caselaws.org

Supreme Court of India
State Of Haryana vs M/S. Shiv Shankar Construction … on 14 December, 2021Author: M.R. Shah

Bench: M.R. Shah, Sanjiv Khanna

REPORTABLE

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS.7379­7380 OF 2021

State of Haryana ..Appellant (S)

VERSUS

M/s. Shiv Shankar Construction Co. & Anr. ..Respondent (S)

JUDGMENT

M. R. Shah, J.

1. Feeling aggrieved and dissatisfied with the impugned

judgment and order dated 03.11.2015 passed by the High

Court of Punjab and Haryana at Chandigarh in FAO No.

4482 of 2011 (O&M), by which the High Court has dismissed
Signature Not Verified

Digitally signed by R
Natarajan
the appeal preferred by the appellant herein under Section
Date: 2021.12.14
16:41:24 IST
Reason:

1
37 of the Arbitration and Conciliation Act, 1996, the State of

Haryana has preferred the present appeals.

2. At the outset it is required to be noted that while issuing

notice in the present appeals, this Court has stayed the

award exceeding Rs.1,03,50,263/­ insofar as claim Nos.1

and 8 are concerned.

3. The facts leading to the present appeals in a nutshell are as

under:­

3.1 That the appellant herein awarded the contract to respondent

No.1 herein – contractor for strengthening, up­gradation and

maintenance of road from Palwal to Hasanpur, Haryana for a

length of 31.17 kilometres on certain terms and conditions as

per the contract entered into between the parties. The

contract was for Rs.5,26,59,688/­. That as per the design

calculation data, the specifications as prepared by the

appellant department were meant for 3364 traffic intensity

PCU (Passenger Car Unit)/day. The contract was up to

31.05.2010. That on 05.03.2005 due to the closing of the

Palwal Aligarh Road on account of the construction of the

railway bridge, the entire traffic was diverted from Palwal
2
Aligarh Road to the present road. That due to this diversion

of traffic from Palwal Aligarh Road, heavy traffic of 24418

PCUS per day was plying on the road as against the design of

3364 PCUS per day, which damaged the road. That according

to the contractor – respondent No.1 herein, he was required

to do heavy repair by incurring additional expenditure.

Disputes arose between the parties. A legal notice was served

upon the appellant making the claims. Disputes were not

resolved and therefore respondent No.1 – contractor invoked

the arbitration clause as per clauses 24 & 25 and

approached the High Court for appointment of an arbitrator

in exercise of power conferred under Section 11 (6) of the

Arbitration and Conciliation Act, 1996.

3.2 Vide order dated 23.04.2007, the High Court appointed Shri

R.S. Jindal, retired Chief Engineer, Delhi Development

Authority as the sole Arbitrator to adjudicate upon all the

disputes between the parties. That the contractor submitted

various claims including claim Nos. 1 and 8. For the purpose

of deciding the present appeals, claim Nos.1 and 8 are

relevant. The sole Arbitrator awarded a total sum of

Rs.1,51,95,400/­ with respect to claim Nos.1 and 8.
3
4. Feeling aggrieved and dissatisfied with the award declared by

the learned Arbitrator, the appellant preferred an application

before the Court under Section 34 of the Arbitration and

Conciliation Act, 1996, which came to be dismissed against

which the appellant – State preferred an appeal under

Section 37 of the Arbitration and Conciliation Act, 1996

before the High Court. By the impugned judgment and order

the High Court has dismissed the said appeal. Hence, the

State of Haryana has preferred the present appeals.

5. Shri Shyam Divan, learned Senior Advocate has appeared on

behalf of the State – appellant and Shri Ranjit Kumar,

learned Senior Advocate has appeared on behalf of the

respondent No.1 – contractor.

5.1 Shri Shyam Divan, learned Senior Advocate appearing on

behalf of the appellant submitted that the appellant has

already paid to respondent No.1 – contractor an amount of

Rs.1,03,50,263/­ pursuant to the interim order dated

26.08.2016 passed by this Court.

4
5.2 Shri Shyam Divan, learned Senior Advocate appearing on

behalf of the appellant has submitted that the arbitral award

is liable to be set aside on the following grounds:­

(i) The award is in excess of claim;

(ii) The Arbitrator exceeded the scope of reference;

(iii) The Arbitrator has rewritten the contract with respect to

the amount payable which was specified in the contract.

5.3 Now, so far as ground No.1 that the award is in excess of

claim, it is vehemently submitted by Shri Shyam Divan,

learned Senior Advocate appearing on behalf of the appellant

that the contractor in its statement of claim had claimed an

amount of Rs. 1,03,50,263/­ only under the claim Nos.1 and

8. It is submitted that despite the above the Arbitrator has

awarded a total sum of Rs.1,51,95,400/­, which is in far

excess of amount claimed. It is submitted that the statement

of claim was never modified by the contractor and therefore,

the Arbitrator ought not to have awarded the sum/amount in

excess of the amount claimed.

5
5.3.1 It is submitted that the differential amount of

Rs.48,45,137/­ is in excess of claim and to that extent the

arbitral award is invalid and liable to be set aside. Reliance

is placed on the decision of this Court in the case of ONGC

Ltd. v. Off­Shore Enterprises Inc., (2011) 14 SCC 147

(para 16).

5.3.2 It is submitted that as held by this Court in the cases of

Associate Builders v. Delhi Development Authority,

(2015) 3 SCC 49 (para 36) and J.C. Budhraja v.

Chairman, Orissa Mining Corpn. Ltd. & Anr., (2008) 2

SCC 444 (para 31­32), making an award in excess of claim

is clear cut an act exceeding the jurisdiction and amounts

to a misconduct of the Arbitrator.

5.4 Now, so far as ground No.2 namely, that the Arbitrator

exceeded the scope of reference, it is contended that the

Arbitrator cannot exceed the scope of reference.

5.4.1 It is submitted that the contractor invoked the arbitration

clause on 06.03.2006. The High Court appointed the sole

6
Arbitrator on 23.04.2007 and the Arbitrator entered upon

reference on 19.05.2007. It is urged that by allowing the

claims for a period beyond 19.05.2007, the Arbitrator

exceeded the scope of reference.

5.4.2 It is submitted that an amount of Rs.57,96,000/­ (approx.)

has been awarded for claims arising between 19.05.2007 to

31.07.2008 (calculated as amount for maintenance of road

@ Rs. 45,000/­ per kilometre (km) per month). It is

submitted that it was not permissible for the Arbitrator to

exceed the scope of the reference beyond the date upon

entering reference and as a consequence the award is liable

to be set aside.

5.4.3 Learned senior counsel appearing on behalf of the

appellant has relied upon the decisions of this Court in the

cases of Indian Aluminium Cables Ltd. v. Haryana State

Electricity Board, 1996 (5) SCALE 708 (para 2) and MSK

Projects India (JV) Ltd. v. State of Rajasthan & Anr.

(2011) 10 SCC 573 (para 15), in support of his above

submissions that as the Arbitrator exceeded the scope of

reference and hence the award is liable to be set aside.
7
5.5 In so far as the ground No.3 is concerned namely, the

Arbitrator has rewritten the contract with respect to the

amount payable which was specified in the contract, it is

submitted that the Arbitrator has rewritten the terms of the

contract by directing the appellant to pay the compensation

to respondent No.1 – contractor at the rate of Rs.45,000/­

per km per month instead of mutually agreed contractual

rate of Rs.1,000/­ per km per month. It is contended that it

was not open to the Arbitrator to rewrite the terms of the

contract and award the contractor a higher rate for the work

than the rate which was already fixed in the contract. It is

submitted that such an exercise is beyond the competence

and authority of the Arbitrator. Reliance is placed on the

decision of this Court in the case of Satyanarayana

Construction Company v. Union of India and Others

(2011) 15 SCC 101 (para 11).

5.6 It is further contended by Shri Divan, learned Senior

Advocate appearing on behalf of the appellant that even

otherwise, the amount awarded by the Arbitrator at

8
Rs.45,000/­ per km per month beyond the time period of

additional traffic i.e. from 31.07.2008 to 31.05.2010 i.e. till

the end of contract is wholly impermissible. It is submitted

that diversion of traffic on 9.2 km stretch of the road which

gave rise to the cause of action ceased to exist w.e.f. January

2008. It is submitted that however, the Arbitrator has

directed the appellant to make payment at Rs. 45,000/­ per

km per month even beyond the time period of additional

traffic. It is contended that the aforesaid is wholly

impermissible.

6. Making the above submissions, it is prayed to allow the

present appeals.

7. Shri Ranjit Kumar, learned Senior Advocate appearing on

behalf of respondent No.1 – contractor, has vehemently

contended that the award passed by the Arbitrator cannot be

said to be (i) in excess of claim; (ii) exceeding the scope of

reference and (iii) rewriting the contract with respect to the

amount payable which was specified in the contract, as

submitted on behalf of the appellant. It is submitted that in

the statement of claim the contractor specifically stated that

9
the amount has been worked out up to the month of May,

2007 and the details of expenditure beyond May, 2007 will be

submitted during the course of hearing. It is therefore

submitted that it cannot be said that claim Nos.1 and 8 were

restricted to Rs. 1,03,50,263/­ only. It is urged that on

appreciation of the evidence on record the Arbitrator has

awarded Rs. 1,51,95,400/­ for claim Nos.1 and 8, which in

any case cannot be said to be beyond the amount claimed in

the statement of claim.

7.1 It is next contended that it also cannot be said that the

award passed by the Arbitrator was beyond the scope of

reference. It is submitted that as such cause of action to

claim the additional amount arose due to over­expenditure

owing to maintenance of road due to diversion of traffic from

Palwal Aligarh Road to the present road which continued

even beyond 06.03.2006 and/or 23.04.2007 and 19.05.2007.

It is submitted that the amount awarded by the Arbitrator

under claim Nos.1 and 8 cannot be said to be exceeding the

scope of reference.

10
7.2 It is further submitted that even the award passed by the

Arbitrator to make payment at Rs.45,000/­ per km per

month cannot be said to be rewriting of the contract with

respect to the amount payable which was specified in the

contract. It is urged that at the time when the contract was

written/entered into between the parties the contract rate of

Rs.1,000/­ per km per month was agreed against the design

of 3364 PCUS per day. However, after the contract was

entered into and the contractor acted as per the contract

there was diversion of traffic from Palwal Aligarh Road to the

present road and the heavy traffic of 24418 PCUS per day

was plying on the road as against the design of 3364 PCUS

per day and therefore the contractor was required to incur

additional expenditure at Rs.45,000/­ per km per month. It

is submitted that the amount awarded by the Arbitrator at

Rs.45,000/­ per km per month cannot be said to be rewriting

the contract with respect to the amount payable than what

was specified in the contract i.e. Rs.1,000/­ per km per

month.

7.3 However, Shri Ranjit Kumar, learned Senior Advocate

appearing on behalf of the contractor is not in a position to
11
justify the award by which the Arbitrator has awarded the

payment at Rs.45,000/­ per km per month even beyond the

time period of additional traffic i.e. up to 31.05.2010 i.e. till

the end of the contract.

8. We have heard the learned senior counsel appearing on

behalf of the respective parties at length and given our

thoughtful consideration.

9. That the contractor was awarded the contract for

maintenance, etc. The contract amount was for

Rs.5,26,59,688/­. The rate of maintenance of the road as

accepted was Rs.12,000/­ per km per annum or Rs.1,000/­

per km per month. The maintenance contract was valid up to

31.07.2010. When the contract was entered into, the

contract was meant for only 3364 PCUS per day. However,

due to diversion of traffic from Palwal Aligarh Road to the

present road, the contractor was required to incur additional

expenditure on the maintenance due to increase in the traffic

and plying the additional commercial vehicles. Therefore the

contractor claimed the amount towards additional

expenditure for maintenance which was due to increase in
12
the traffic and plying more commercial vehicles. On

appreciation of evidence the Arbitrator has determined the

loss at Rs.45,000/­ per km per month (claim Nos.1 and 8).

9.1 The case on behalf of the appellant that as in the statement

of claim, the claimant claimed an amount of

Rs.1,03,50,263/­ under the claim Nos. 1 and 8 and the

Arbitrator has awarded Rs.1,51,95,400/­, the same is in far

excess of amount claimed and therefore the award is in

excess of amount claimed has no substance. When the

statement of claim submitted by the contractor is seen, it is

specifically stated by the claimant that the amount of

Rs.1,03,50,263/­ has been worked out up to May, 2007 and

the details of expenditure beyond May, 2007 will be

submitted during the course of hearing. It is specifically

stated that expenditure incurred up to May, 2007 works out

to Rs.1,03,50,263/­. Therefore, the amount awarded by the

Arbitrator cannot be said to be in excess of the claim.

9.2 Now so far as the submission on behalf of the appellant that

the Arbitrator exceeded the scope of reference while awarding

an amount beyond 19.05.2007 – the date on which the High
13
Court appointed the sole Arbitrator is concerned, the same

has no substance. The case on behalf of the appellant that

the Arbitrator ought to have restricted the claim either up to

06.03.2006 – the date on which the contractor invoked the

arbitration clause or 23.04.2007, the date on which the High

Court appointed the sole Arbitrator or at least up to

19.05.2007 – the date on which the Arbitrator entered into

reference, is concerned, it is required to be noted that the

claim made by the Arbitrator was till the traffic was diverted

which was up to January, 2008. Therefore, the Arbitrator

was justified in awarding the amount beyond the aforesaid

periods and till the additional traffic was diverted due to the

closure of Palwal Aligarh Road.

9.3 Now the submission on behalf of the appellant is that by

awarding Rs.45,000/­ per km per month the Arbitrator has

rewritten the contract with respect to the amount payable

than what was specified in the contract. It is urged that

under the contract mutually agreed contractual rate was

Rs.1,000/­ per km per month and therefore any amount

higher than Rs.1,000/­ per km per month is beyond the

terms and conditions of the contract, is also without
14
substance. It is noted that at the time when the contract was

entered into the mutually agreed, the rate fixed was

Rs.1,000/­ per km per month and the estimated traffic was

3364 PCUS per day. The cause of action arose subsequently

due to diversion of traffic from Palwal Aligarh Road and

plying of more heavy vehicles due to which the contractor

was required to incur additional expenditure for maintenance

of the road. Therefore, the contractor was entitled to the loss

on account of the additional expenditure incurred for

maintenance of the road due to increase in the traffic

because of the closure of the Palwal Aligarh Road and

diversion of the traffic to the present road. Therefore, by no

stretch of imagination it can be said that there was rewriting

the terms of the contract as submitted on behalf of the

appellant.

9.4 In view of the above findings, none of the decisions of this

Court relied upon by the learned senior counsel appearing on

behalf of the appellant are applicable to the facts of the case

on hand as the same are not of any assistance to the

appellant.

15
9.5 However, at the same time Shri Divan, learned Senior

Advocate, appearing on behalf of the appellant is justified in

submitting that the Arbitrator ought not to have awarded an

amount of Rs.45,000/­ per km per month beyond the time

period of additional traffic. The Arbitrator has awarded the

loss/amount at Rs.45,000/­ per km per month up to

31.05.2010 i.e. till the end of the contract which is wholly

impermissible diversion of the additional traffic ceased to

exist w.e.f. January, 2008. Therefore, the Arbitrator ought

not to have awarded any amount beyond the above time

period beyond January, 2008. To that extent the award

passed by the Arbitrator can be said to be perverse and to

that extent the present appeals are required to be allowed.

10. In view of the above and for the reasons stated above, the

present appeals are allowed in part. The award passed by the

Arbitrator awarding the amount/compensation at

Rs.45,000/­ per km per month up to January, 2008 under

claim Nos.1 and 8 is hereby confirmed. The award passed by

the Arbitrator awarding the amount/compensation at

Rs.45,000/­ per km per month from February, 2008 to

31.05.2010 i.e. till the end of the contract is hereby quashed
16
and set aside. The amount due and payable has to be worked

out accordingly. The present appeals are partly allowed to the

aforesaid extent. In the facts and circumstances of the case

there shall be no order as to costs.

…………………………………J.
(M. R. SHAH)

…………………………………J.
(B.V. NAGARATHNA)

New Delhi,
December 14, 2021.

17

Comments

Leave a Reply

Sign In

Register

Reset Password

Please enter your username or email address, you will receive a link to create a new password via email.