the
event, if I could not complete the
project within 2 years because of the
natural calamities or the reasons
beyond the control of the petitioner,
in that event, I undertake to pay
rent/transit accommodation as per the
choice of the respondent No.1 till
the project the completed and
competition certificate is issued by
the appropriate authority.

3. I undertake that I will provide
14

monthly rent at the rate of Rs.18 per
sq. ft. X authorised/legal area of
the subject house of the respondent
no.1 from the date of vacation of the
subject house by the Respondent No.1
till receipt of the completion
certificate from the MCGM.

4. I also undertake to provide 11
months’ rent in advance by post-dated
cheques. Also, I undertake to provide
Rs.2000/- towards freight.

In the event; the respondent no.1 is
not willing to take rent as offered
in that event I undertake to provide
alternative accommodation in the
transit camp from the date of
vacation of the subject house till
the completion certificate issued by
the appropriate authority.

5. I undertake that as soon as the
construction of the proposed building
is completed and upon receipt of
Occupation Certification from the
appropriate authority, I shall give
possession of newly constructed
Alternate Accommodation flat
equivalent to the authorised / legal
area which mentioned in the ‘Area
Certificate’ and Assessment Extract
in respect of “subject house” in the
proposed building.

6. I undertake that I will be providing
newly constructed flat to the
respondent no.1 in the newly
constructed redeveloped building,
equivalent to the authorised / legal
area which mentioned in the ‘Area
Certificate’ on ownership basis and I
shall not have any right over the
said flat once it is handed over to
the respondent no.1.

7. I undertake that I will not charge
any amount from the respondent no.1
towards new Alternate Accommodation
15

which is to be provided in the
proposed building.

G) I have already submitted the proposal
before the competent authority for the
redevelopment of the subject property and I
am awaiting for the approval.

H) I assure that all the permissions & no-
objection certificates required for the new
building under this redevelopment as well
as all legal action will be taken by me.

I) I assure that no legal charges, stamp duty,
registration fee & other charges will be
levied to Respondent No.1 for all
redevelopment costs and the full cost will
be borne by me.

J) For this redevelopment, the deposit amount
for water tax, property tax & sewerage tax
will be paid by me up to obtaining
Occupation Certificate.

K) I guarantee that I will pay extra rent for
the extra time taken for redevelopment due
to natural calamities, strikes, and other
reasons.”

31. In terms of the aforesaid proposal, the Appellant is to

provide area equivalent to the area now under occupation of the

Respondent No.1 after demolition and reconstruction of the

building, on ownership basis free of charges. In the

interregnum, the Appellant shall provide monthly rent @ Rs.18/-

per sq. mtr for area corresponding to the authorized legal area,

now in occupation of the Respondent No.1, from the date of

vacating till the date of completion certificate. Eleven months’

rent shall be given in advance by post-dated cheque.
16

32. In addition, the appellant also undertakes to provide

Rs.2000/- towards freight charges. In the event, the Respondent

No.1 is unwilling to accept the rent, the appellant undertakes to

provide alternative accommodation in a transit camp, from the date

of vacating of the premises in question till the issuance of

completion certificate by the appropriate authority. Needless to

mention that the appellant shall abide by the conditions of the

offer, if the Respondent No.1 agrees to accept the same.

33. The appeal is, accordingly, allowed, for the reasons

discussed above. The impugned final judgment and order is set

aside and the writ petition is dismissed.

34. All interim orders stand vacated.

35. Pending applications, if any, stand disposed of accordingly.

………………………………………………………,J.
[INDIRA BANERJEE]

………………………………………………………,J.
[V. RAMASUBRAMANIAN]
New Delhi;
July 20, 2021. 17

ITEM NO.2 Court 10 (Video Conferencing) SECTION IX

S U P R E M E C O U R T O F I N D I A
RECORD OF PROCEEDINGS

Petition(s) for Special Leave to Appeal(C) No(s). 1837/2021

(Arising out of impugned final judgment and order dated 24-11-
2020 in WP-LD-VC No. 163/2020 passed by the High Court of
Judicature at Bombay)

SHUBHAS JAIN Petitioner(s)

VERSUS

RAJESHWARI SHIVAM & ORS. Respondent(s)

(IA No. 14675/2021 – EXEMPTION FROM FILING AFFIDAVIT
IA No. 13133/2021 – EXEMPTION FROM FILING C/C OF THE IMPUGNED
JUDGMENT
IA No. 13134/2021 – EXEMPTION FROM FILING O.T.
IA No. 14673/2021 – PERMISSION TO FILE ADDITIONAL
DOCUMENTS/FACTS/ANNEXURES)

Date : 20-07-2021 These matters were called on for hearing today.

CORAM : HON’BLE MS. JUSTICE INDIRA BANERJEE
HON’BLE MR. JUSTICE V. RAMASUBRAMANIAN

For Petitioner(s) Mr. Dilip Annasaheb Taur, AOR

For Respondent(s) Mr. Preteesh Kapur, Sr. Adv.
Ms. Vishakha, Adv.
Mr. Karthik Rajshekhar, Adv.
Mr. Atul Kumar, AOR

Mr. Siddharth Bhatnagar, Sr. Adv.
Ms. Pallavi Pratap, Adv.
Ms. Aruna Savla, Adv.
For M/S. Pratap And Co., AOR

UPON hearing the counsel the Court made the following
O R D E R
18

Leave granted.

The appeal is allowed for the reasons discussed in the signed

non-reportable judgment. The impugned final judgment and order is

set aside and the writ petition is dismissed.

All interim orders stand vacated.

Pending applications, if any, stand disposed of accordingly.

(GULSHAN KUMAR ARORA) (MATHEW ABRAHAM)
AR-CUM-PS COURT MASTER(NSH)

(SIGNED NON-REPORTABLE JUDGMENT IS PLACED ON THE FILE)

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.